Hi
Internal Order created for Rs. 500000. While making PO against this internal order for 1 Qty and net price as 10000, it gives an error message stating that Internal order limit is exceeded.
itme 010 order 234567 budget exceeded
errro message.bp603
please help me on this
kind regards
sunitha

HI,
Budget assigned to internal order has been exceeded so you will not be able post any further transactions to internal order...
If you want to post then take approval finance department to augment (increase) the budget....if get approval from finance department the use transaction KO24 and add the budget for Internal Order...
Regards,
Chintan Joshi

Similar Messages

  • Purchase order with reference to internal order

    Dear all
    I am creating a purchase order with reference to a statistical internal order.The total PO value should not exceed the budgeted amount for that statistical internal order.How should i achieve this?
    Thanks in advance.
    Madhavi

    Hello
    First Create Budget Profile.
    Make Specification In Availability Control as Activation Type ''01- Automatic activation during budget allocation''
    Usage 100 and Tick ''Overall'' check box.
    After that Make Setting for your Controlling area in SPRO Path '' Define Tolerance Limit for Availibility control''

  • How to block entry through internal order budget in F-02

    Hi,
    Kindly tell me during Purchase order creation through internal order (Order related PO) whreas budget is maintained against that internal order if the PO amount is exceede than budgeted amount it gives warning / error messge that budget is exceeded. Same internal order or any other internal order which has budget against that internal order if I go to  F-02 tcode and pass entry with cost center and internal order(budget is given) both it does not give any warning message if budget value exceeded i.e, F-02 posted amount is greater than budgetd amount. It goes to next screen which should not do. Kindly tell me the reason why it is not being blocked and goes to next screen or if there is any configuration  please guide me.
    Best Regards,
    Samrat
    Edited by: Samrat Roy on Nov 2, 2010 11:43 AM

    Hi Eli,
    Now I have observed during saving the record in F-02 it gives warning message as per tolerance limit set in config area. Actually I want in F-02 screen when you put Document date, posting date, type, period, company code, currency, posting key(debit), GL account, next 2nd screen you mention amount, cost center, internal order(budget is maintained), posting key(credit) and press enter for next 3rd screen to put credit amount. While you go from 2nd screen to 3rd screen then warning / error message should give if amount is exceeded than budgeted amount which I am getting during saving. Is it possible to make any check between two screens ????
    Beside I would ask you here tolerance limit is set as 95%, 100% and 102%. During PO creation through internal order it gives error message when amount is exceeded than 102% as budget is exceeded. If the amount is between 95% to 99% it does not give warning message which should do. But from posting in F-02 screen it gives proper messge in all levels since 95 % to 99% and 101% to 102%.
    Regards,
    Samrat

  • SWL SC only considers partial amount of Internal Order

    Greetings, Experts.
    We are using SRM 4.0 - Classic and use Portal for creating SC.
    We have an Internal Order no. 1111 in the backend with original budget as 1000 GBP and unassigned budget as 700 GBP (1000 less 300 assigned to already created PO's). The Internal order is created for Controlling Area CA01 which has PDR as the currency.
    We create SHOP WITH LIMIT (SWL) SC in USD currency with this internal order as account assignment. Reason of using USD (instead of GBP which is the Internal order currency) is - we want PO in USD because Vendor currency is USD. The resultant PO will have account assignment = F(order) and Item Cat=D (service).
    For simplicity sake assume that 700 GBP = 1200 USD.
    When we specify limit amount as 1200 USD in SWL SC, the system throws error that this amount exceeds the budget. Not only this, say for any amount more than 300 USD, the system keeps on throwing this error and we can not create the SC.
    In essence, we can not use the full unassigned amount to crete SWL SC.
    The system allows to create SC if Limit amount is less than 300 USD.
    We have tested -
    1) If we create SHOP SC (as against SWL), the system allows full unassigned amount of internal order.
    2) If we create stand-alone PO in the backend, the system allows full unassigned amount of internal order.
    Please help in resolving - why the system does not allow full unassigned amount of internal order while creating SWL SC?
    Thanks and regards
    Vilas

    Hi
    <b>Please go through the following SAP OSS Notes -></b>
    Note 640369 - Incorrect values in dropdown in account assignment details
    Note 1027656 - Simplified pricing:wrong price calculation in SC using prod.
    Note 1038241 - Simplified pricing: Follow-on note to note 1027656
    Note 1034949 - Wrong price in SC when a product has multiple conditions
    Hope this will help.
    Regards
    - Atul

