Internal Order - Purchase Order -Purchase Requisition

Hi,
Can anyone please help me out with understanding how costs are posted to an internal order from Purchase Order/Purchase Requsition?  How to make commitments via PO/PR? And how is it settled onto an asset?
Sorry its too much to ask. If anyone can guide me to a document explaining this online somewhere.
Thanks,
M

Hi,
Whenever you assign your PO/PR items to be issued on internal order, you will see the posting on it. You will have to activate commitment management in CO (OKKP). After the GR/IR process is done, and the cost are on I/O, you can settle it to an asset. In order to do so, you have to define a settlement profile for order type, create a settlement rule in the order (KO02) and run the settlement (KO88/KO8G).
Regards,
Eli

Similar Messages

  • Purchase order and purchasing requisition .

    Hi
    What is the difference between Purchase order and Purchase requisition . ?
    And why cube are different for them ?
    Regards

    A purchase requisition is an internal document that's created to initiate a procurement transaction. The requisition is created to identify the materials that are needed to be acquired and when they're needed. Once completed by the initiator, it's sent to the appropriate approvers.
    Upon approvals of the requsition have been provided, and a vendor is selected, a purchase order is created. The purchase order is an external document whereby an agreement is made to procure the materials at an agreed upon price and delivery schedule
    The InfoCubes for each of these is different due to the nature of the documents (internal v. external).

  • User Exit/BADI for Purchase Order and Purchase Requisitions

    HI,
    I have a requireent where i have to check the the user does not enter both Subitems and Over a Limit for a Service Purchase Requisition.
    Is there a User Exit or Badi that i can use where this information is availaible.
    also i have to check that release strategy is assigned to every purchase order where the version has been completed.
    Is there a User Exit or Badi where Information of EREV table is availaible.
    Regards,
    Tarun Bahal

