Hi PP Experts,
My client has the following requirement,
Two Plants exists Plant A and Plant B. Plant A centrally handles purchasing from external vendors. Material usage happens from both the plants (for Projects in PS). Material required for Plant B are requested from Plant A and transfered via or:red}Stock Transport Orders. The total material requirement (for Plant A and B) are centrally procured from Plant A then stored and dispatched as and when requested by Plant B. We use MRP for material planning.
I want to configure the system in such a way that when I run MRP for Plant B stock Tranasport Orders (or Requisitions) are created at Plant B to get goods from Plant A. When MRP is run for Plant A it should creat PR s for external vendors considering the Plant B requirement as well.
Please guide me on this.
Cheers
Deepal

Hello,
define a special procurement key for your product that is in plant B.
The special procurement key should say that it is a stock transfer (U) from plant A.
(in customising==> Production / MRP / Master data / define special procurement key
then assign that key to your products in plant B (in the MRP2 screen of the materials).
Any requirements in plant B tha are not covered by the stock on hand will be passed on to plant A.
Hope it helps.
Edited by: Pascal on Jul 31, 2009 2:10 PM

Similar Messages

  • Purchase Order is generated after MRP for Material with MRP Type ND

    Hi Everyone,
    Material type := HAWA
    My material procurement type = F i.e. External Procurement.
    MRP Type = ND in Production server , and VB in Quality
    Lot Size = EX
    Material Status :- 15 Pre-release both for Quality and production server
    The Material is bulk material and bulk material indicator is set.
    Purchasing View is also maintained for the same.
    Planning Strat = Z5 Company specific
    Special procurement key:- Z7 Company specific
    I am running MD02 with following parameters.
    Create Pur Req =1, PR
    Create MRP List = 1, MRP List
    Delivery Schedule = 3, Schedule Lines
    Planning Mode = 2 Re- Explode BOM & Routing
    Scheduling = 1
    Issue:
    After MRP run, system is  generating PR, Though with MRP type ND purchase requisition should not be generated.
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.
    After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    We havent been able to locate the root cause so far
    Please guide us
    Thanks in Advance,
    Ayaz
    Edited by: Ayaz Alam Khan on Feb 16, 2011 2:41 PM

    IF the material is ND, system won't Run MRP for the material
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    There is no link
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    system will read the X plant  material status or plant specific material status first and then only system will read MRP type

  • Cross Plant Planning for External procured Material in MRP with their stock

    Dear Gurus,
                 I have one requirement my client want Cross plant planning in MRP. this plants are only site plants no Manufacturing. All materials in these plants are Externally Procure Materials(F). Now they want cross plant planning  for Externally Procure Materials or cross plant planning  for Externally Procure Materials  with consider all plant stock details while planning.
            can you tell me procedure for this,
    Thanks in advance,
    Regards,
    Devraj

    Hi,
    In R/3 you cannot consider all plants in planning, you have to use SAP APO to achieve your goal (if your goal is to optimize the procurement in your plants). When you execute MRP run in R/3 it will only consider the details of one single plant.
    I mean if you have several plants used for external procurement, and you want to make an optimal decision considering all the stocks and open transactional data, requirements in those plants, it is not possible in R/3 as per my knowledge - multi site/plant planning won't give you such optimal solutiion.
    http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d2d4d44af11d182b40000e829fbfe/frameset.htm
    http://help.sap.com/saphelp_apo/helpdata/en/7e/63fc37004d0a1ee10000009b38f8cf/frameset.htm
    Regards,
    Csaba
    Edited by: Csaba Szommer on Nov 17, 2008 10:27 AM

  • Inter company PR through MRP Execution

    Hi Guys ,
    Greetings!
    How to get Inter company PR through MRP Execution
    Note: i have done required configuration setting in MRP  still i am unable to get the same.
    Thanks in advances
    Regards:
    xxxxxxx