  • Internal Order : Plan & Budget

    I want to know what is the exact difference between Planning & Budgeting of Internal order ?
    How do we differentiate them ?
    Moderator: Please, avoid asking basic questions. This is not the first warning you are receiving from moderators. Search basic SAP material before posting

    Hi,
    Planning is forecasting of cost and revenue and when it comes to budget it is a control prospective and we will restrict the cost limit
    Regards,
    Satya

  • Internal Order Vs. Maintenance Order

    Dear All.
    Greetings of the day
    We have a scenario in which settlement receiver is internal order , and internal order have budget profile .
    how can we link the maintenane order to internal order wrt to budget , means system should not allow to exceed the budget assigned in internal order.
    right now what is happening is system does not stop to exceed the budget limit  but settle only amount that is assigned to intenrnal order  which is receiver in Maintenance order.
    and how can we link material procurment through  maintenance order  as  non stock item to internal order  ( when settlement receiver is internal order)
    Thanks in advance
    Armaan

    Khan we are already using the same , internal order as settlement receiver in Maintenance order of that object , but the budget assigned in internal order is not reflecting in maintenance order 
    for example internal order have budget 100 rs. for any asset ( as equipment ) and we need to do some maintenance work on that equipment hence create a M.O. for that equipment , now there should be control that we can not use more that 100 rs on this maintenance order , for example we nee spare of worth rs. 200 on this order , and system should allow more than 100,
    but here no control of it
    and also we are facing a problem that we get settlement of 100 only instead of 200,
    so my query is how to control this ?
    Armaan

  • Why does internal order can exceed budget ?

    i use real internal order 400001 . set budget at KO22 year 2008 = 100  (post not over 100)
    config at t-code KOT2_OPA   budget profile = 000001
    and set order availability control : tolerance limits = 100 (error message)
    but when i post expense at FB60  i use internal order 400001
    to get value 5000.   document can post and saved. 
    please tell me .
    1  why internal order can post exceed budget 100 ?
    2  can i use statistical internal order to check budget ?
    Edited by: dittaporn nanasilp on Oct 16, 2008 5:36 AM

    Hi
    1.Check in OPTK whether you have exempted that cost element.
    2.Check tolerance limit is set for "all activity groups"
    3.Use KO31 to reconstruct availabilty control.
    Regards

  • Internal Order value check upon CM request entry

    Hi,
    We would like to receive an error message when the amount input in the sales order exceeds the available value of the assigned Internal Order (in the account assignment tab).  Is this possible?
    Currently, this happens only when we do the billing, where an FI document is generated.
    Pls advise any user exit if any..

    Hi Kailash ,
    What kind of value check are you talking about... Are you concerned wether budget is exceeding limit or not...
    For doing that.. you can use SAP standard functionality using tolerance limit for avialibility control...
    Check the SAP IBM Guide -> Internal Order -> Order Master Data -> Budgetary Control..
    Kindly revert back for any further clarifications
    Regards
    Sarada

  • Budgeting internal order..

    Dear All,
         I have done internal order buget config and in 'Tolerance limit and availability control' i have taken action 3, that means whenever i post more than the budget amount, it should throw the error, but in my case it is accepting any amount. When i try to post more than my budget amount, it should throw the error. what do i do now...
    Regard,
    Suresh Patipati.

    Hi Suresh,
    Pls try to "Activate" "Budget Availability Control" in transaction code KO30 and try.
    Pls revert back if it doesn't work...
    Srikanth Munnaluri

  • Internal Order not allowing to decrease budget amount

    Dear Experts
    We have to close Internal Order no. 800001526 but system is not allowing to decrease budget amount from Rs. 2606000
    Regards
    Ajeesh

    Hi Ajeesh,
    I happen to go with Manikumar, because in the recent post we see either actuals/commitments Zero only, but when we see at your first screen, there we see total value (either actual/commitment) as 5212000, which is double of your budget i.e. 2606000, that's why there it is giving negative budget value of -2606000 (i.e. 2606000-5212000) which implies your budget has exhausted.
    So when you post with 5212000, system hasn't stop you as you might have not had availability control or had tolerance limit for more than 200%.
    Please if at all it is testing server, why don't you create one more order and check?
    Regards...
    Jose