    For Purchachase requisition , the BADIs and USER EXITS are
    ME_COMMITMNT_PARKING BAdI for Redefining Commitment Interface When Parking
    ME_MEREQ_PARKING BAdI Purchase Requisition: "Hold"
    ME_REQ_HEADER_TEXT Copy Header Text: Enjoy Purchase Requisition
    try with the above BADI's
    MEREQ001 Customers' Own Data in Purchase Requisition
    for Purchase order , the BADIs and USER EXITS are
    ARC_MM_EKKO_CHECK BAdI: Enhancement of Archivability Check (MM_EKKO)
    ARC_MM_EKKO_WRITE BAdI: Enhancement of Scope of Archiving (MM_EKKO)
    EXTENSION_US_TAXES Extended Tax Calculation with Additional Data
    MEGUI_LAYOUT BAdI for Enjoy Purchasing GUI
    ME_ACTV_CANCEL_PO BAdI for Activating the Cancel Function at Header Level
    ME_BADI_DISPLAY_DOC BAdI for Internal Control of Transaction to be Invoked
    ME_BAPI_PO_CREATE_01
    ME_BAPI_PO_CREATE_02
    ME_BAPI_PR_CREATE_01
    ME_BAPI_PR_CREATE_02
    ME_BSART_DET Change document type for automatically generated POs
    ME_CCP_ACTIVE_CHECK BAdI to check whether CCP process is active
    ME_CCP_BESWK_AUTH_CH BAdI for authorization checks for procuring plant
    ME_CCP_DEL_DURATION Calc. of Delivery Duration in CCP Process (Not in Standard)
    ME_CHANGE_CHARACTER Customer-Specific Characteristics for Product Allocation
    ME_CHANGE_OUTTAB Enrich ALV Output Table in Purchasing
    ME_CHECK_ALL_ITEMS Run Through Items Again in the Event of Changes in EKKO
    ME_CHECK_OA Check BAdI for Contracts
    ME_CHECK_SOURCES Additional Checks in Source Determination/Checking
    ME_CIN_LEINRF2R BADI for CIN India - Delivery charges
    ME_CIN_LEINRF2V BADI for LEINRF03 excise_invoice_details
    ME_CIN_MM06EFKO Copy PO data for use by Country version India
    ME_CIP_ALLOW_CHANGE Configuration in Purchasing: Changeability Control
    ME_CIP_REF_CHAR Enables Reference Characteristics in Purchasing
    ME_COMMITMENT_RETURN Commitment for return item
    ME_COMMITMENT_STO_CH BadI for checking if commitments for STOs are active
    ME_COMMTMNT_PO_RELEV Check for Commitment-Relevance of Purchase Orders
    ME_COMMTMNT_PO_REL_C Check for Commitment-Relevance of Purchase Orders
    ME_COMMTMNT_REQ_RELE Check of Commitment Relevance of Purchase Requisitions
    ME_COMMTMNT_REQ_RE_C Check of Commitment Relevance of Purchase Requisitions
    ME_DEFINE_CALCTYPE Control of Pricing Type: Additional Fields
    ME_DP_CLEARING Clearing (Offsetting) of Down Payments and Payment Requests
    ME_FIELDSTATUS_STOCK FM Account Assignment Behavior for Stock PR/PO
    ME_GUI_PO_CUST Customer's Own Screens in Enjoy Purchase Order
    ME_HOLD_PO Hold Enjoy Purchase Orders: Activation/Deactivation
    ME_INFOREC_SEND Capture/Send Purchase Info Record Changes - Internal Use
    ME_PO_PRICING Enhancements to Price Determination: Internal
    ME_PO_PRICING_CUST Enhancements to Price Determination: Customer
    ME_PO_SC_SRV BAdI: Service Tab Page for Subcontracting
    ME_PROCESS_COMP Processing of Component Default Data at Time of GR: Customer
    ME_PROCESS_PO Enhancements for Processing Enjoy Purchase Order: Intern.
    ME_PROCESS_PO_CUST Enhancements for Processing Enjoy Purchase Order: Customer
    ME_PROCESS_REQ Enhancements for Processing Enjoy PReqs: Internal
    ME_PROCESS_REQ_CUST Enhancements for Processing Enjoy PReqs: Customer
    ME_PURCHDOC_POSTED Purchasing Document Posted
    ME_RELEASE_CREATE BAdI: Release Creation for Sched.Agrmts with Release Docu.
    ME_REQ_OI_EXT Commitment Update in the Case of External Requisitions
    ME_REQ_POSTED Purchase Requisition Posted
    ME_TAX_FROM_ADDRESS Tax jurisdiction code taken from address
    ME_TRF_RULE_CUST_OFF BADI for Deactivation of Field T161V-REVFE
    ME_TRIGGER_ATP Triggers New ATP for Changes in EKKO, EKPO, EKPV
    ME_WRF_STD_DNG PO Controlling Reminder: Extension to Standard Reminder
    MM_DELIVERY_ADDR_SAP Determination of Delivery Address
    MM_EDI_DESADV_IN Supplementation of Delivery Interface from Purchase Order
    SMOD_MRFLB001 Control Items for Contract Release Order
    AMPL0001  User subscreen for additional data on AMPL             
    LMEDR001  Enhancements to print program                          
    LMELA002  Adopt batch no. from shipping notification when posting
    LMELA010  Inbound shipping notification: Transfer item data from 
    LMEQR001  User exit for source determination                     
    LMEXF001  Conditions in Purchasing Documents Without Invoice Rece
    LWSUS001  Customer-Specific Source Determination in Retail       
    M06B0001  Role determination for purchase requisition release    
    M06B0002  Changes to comm. structure for purchase requisition rel
    M06B0003  Number range and document number                       
    M06B0004  Number range and document number                       
    M06B0005  Changes to comm. structure for overall release of requi
    M06E0004  Changes to communication structure for release purch. d
    M06E0005  Role determination for release of purchasing documents 
    ME590001  Grouping of requsitions for PO split in ME59           
    MEETA001  Define schedule line type (backlog, immed. req., previe
    MEFLD004  Determine earliest delivery date f. check w. GR (only P
    MELAB001  Gen. forecast delivery schedules: Transfer schedule imp
    MEQUERY1  Enhancement to Document Overview ME21N/ME51N           
    MEVME001  WE default quantity calc. and over/ underdelivery toler
    MM06E001  User exits for EDI inbound and outbound purchasing docu
    MM06E003  Number range and document number                       
    MM06E004  Control import data screens in purchase order          
    MM06E005  Customer fields in purchasing document                 
    MM06E007  Change document for requisitions upon conversion into P
    MM06E008  Monitoring of contr. target value in case of release or
    MM06E009  Relevant texts for "Texts exist" indicator             
    MM06E010  Field selection for vendor address                     
    MMAL0001  ALE source list distribution: Outbound processing      
    MMAL0002  ALE source list distribution: Inbound processing       
    MMAL0003  ALE purcasing info record distribution: Outbound proces
    MMAL0004  ALE purchasing info record distribution: Inbound proces
    MMDA0001  Default delivery addresses                             
    MMFAB001  User exit for generation of release order              
    MRFLB001
    Regards,
    Anirban