    Hi Tata,
    Say Plant X supplies to Plant Z and they belong to different company codes,
    Create a special procurement key in plant X using transaction "OMD9". The key should be a copy of "40" or it self with defination that Plant Z as Special procurement plant.
    Assign this special procurement key to material master in Plant X- MRP2 view, and in plant Z the defination of this material should be "E" - Inhouse production with BOM & Routing for production.
    You should also setup the customer and assign that in the shipping data for plants in the mm-sto settings of SPRO. Here you also need to maintain the delivery/billing type and availability checks.
    With this settings now if a Stock Transfer PO is created in Plant X againsts Plant Z or if a demand exists for the material in Plant X, the requirement is transfered to the plant Z and planned order is created for the same after MRP run based on the MRP parameters set in the material master in Plant Z.
    Once GR is done with referance to the STO in Plant Z and PGI is carried out.
    Once the material is recieved in Plant X, GR is created for the STO. This completes the logistic cycle.
    Thanks
    Bala

  • MRP area for running a sale order MRP

    Hello PP experts,
    I come across a scenario where , I need to do the  MRP run for sale order in a MRP area. I have checked , I can put PIR with respect to MRP AREA , but when I open MD50 screen for running MRP for sale order. I did not found the MRP AREA
    field in the screen.
    In short , my question is , How the sale order MRP run ,  system will do in a MRP
    area defined for the material ?
    Here , I have already defined the material is MRP AREA and also I have created
    MRP area segment in the material master.
    I have also configured the MRP area in SPRO.
    Waiting for your reply.
    Regards,

    Hello ,
    Thanks for reply.
    I am using plant MRP area. For FERT , I am using make to order strategy 20.
    I want to specify the real problem. It is like below.
    Suppose 'A ' is sumassembly goes to a variant configured MTO KMAT say 'V'.
    The same 'A'  subassembly is a child for a make to stock FERT say ' S'.
    Presently  using strtegy 11 for MTS fert 'S' and 10 for the subassembly ---'A'.
    Now the planner want to plan for the subassembly.
    He is putting the PIR for the subassembly as sales order is not availble and he is putting the PIR for FERT 'S'.
    When sales order is coming then additinal quantity planning is happening.
    So I suggested to use the strategy 70 for subassembly 'A' , so the sales order (of 'V') OF  quantity will be offset for the PIR of the SUBASSEMBLY 'A'.
    But the consumption of PIR of 'A' will  be apllicable to MTS  FERT that is 'S'.
    So how can we prevent the system from offsetting the dependent requiremet triggered from the PIR of 'A'.
    That means the consumption  (that is the usage of stategy 70) of the FERT requirement should only work for ' A' and sales order based KMAT 'V'.
    The same offseting should not work for subassembly 'A' and MTS FERT 'S'.
    For for Make to order KAMT 'V' , if I use MRP area and do the sales order planning in MRP area. Will I get the desired result ?
    Waiting for reply.
    Regards,
    Ravindra

  • Inter-plant planning in REM

    Hi i need some suggestions for inter plant planning in REM before mapping in SAP.
    Our Scenario is Repetitive manufacturing and we have 2 plants which have 3 assemblies in each plant in case of discrete/process scenario with using special procurement key we can do inter plant planning but in case of REM SAP HELP suggest its not possible but don't understand why it is so?
    please refer this link : http://help.sap.com/saphelp_46c/helpdata/en/70/442986c48d11d1b59d0000e82d81c3/frameset.htm.
    So i want some suggestions from  any one you who might have already experienced this scenario to map in SAP.
    As i understand this can be achieved by MRP at 2 plants or with scope of planning apart from these is there any other way which can be simplified the task.
    Cheers
    KK
    Edited by: kiran kumar on Feb 7, 2011 4:54 PM

    On which version are you working?
    ECC6
    Have you tried the Inter-plant planning in REM If yes then what the error are you getting?
    No i haven't tried this scenario will try and update mean while i want some inputs from any one who might have already experienced this scenario.
    It s possible a stock transfer of the production plant may also be executed to the plant of the sales order also.
    Could you please elaborate more what do you mean by this statement?
    Cheers
    KK

  • Delivery from one plant taking order of another plant

    Hi,
    Please share your view that how it is possible to delivery from one plant taking the order from another plant where production is made in later plant and material is moved by STo to the first plant for despatch.
         So stock is ready in first plant but since the order is of second plant , if we bypass the first phase check in shipping point while create delivery by VLO1N , inside the document the second plant is determined. is there any way around?
    Please explore.
    Regards
    Indranil Saha

