Internal Data Transfer to Funds Management - Version Management Error

Hi All,
We are trying to convert the open PO's in our system that were created before FM was implemented, and that are to be converted now before the MIGO stage.
We are using the following steps:
1) Select the document
2) Convert the worklist.
We had done the first step, and faced no issues. During the conversion of the worklist, we face the following error
Message ID - MEPO;Message Number - 813; Version Management of purchase order still faulty.
Message ID - MEDCM; Message Number - 4; Enter short text for version
Message ID - MEDCM; Message Number - 3; Enter reason for change for version
In the Control Data for each of the Document Type, the control data, Version Active and Version 0 OK are activated.
Can someone kindly suggest what could have possibly gone wrong here ?
Regards,
Wy

Hi All,
Just to clarify, I went through note 800784 and found that in our system
1. None of the fields - 'Reason,' 'Description,' 'Req By,' 'Req By Ext' or 'Post Date' -  is a required entry in the version management  field selection
2. None of the fields - EKPO-ELIKZ or EKPO-EREKZ or EBAKZ - are set as Version-Relevant Fields of Purchase Requisitions.
Cant figure out why I am not able to assign the fund centre and commitment item here, although I am able to perform MIGO and MIRO on that.
Regards,
Wy

Similar Messages

  • Internal Data Transfer to Funds Management

    Hello All,
    We are implementing the Funds Management in the middle of the Fiscal year, now all the settings are done and budget also uploaded.
    Now my question is How to convert the previous documents into funds management which were posted from the year starting 01.04.2008.(FI and MM documents including park documents)
    For this I am refering the following IMG steps, i.e Internal Data Transfer to Funds Management-Supplementary Account Assignment-Select Documents-Convert Worklist-Display Worklist
    Here I am unable to understand what is happening in the first step and second step
    Can any one pls clarify and give correct solution
    Regards
    Uma

    Hello Uma,
    In PSM-FM you have similar processes in two-steps (select and run), first selecting the data and after that processing the data.
    In the step "Select Documents" (step 1) you select the documents, based on your selection criteria, for which you want to provide a supplementary account assignment within your company code. The documents selected are displayed in a worklist.
    You can provide the documents with a supplementary account assignment in an additional step by converting the worklist (step 2).
    In the Convert Worklist section (step 2), you add account assignments to the documents contained in the work list (generated by the step 1) for your FM area. The documents to which an account assignment is added are displayed in a list which shows the original account assignment and the changed account assignment for each document.
    With each program run, the system assigns a run number. You can use this run number as a selection criterion for selective deletion or selective display of the work list. This is very useful if you do not want to do the running process (convert worklist) in one step, you can convert in more than one step.
    To convert (step 2) you must first have selected the documents (step 1) to which you want to add an account assignment.
    For example, you can in the step 1 select ALL the documents that you want to convert and in the step 2 you can split in more than one process (due to performance or checking reasons) the data generated in the step 1.
    The option "Display Worklist" is to check the worklist generated in the step 1 for a specific FM area based on particular selection criteria. If no data was deleted from the worklist, the worklist contains all the information on the supplementary account assignment:
    The system assigns a run number during each program run for converting the work list. You can use this number as a selection criterion when displaying the work list.
    You can display these documents by starting the program without specifying a run number.
    You can test this process with a single document in step 1 and step2 and you will see that the step 1 only makes the document as selected and the real change will happen in the step2.
    I hope I could clarify the process
    Best Regards,
    Vanessa.

  • International- Data Transfer

    Be careful about using your phone for data transfer in Europe! I Just got back from a 2-week trip to Europe with my family of four- we all brought our iPhones. I had international roaming- World Traveller- turned on before we left. I was told that phone calls would be $1.99 per minute and data transfer (Internet, email, etc.) would be unlimited because we already pay the $20 for that. It turns out it is NOT unlimited. We just got a bill for $3700. AT&T has agreed they told us wrong and they will credit our data usage charges but I'm still not sure it is really going to happen. They have since instituted a new plan something like this: International Data Transfer is about $20 per month for about 15mb of data. But there is a 1 year commitment for this plan. Hopefully, they will revise this plan to something more useful.