  • Attachment for Purchase Order and Purchasing Requisition

    Dear All,
    At the moment we are on ECC6 EHP 4 and would like to use Document Management in SAP. Now att the PO and PR line item we need to click the Documents icon to see the if the is any document that is being attached to the line item . Is there any way that we can have and indicator at the PR or PO item to denote that there is an attachment attach without the need to click the Documents icon? Maybe an attachment symbol that outlook use whenever there is an attachment in the email.
    Would appreciate if you provide any notes or configuration step how to do this.
    Thanks

    A purchase requisition is an internal document that's created to initiate a procurement transaction. The requisition is created to identify the materials that are needed to be acquired and when they're needed. Once completed by the initiator, it's sent to the appropriate approvers.
    Upon approvals of the requsition have been provided, and a vendor is selected, a purchase order is created. The purchase order is an external document whereby an agreement is made to procure the materials at an agreed upon price and delivery schedule
    The InfoCubes for each of these is different due to the nature of the documents (internal v. external).

  • Problem with Purchase order (requisition)

    Hello friends,
    I have a problem during creating a PO also PO requisition. During my work, the system is reporting this error message:
    "Budget for all Years under year-based commitment update of value type Purchase order".
    I thing the problem is caused by some wrong year end closing activities or by the budget.
    I am hopeless. Thanks for your help,
    Charlie

    If you getting reqs against the internal order then it is related to controlling mans you have to check the settings for controlling which i have suggeted

  • Assigning an Internal Order to a Purchase Requisistion

    Hello,
    Probably not an ABAP question but I have noticed that most(if not all) question regarding PR's are directed here.
    Anyways my question is quite simple, is there a way to assign an Internal Order to a Purchase Requisition. I know there is an Account Assignment where the Fixed Asset is entered in the PR but some of the Internal Orders arent even fixed assets (or assets for that matter as some are overhead costs).
    Thank you everyone and good day.

    Hi Chad,
    when you create a purchase requisition (transaction ME51N) pick for your line item the account assignment <b>F</b> (the account assignment is the first field after the item number with the header <i>A</i>).
    Then you can assign in the item details an order number (tab <i>Account Assignment</i>).
    Regards,
    Claus

  • Purchase order vs Purchase Request vs Purchase Requisition

    Good Day Gurus,
    Could someone tell me the differences bet these three in detail
    thanks in advance

    1) Purchase requisition created by user dept. or automatically by MRP run, which can be converted to purchase order or RFQ (request for quotation). its a internal document
    for more details:
    http://help.sap.com/saphelp_47x200/helpdata/en/75/ee1fa755c811d189900000e8322d00/frameset.htm
    2) Purchase request : nothing like this in SAP
    3) Purchase order : A out going document which we send to vendor or supply plant to deliver required materials with other condition like when to delivery ,delivery address, pricinging condition, payment terms and condition etc
    for more visit http://help.sap.com/saphelp_sbo2004a/helpdata/en/32/27074bfc8bb54ba46dc5e76a8838f4/content.htm

  • Planned orders to Purchase Requisitions and Purchase Orders

    Hi,
            Just wondering if this is possible. I heard this from a client and want to confirm if it's true.
    The client owns the technology and has contractors manufacture the product.
    A planned order is generated by the client and based on the type of contractor, some of them are converted to Purchase orders and others to Purchase requisitions.
    Is this possible? I was thinking, planned orders ans purchase requisitions are completely different entities. Planned orders are for internal manufacturing which are subsequently changed to Production orders and purchase requisitions are for external procurement that would be converted to Purchase orders.
    But converting the Planned orders to Purchase Requisitions and orders is what I could not digest.
    Is there any possibility of this case?
    Thanks.

    Hi,
    We can create planned orders & convert them into purchase requisition or into production order.
    In the material master ,mrp2 view give the procurment type as 'X', for both internal & external procurement.
    Also include purchasing view for this material.
    When you run mrp using md02, a planned order will be created for the rquirement (Eg:say 100 nos given using t.code md61).
    Use t.code md04 to view the stock/requirement list.
    Here double click the planned order, you can see tabs such as convert into purchase requisition, into production order, into process order.
    Click convert into pur req & enter 50 Nos. Then a pur req will be created which can be further converted into pur order.
    Again come to md04 screen.
    You can see a planned order & pur req for 50 nos.
    This planned order can be converted into production order & 50 nos can be produced internally.
    Hope this clears your doubt.
    Regards,
    Senthilkumar SD

  • Purchase order to Asset non imposed the Internal Order.