    Dear Lakhsmipathi,
    Thnaks for your reply . I will Definitely close the open issues later.
       There is no problem about STO. Problem is that we have to issue the sale order in manufacturing plant and with respect to the same order we have to make the delivery by VL01N from another plant. So MRP will run in manufacturinf plant. Stock will built up in manufacturing plant, then it will be transferred to another plant and from there the same material is to be despatched where the delivering plant in sale order is the manufacturing plant.
        SAP does not allow to do it as the delivering plnat specified in the order is different from thye plant from where it is to be despatched.
       We have thought also to create customized routine for it where we may bypass the check of shipping point in copy control as well as the population of the plant which is to be filled up manually by user in delivery document.
       Is there any other alternative . please explore.
    Regards
    Indranil

  • Inter company stock orders

    In MD04, there are many MRP elements like Cus ord, ShpgNt and so many.
    CAn anybody please tell me which elements will constitue the sales orders and which will constitute the Inter company orders..
    I am in need of developing a report which says the sales orders for a material and Inter company stock orders in seperate columns..
    Please help me out..
    THanks
    Karthick P

    My question is different..
    I just want to know which of the MRP elements will combine to form the sales orders of a material and which will combime for Intercompany atock orders...
    Karthick p

  • Goods issue for plant maintenance order

    Goods issue with ref to plant maintenance order( Componenets of the order) is not possible in transaction code MIGO. Error message " MIGO is not possible for the refurbishment order".
    Goods issue for the same order can be posted with transaction MB!A.

    hi santhosh
    kindly check the order type .i think you are using MB1A for refurbishment process.but it is not possible.only maintenance order can be posted via MB1A
    follow the procedure for goods issue in refurbishment order.
    Choose Logistics ® Plant maintenance ® Maintenance processing ® Completion confirmation ® Goods movement ® Goods movement.
    The entry screen for a goods issue appears.
    Choose the pushbutton For order.
    Enter the relevant order number in the dialog box and choose Continue.
    An entry screen appears.
    Choose Copy.
    The Maintain Serial Numbers dialog box appears.
    Choose Reference document.
    Enter the order number in the Refurbishment order group box and choose Execute.
    A list appears with the planned serial numbers for the refurbishment order.
    Check the selections of serial numbers, for whose material you want to post a goods issue, and choose Copy.
    The serial numbers are copied into the Maintain Serial Numbers dialog box.
    Choose Exit window.
    The goods issue is posted.
    regards
    thyagarajan

  • Free Goods determination -acess sequence sales org/ plant/material

    Hi
    I am trying to determine the free goods by choosing the key combination as Sales org/plant/material.
    The system is not determineing the free qty ,instead when i maintain the condition record with customer/Material key combination ,then the system is determineing the free qty.
    I also tried to put acess Sequence Sales org/plant/material above the Acess sequence customer/Material,but still the system not detrmineing the free qty in the order.
    can any one pl gide me how to solve this issue.
    regards
    shashi

    Hi
    Go to the access sequence where Sales org/Plant/Material are maintained as condition table.
    Now select the condition table and then click the node "Fields" on the left hand side of the screen.
    It may give a warning message that "Fields are not yet generated". Just ignore this and Enter once again.
    Do this until it takes you to a screen where you can see fields like KOMK-VKORG, KOMK-WERKS and KOMP-MATNR
    Now create the condition records and check in transaction by creating sales order. It shoudl work.
    Hope this helps.
    You can reward if it helps you

  • Bom explosion in sales order mrp(MD50)

    Hi Experts,
    In sales order MRP i.e. MD50 Getting the planned orders for header material(Finished goods) generated but for raw materials (BOM items) Purchase requisitions are not getting generated.
    Details:
    Header material A and raw materials B and C.
    In material B in MRP 4 coll/ind indicator is 2 And same indicator for C is blank.
    Now when we are running the MRP sales order based it will generate the purchase requisition for C only but not for B.
    In OPPQ we have done the setting for sales order BOM explosion.
    Can anyone please throw some light what is the setting missing in customization or in front end?
    Thanks in advance.
    Regards
    Vilas

    Dear,
    If you select individual requirement then system will not consider available stock and generate Proposals for every single requirments. Check in MRP4 view Individual / Collective .
    Also you will find PR and Plan order with account assignment of Sales order (in case of MD50).
    - If you select collective requirement then system will not generate planing proposals through MD50.In that case you have to go for individual MRP (MD02 / MD03)
    Please try and come back.
    Regards,
    R.Brahmankar