    Yesterday afternoon the advice I received from AT&T was to call and have the data part of the phone turned off while traveling. That would, I was told, keep me from getting a big bill. This morning I telephoned again to ask about wi fi, and was told, essentially, that if wi fi is free where I am, there would be no charge for web browsing or reading and sending email. Also, I was told that the advice I received yesterday was incorrect. The way to keep from getting the data charges that are very large is to go to mail settings and for each account, to turn it "off." That way the phone will not look for email. Presumably not clicking the Safari icon is a part of this plan. So the work around today sounds like it is to use free wi fi if you can find it.

  • Budget vs Actual data Datasource in Funds Management

    We are not able to find the correct datasource for Budget (Vs) Actual in Funds Management in R/3. We have activated most of the existing datasources and checked but could not find any data for the Value Type 'Actual'. Where can we find this?
    Thanks

    Hi,
    Look at this datasource
    0PU_IS_PS_44 Fund Assigned and Fund Consumed - R/3 Table FMAVCT
    Did you check
    0PU_IS_PS_33 - CO Line Items in Funds Management
    value type 70 - Actual and commitment.You should put restriction on 0FM_ACTDETL - Commitments and Actuals Detailing in Funds Management with values like ( 140 Invoice,110 -Transfer posting, and 160 Actual transfer)
    Regards,
    Saran

  • Fund Management Error in Billing Document

    Dear all,
    We are upgrading from 4.6 C to ECC 6.0, when i am creating service order and with reference to service order i am creating Service Invoice and save it dosenot transfer to accounting bcoz of FM account assignment is incomplete.
    I checked in Sales order at item level there is one field for Fund Management in Account Assignemnt but it is not active so i cannot enter any field.
    Can any one plz provide some solution for the same.
    Thanks & Regards,
    Pankaj

    You might want to check the account determination analysis in the document, menu Environment ->Analysis -> Account Determination. Usually the accounting information is greyed out because it's supposed to be determined automatically. Obviously, something is incorrect or missing in your system. Unfortunately, I'm not familiar with Fund Management config, you might want to ask in the industry-specific forum.

  • Funds Management Error (Message no. FI125)

    I have just configured Funds Management ( we require Cost Element Annual Business Plan Budgeting). All is working fine including availability control) When I try to test using ME21N create PO, I get the error
    "No warehouse funds center found for plant 5500/valuation class 4110."
    Message no. FI125
    We have not implemented MM at warehouse level.
    What configuration is missing, pls help.

    Hi,
    You can find some information in the SAP Knowledge Warehouse for PSM, regarding to Warehouse Concepts.
    There is some documentation available in this link:
    <a href="http://help.sap.com/saphelp_47x200/helpdata/en/f0/ca3f43260211d28a430000e829fbbd/content.htm">Funds management</a>
    I am not sure if this link will work. If it does not, you can access to the online help on:
    www.help.sap.com and then select:
    SAP R/3 enterprise release 4.70.
       English
         SAP Library
            SAP R/3 Application Components
              Financials
                Public Sector Management
                   Funds Management
                     Recording Actual and Commitment data
                       Integration with materials management
                        Integration Stock Material Procurement
    In summary, you should work on any of the proposed Warehouse scenarios in order to avoid such messages.
    I hope this helps.
    Kind regards,
    Mar

  • Global Funds Management - Error on activation

    I am trying to activate Global Funds Management functions.  However, I notice a very strange situation.  After activating it, when I try to post a FI Document, system is saying "Enter a leading ledger".  I had already defined leading and non-leading ledgers in the New GL.  If I deactivate the Global Fund Management functions again, I am able to post the document and the same error message is not appearing.

    Hello,
    Please tell me about your system condition. Is your ecc 6.0 also implement Public Sector component, and the relevant consultant already activated public sector management component in SPRO? Usually de-activate leading ledger 0L cause by activated this component.
    It is the behavior system once Global PSM -FM activated it create new total table FMGLFLEXT, and customer free to use either FAGLEFLEXT or FMGLFLEXT.
    If you want to use/activate again 0L then you can programt via SE38. Run the program FMGL_CHANGE_APPL_IN_LEDGER.
    Leading ledger 0L will come back again.
    Also you can get more information on note 840783