    I'm entering a purchase order of an asset tied to an internal order of investment. The order has a budget X. If I enter a purchase order with value greater than the amount budgeted in the internal order, the system allows me to create the request and not imposed the internal order. In the report S_ALR_87013019, the order has no value released.
    How can the system do not allow the purchase of assets with values greater than estimated and how to make that encumbers the purchase order and appear in the report S_ALR_87013019?
    This only happens in the purchases of assets!
    Thanks in advanced!
    GLMacedo

    My friend, see my answer to witch point.
    1. Your Asset APC account should be Category 90 (Statistical) Cost element
    The Internal Order is Statistical (I see in KO03). Should I verify in another place?
    2. your Internal Order must be of category "Investment" and not "Overhead"
    OK
    3. Assign this Internal order in your Asset Master in the field "Investment Order"and not "Internal Order"....
    OK
    if Investment Order is not visible in Asset Master, change your screen layout of the asset and plug it in (IMG > AA > Master Data > Screen layouts)
    4. Do settings in T code ACSET - Allow EAUFN for Trn Type = *, Acct Assign Type = APC Postings, and check the Acct Assgn check box
    I don´t know how can I do this. How Can I Do?
    Allow commitment management in your contr area OKKP and in your Internal order type (KOT2_OPA)
    My type Order (investment) in KOT2_OPA is OK (commitment management was allowed). But in OKKP it is not! It is a critical setting. Should I flag this field?
    6. Feield Status Group of Asset must allow CO/PP Order in OBC4
    OK
    Thank you very much!

  • Purchase Order and Purchase Requisition

    Hi To All,
    my customer while using tcode me2m hase extracted purchase order opened since 2007. now he want to close all this order and settle them to zero. this operation should be done also for the purchase requisition.
    there is a standard way to do this? if not any idea?
    thanks
    C.

    Hello
    Just by doing
    In the PO line item level details, activate DELIVERY COMPLETED check box.
    system will not close po from GR
    U will have to check what is the gr qty did till date
    and update the po with the same qty manually
    eq
    if po qty is 50 and total gr done till date is 40
    change the PO qty to 40 and save
    this is the way u can shot close the po
    Which effects has the "delivery completed" indicator?
    The purchase order item is considered closed, even though the total quantity may not have been delivered.
    Although a further delivery is not expected, it is still possible.
    At the time of the next goods receipt, the system suggests the item as unselected.
    The purchase order item can be deleted, even if the total quantity was not delivered.
    Although the "delivery completed" indicator is not set, a purchase order item is still considered closed if the full quantity has been delivered. In this case, the "delivery completed indicator" is not required.
    The system allows to make further goods receipts. Why?
    Answer
    See note 16239 and 856279
    hope this helps
    Edited by: Umakant Bhangale on Oct 11, 2010 5:20 PM

  • Report for purchase requisition, purchase order and schedulling agreement.

    Hi, thanks for your help.
    I need a report or query just to view in one screen the related docs. as purchase requisition, purchase order and schedulling agreement.
    I don´t know if there is a table or trx. with that information.
    Is it possible to get that information via query ?
    Thanks for your help.
    Regards.

    For PR and PO you can use ME5A
    For PR and Scheduling agreements also you can use ME5A.

  • Purchase Requisitions, Purchase Orders and Receipts

    Hello all,
    The following is the sequence for Purchasing
    Purchase Requision -> Purchase Orders -> Receipts
    However I have a requirement to bring in the related Purchase requisions,purchase orders and receipts from 11i into R12 instance.I can do that using the open interfaces.However How do i link these 3 objects together?
    I intend to import the purchase orders first and then import its related purchase requistions and the receipts...In doing so how do i link them together.How do i know that this purchase order was created from this Purchase requistion or this receipt is meant for this purchase order? What is the joiing columns in the base/open interface tables?
    Thanks
    AJM

    Hi Venkat
    1. To perform ATP do we need all the issues(Sales Orders, Deliveries) and receipts(Purchase Requisitions, Planned Orders) in APO?
    Yes you need all the mentioned elements above in APO to do ATP check. Again, you can also extend the scope of the check to further more receipts and issues. All  depends on your configuration of scope of check.
    3. I guess in Apo the planned order and process order is a single elment. Is that Correct?
    Yes, technically a planned order can be a planned process order or a planned production order.
    regards
    Mohan Chunchu