  • Missing Part list for Plant to Plant Purchase order

    Hi,
          I need the following requirement in CO24,
          In CO24 its shows the missing parts for Sales order, similarly we want the missing parts list for Plant to Plant Purchase order in the same report. Also the report,
    1.It  should not consider the Planned order for a sales order.
    2.It should not consider the planned order which can be convert into purchase requisition.
    3.The procurement type should be "E" or "X".
    Kindly guide me is there any standard layout changes in available or any development we have to do.
    Thanks
    Muthamil Murugan.G

    Hi Purushothaman,
    If you have the following settings in OPJK:
    Plant                 XXXX
    Order Type       XXXX
    Availability Check    2
    [X]Status Check
    [X]Check material availability when saving order (may not need)
    Checking Rule        PP PP checking rule
    Component Check Type    ATP check
    Release material     2  Release permitted despite missing parts
    Then in COHV you try to mass release the order with the following parameter:
    List: Order Header
    Selection: Your selection criteria
    Mass processing:
    Function: Release
    Max. No.of Processes 99
    Save Log: Always
    Release control order: Collective Order Release
    Then after the order is released, you can find the missing part list of that order in CO03 menu path:
    Goto->Missing Parts->Missing parts list
    Hope it helps.
    Regards,
    Rachel

  • Inter plant STO with intermediate G/L Account & profit at Plant level

    Hello Experts,
    I have a situation at a client in California. The client does Make-to-Order sales. This client has plants in several cities.
    The scenario goes like this. The plant 0020 wants to sell materials to external customer. If this 0020 plant does not have enough stock in inventory, a purchase order needs to be placed with another plant 0010 of same company code.
    I know this can be mapped with standard STO Process but client's concerns are:
    1) At the time of PGI, both stock accounts will update once.
    But he wants an intermediate G/L account as it takes 1 month to recieve goods.
    2)  Inter plant profit has to be captured.
    Example: 0020sells materials @ 120$, procures from 0010@ 100$. Actual cost of that in 0010 is 80$.
    Meaning total profit for company is 40$, 20$ each to plant 0010 & plant 0020
    Would someone please be so kind as to helpme with a Best  process flow for this scenario
    I am open to your suggestions.
    Thanks,
    Nagesh

    Hi Nagesh,
    Generally it sounds wrong; I think that businesswise it is not good practice (and in some countries even forbidden) to record a profit in a company just by moving stock around. This way we could all make millions!
    Stock price can vary from one plant to another, but then it is recorded as price difference when it moves, not profit.
    Regards,
    Mario

  • Planned Order Creation after Sale Order MRP MD50

    In a BOM of FERT material, one HALB material is present at different BOM levels. When we run sale order MRP (MD50), system will create one planned order for complete quantity (total qty of HALB material at all  levels put together). Is there any way, so that system will create different planned orders for the same material present at different levels ?

    Hi,
    MD50 is T code for running MRP w.r.t sales sales, During MRP run system will explode the BOM and plan the requirements for all the levels( i.e, multiple levels)
    with regards,
    P.P.Anand

  • Inter Company Purchase Orders for Asset Acquistion

    Hi Everyone,
    I need your expert help on the following business situation.
    My client has 2 company codes. Now the fixed assets have to be transferred from one company code to another by means of purchase orders being created by acquiring company. Can someone help me with the SAP process (like creation of inter company purchase order etc.) for asset transfer in this scenario.
    Thanks,
    Rohit

    Hi
    I think ur createing intercompany Stock transport order with SD involvement
    If yes then vendors are nothing to do with it
    If NO pls. elaborate ur prob.
    Pls check have u done following configutarion for STO
    SPRO --> MM --> Purchasing --> PO --> Set up Stock transport Order --> Define Shipping data for plants.
    Here  maintain, the cusomer, Sales Organization , Distirbution channel and the division combination.
    Also in the Assign delivery type and checking rule node,  maintain the follwing relation.
    Document type --- Supplying Plant --- Delivery type and Checking rule need to be assigned together so that you will be able to see the shipping tab in the Stock transprot purchase Order
    Vishal...