  • Funds Management -Error

    Hi,
    I had implemented funds management so while creating normal Purchase order for raw material system is giving below error.
    For the particular material i had maintained configuration in FMLF -warehouse integration and derivative rule=valuation class-commoitment item,GL-conmmitment item.
    Suggest something.
    Item 00010 contains commitment item with financial transaction other than 30
    Message no. FICUSTOM000
    Diagnosis
    Item 00010 contains a commitment item with <DS:GLOS.Financial transaction Financial transaction unequal to 30 (Post revenue, expenses, assets). In Funds Management (and in the Cash Management project) only postings containing the transaction 30 are updated.
    Procedure
    Check your entry and enter a commitment item with financial transaction 30.
    Regards
    Deepa

    Hi Deepa,
    Use transaction FMCIC and enter your FM area. Then enter the this committment item and check there is 30 in the Financial Transaction field. If not then make it so.
    System is causing the error because purchase order transaction is allowed for this committment type.
    By keeping financial transaction 30 will resolve the issue. You can use FMCIA to change committment item.
    If document is posted to this then you will not be able to change then it is better that you create new committment type and start posting.
    Regards,
    Chintan Joshi.

  • Fund managment error

    Dear Guru,
    In my client place they are using fund management.  While making entry  the commitment item is shown as depreciation for all expenses items irrespective of its nature. how to rectify it please  guide me to solve this issue it is very urgency
    Regards,
    Girija

    hi santhosh,
    Please tell which t code i have to check this for all expenses gl by defult the same depreciation commitment items is coming
    pl guide me.
    girija

  • Data Transfer from 4.7 version system to 6.0 version system

    Hello Experts ,
        We have our FICO system is on 4.7 version. But our HR System is on 6.0 version. FICO (4.7) system is old one with all data. And HR (6.0) is being newly implemented....
       We need some data from FI (4.7) system to HR (6.0) . In future if any changes happens in FI (4.7) system the same changes need to be done in HR (6.0) system too . For ex : If currency of particular country changed..Then as FI is imp we will make that chnage in FI box..We want to reflect the same change in HR box as well.....
      We found 2 ways for this :
    !) doing manually
    2) Doing either by transporting or using ALE /IDoc method
    We want to investigate ways to perform the same using 2 way as this is very simple. But we have doubts here... As HR is on 6.0 and FI is on 4.7 .....  Can we transport data using transports ??? (between2 different versions /??) 
    If transports are not done , then we do that using ALE/ IDocs? using IDoc's we gerenally send transctional data... This configuration settings comes under master data ... can we send this master data using ALE/ IDoc or LSMW..If yes suggest us the msg types ...or other needed info,.
    Thanks in advance. Reward points are garunteed...

    Hello Sampath,
    Yes, distribution of master data via ALE should be OK between these two systems, no problems whatsoever.
    You can use message type COSMAS to distribute cost centres for example which is necessary and is most common change scenario for both HR and FI systems. For all other message types see list of Message Types under transaction (Area Menu) WEDI.
    I think ALE should be the correct approach given your scenario.
    Hope this helps,
    Cheers,
    Sougata.

  • Can data transfer from SAP4.7 version to ECC6.0?

    Hello ABAPers,
                           I want to know is it possible to transfer the data from 4.7version to ECC6.0.
    I want to transfer the Data of a table which is there in ECC6,0 to SAP4.7.
    I am following the steps given in
    http://www.****************/Tutorials/ALE/DataDistributeCustomIDOC/page1.htm
    And one more thing i want to know is i am having 2 clients in ECC6.0 200 and 800 thing is wht ever table i am creating in 200
    it is replicating in 800 with data too. So i am confused wht to do ? can anyone suggest me the solution.

    If your table has a field named MANDT then it is client-dependent and the data will be different in client 200 and 800. If there is no field MANDT, then the data will be the same. Such table might require a transport though to update the data.
    I've never moved separate tables from one client to another (you might talk to your Basis administrator first), but it definitely is possible to exchange the data between different SAP releases. Otherwise they would be out of business already.