  • Internal order(urgent)

    Hi,
      Plz explain how to create orders(internal orders) cost element group wise for budgeting.
    Thanks in advance,
    Manisha

    Dear Manisha Gupta!
    Following the following Step
    1- Creation of Internal order Transaction code Ko01, input Order Type that You configured.
    2-For Budgeting, maintain Budget Profile Transaction Code okob
    3- Maintan Tolerance limit
    4- activate the avialability Control Ko30
    But remeber that You can enter your budget at internal order level, you can't enter the budget at the cost element level.
    Hope this will be helpful

  • IW32 - restriction or validation to accept only internal order from a plant

    HI team!!
    I´m needing your help
    Im working with Tcode IW32 when creating a maintenance order and we got through Goto / Settlement rule we can assign any internal order number.
    there is no restriction or validation to accept only internal order numbers from the corresponding plant, this condition may affect other entities
    How can I limit it?
    Thks & regards "

    In configuration, in settlement rule, restrict receiver other than internal order. In case if you want to have internal order as a receiver but restrict only some orders, you can do that using a user exit/badi at save.
    example user exit -IWO10009

  • Internal Order settlement taking long .

    Hi all,
    We are doing the Internal Order settlement throught c088 and running it in the back ground processing.
    Somehow its taking very long ( few days and still running ) . Its not an ABAP issue as there are no competing jobs. This is being done in ECC 6.0.
    Any clue why the settlement is taking so long? any help will be useful.
    thanks so much.

    Hi,
    I hope you might have included more than 1000 Internal orders for collective settlement...this will cause for either ABAP run time error or long time for completion.
    Please limit your selection like 500,500,500 ....then it would work.
    Please check OSS note.532323 and 621934
    Regards, Velumani
    Message was edited by: Velumani Arunachalam

  • Internal order budget message

    Hi,
    We use internal order budget function, after budget is maintained in KO22, then i make a PO, if the PO value is over the budget, SAP will have a message saying over budget how much amount, but it did not tell directly the budget total amount, is there any way to enhance this?

    hi,
    This can be possible.You can activate the Budget avaibalility control, in the tolerance limit you set the pecentage.Once it activate, the you got the following messages which your configuration.
    1. Warning
    2.Warning with mail to person responsbile.
    3.Error Message.
    Thanks and regards.
    Sivakumar.Subbiah

  • Internal Order budgeting not checking at the time of FB60

    Dear All Experts,
    Very Good Morning !
    I have configured IO budgeting with Overall Planning ticked budget profile. I have assigned budger profile to Order type also.
    In KO23 I have given limit also of Rs.10,000 /- for overall and yearly 2011 Rs,5,000 /-. In define tolerance I have maintained two entries as below : 1 is with 01 Group wich will check PO's and 2nd one is 04 Group which will check Financial account document. ( I hope this correct, If not please rectify me ). In tolerance limit I have given 3 as a error should throw.
    I refer this thread [Internal Order Budget - Availability Control|Internal Order Budget - Availability Control; from our SDN forum. I activated budget control from KO23 and referring KO30 now system is showing GREEN Availability control is active.
    Now when I am running FB60 with assignment IO, system is not throwing any error, warning , it remains normal posting is happening.
    If anybody has gone through the same issue, experts inputs / guidance will be very helpfull.
    Regards,
    Revati Joshi.

    Your tolerance limits are fine
    Let me put you some points here.
    Creating IO
       1. Investment Profile is mandatory for Capital projects
       2. If you are using Investment management, then check IM32, & IM52
       3. KO02 - Check  - Investments tab - IM Program and Position ID assinged or not
       4. Need to assign the budget in both Controlling area currecny and object currency (KO12, & KO22)
       5. Availability control should be Active - KO30
       6. Planner plofile - KP04 - Just press F4 and check - if there are any created for your controlling area
       7. Check if you have any line itesm already posted to the IO - KOB1, KOB2, KOB3
    Now, the actual plan is - KPF6 and KDF6
    Here you need to input the below details
    Version                    0
    From Period               01
    To Period                      12
    Fiscal Year          2011
    Order                                           input the order
                      to
             or group
    Cost Element                              which Cost elemtn you are going to post in FB60
                      to
             or group
    Enter those details and in next screen - give the amount for that cost element.
    Now o and post in FB60
    Hope it helps
    Thanks