  • Payment Budget Exceeded in Funds Management Error BP629

    Hi All
    I am facing the Below error while doing the FB50 transaction.
    "Item 002 20020001 /EXPENDITURE payment budget exceeded"
    I have created the commitment item "Expenditure" to post the expenses to the budget.
    I have made the budget entry into the system for Expenditure as well as Revenue Commitment Item.
    I am able to post revenue posting successfully with FB50 transaction through revenue commitment item but facing the above error for expenditure commitment item.
    Regards,
    Dimpesh Ray

    Hi Dimpesh,
          Check whether the budget has been released (consumable) if you have made budget release setting in FM . If you have defined consumable budget types in Customizing, only these budget types will be considered as "releasable" budget.
    Regards,
    Lewis

  • CATS - Data Transfer to Target Components via CATA - Error "No Data for Trf

    Hello
    I am recording hours via CAT2 on Network Activity. These hours are then approved.
    However, when I run CATA to transfer the hours to CO and PS, I get popup information "No Data for Transfer".
    When i proceed further , i get another popup saying all records were read and saved successfully, and no. of confirmations generated.
    However, when i run CJI3, I do not see any Actual cost line items.
    Please help
    JG

    Hello Joy,
    (1) Perhaps you have on your profile on CAC1, the "Immediate Transfer to HR" flag set.
    This way you have the "Release on Saving" flag set, all the time you save data, it gets transferred directly.
    (2) But, I see that you are having the issue with the CO and PS, so I highly suggest you to check on if the data is on the interface tables.
      a. First you should make sure that the data exists on CATSDB with Status 30.
      b. Then, you should check the data on CATSPS (Interface table for PS) and CATSCO( interface table for CO).
      c. If you don't have the data on these tables there should be no record after all to transfer.
    Regards,
    Bentow.

  • Funds Management cut over of Open PR and PO

    Hi,
    In case of cutover, we are using following link to update FM account assignment in open PR/PO.
    SPRO>Funds Management Government>Actual and Commitment Update/Integration>Internal Data Transfer to Funds Management>Supplementary Account Assignment-->Select Documents
    and
    SPRO>Funds Management Government>Actual and Commitment Update/Integration>Internal Data Transfer to Funds Management>Supplementary Account Assignment-->Convert Worklist
    1) But in this case, for open PO of which GR is not done FMRP_RW_BUDCON report is not updated after doing above mentioned process. when I make GR, commitment get updated in FMRP_RW_BUDCON report. This does not show actual status of budget consumption as budget consumption is shown at the time of GR only.
    2) If GR is already done for PO and after doing above mentioned process, if GR get reversed then Negetive commitment shows in FMRP_RW_BUDCON report and after deletion of that respected PO, commitment of PO gets zero. But negetive GR commitment remains open which leads to wrong status of budget consumption. e.g. GR of Rs 5000 is reversed. Then report shows two documents as -5000 for GR reversed and 5000 for PO commitment getting open. IF I reversed this PO then PO commitment of 5000 become zero. but GR reversing amount -5000 still remains open. So it shows less consumption of budget by Rs.5000.
    Do I am missing any process. Suggest.

    Hi,
    Firstly, after you convert the open commitments, you'll need to run FMAVCREINIT to reconstruct AVC. FMRP_RW_BUDCON will then reflect the converted commitments.
    Secondly, based on your posting, it seems that you do not want PO commitments (VT 51) to be counted as budget consumption. You can achieve this in the ledger 9H configuration:
    Public sector management > Funds management government > BCS > Availability control > Settings for availability control ledger > Define filter settings for commitment/actual values. You will want to exclude both value type 50 and 51 from ledger 9H. After you change the setting, you will need to run FMAVCREINIT again.
    Hope this helps.
    Regards,
    Ming

  • CASH FLOW REPORT FROM FUNDS MANAGEMENT

    Hi All
      I am in the mid of BW implementation for FI and FM reports.
    As part of this i have to create CASH FLOW report..
    Currently the user using a SAP report from , Funds Management, FMEM which points to the structure IFMEISB , Cash Budget Management.
    Is there any datasource is available in FM to access this structure?
    Otherwise any body knows what are tables in FM has to be extracted for this puropes..
    Regards
    Mano

    Hi
    You can check the Financials business contect.
    Funds management
    http://help.sap.com/saphelp_nw04/helpdata/en/71/d3143cb1b8be00e10000000a114084/frameset.htm
    Have a look at these data sources:
    http://help.sap.com/saphelp_nw04/helpdata/en/b5/12163c240a9440e10000000a114084/content.htm
    http://help.sap.com/saphelp_nw04/helpdata/en/d3/29ae399c1a6651e10000000a114084/content.htm
    Data sources for funds management
    http://help.sap.com/saphelp_bw33/helpdata/en/ba/c8ad3928a07c50e10000000a114084/frameset.htm
    Regards
    Naveen
    PS: Assigning point to the helpful answers is the way of saying thanks in SDN

Maybe you are looking for