  • Purchase orders and requisitions - R12 user interfaces

    Hi,
    I see that the purchase order can be registered in the system by two different interfaces (I'm running R12.1.1): Using Oracle forms (Navigation path: Purchasing Super user: -> Purchase orders -> Purchase orders) and using Java html pages (Navigation path: Purchasing Super user: ->Buyer workspace ->Orders).
    I have two questions:
    1. The second option (using java pages) is not documented in the usersguide. Is it fully in production or they are still developing it? Why there are two different interfaces for the same purpose?
    2. I see that from Java pages interface I can only see requisitions, but I cannot enter new ones (Navigation path: Purchasing Super user: ->Buyer workspace ->Requisitions). Should I enable somewhere this or the requisition is not developed using Java pages interface?
    Thank you

    993322 wrote:
    Hi,
    I see that the purchase order can be registered in the system by two different interfaces (I'm running R12.1.1): Using Oracle forms (Navigation path: Purchasing Super user: -> Purchase orders -> Purchase orders) and using Java html pages (Navigation path: Purchasing Super user: ->Buyer workspace ->Orders).
    I have two questions:
    1. The second option (using java pages) is not documented in the usersguide. Is it fully in production or they are still developing it? Why there are two different interfaces for the same purpose?
    2. I see that from Java pages interface I can only see requisitions, but I cannot enter new ones (Navigation path: Purchasing Super user: ->Buyer workspace ->Requisitions). Should I enable somewhere this or the requisition is not developed using Java pages interface?
    Thank you
    http://docs.oracle.com/cd/E18727_01/doc.121/e13410/T446883T443956.htm
    http://www.apps2fusion.com/training_demo/puneetk/Professional-Buyer-Work-Center.pdf
    HTH
    Mahendra

  • Report with purchase requisitions and purchase orders: how?

    Hi,
    I need to get a list of items bought with their purchase requisitions and purchase orders (when they exist). This can be done looking at each purchase order (ME23N), ou purchase requisition (ME53N), and writing it down. But in some cases, I have to do it on about 450 operations. I'd like to get this list without having to search for each requisition ou order. I can get a complete list of orders and requisitions, but without any relationship between them (they are mixed as if they were the same thing, but there´s a field telling it that row is an order or a requisition). Using some macros in excel, I can find this relationship in 40% of the cases (for example, if item 421351 was purchased only once, an order for item 421351 is related to a requisition for item 421351). Is there any way to get this list automatically? Or is there any field that tell me this relationship?
    Thanks,
    Francisco Morbiolo
    Votorantim Cimentos
    Votorantim, SP - Brazil

    Sorry, I forgot to tell this: I don´t have access to SQ01/SQ02/SQ03.
    I get the orders and requisition reports using ZGLPS020.
    Thanks,
    Francisco Morbiolo
    Votorantim Cimentos
    Votorantim, SP - Brazil

  • Availability  check in Enjoy Purchase Order & Requisition

    Hi Experts,
    The availability check is used in 4.7E also but what is difference in Ecc 6.0 or new functionality added
    Can any one plz let me know
    Regards
    Pratap

    Below is capture from sap release documentation :
    Availability Check in Enjoy Purchase Order and Requisition
    (Changed)
    Use
    As of SAP ECC 6.0, SAP_APPL 600, display and checking of availability are invokable separately in the
    Enjoy purchase order and requisition in line with the system behavior on the Sales side.
    You invoke the display and checking of availability in the Enjoy purchase order (transaction code
    ME21N) and the Enjoy purchase requisition (transaction code ME51N) as follows:
    - To display the availability overview, choose Environment -> Availability
    - To check availability, choose the Check Availability icon.
    13.6.16.3 System Behavior After Availability Check for an Item (Changed)
    Use
    If you carry out the availability check for an item of a stock transport order, hitherto the system adopted
    confirmations as per the desired date/time only.
    SAP AG 30
    ______________________________________________________S_A_P_-S_y_s_te_m_
    As of SAP ECC 6.0, SAP_APPL 600, you can define in Customizing how the system reacts if the desired
    quantity cannot be confirmed for the desired date/time.
    You have a choice of two settings:
    - Confirmation as per desired date/time
    This is the standard setting and corresponds to previous system behavior.
    - Delivery proposal
    - Full confirmation
    Effects on Customizing
    You make the settings in the Rule for Adoption of ATP Results in Purchasing field in Customizing for
    Purchasing under Purchase Order -> Set Up Stock Transport Order -> Assign Delivery Type and
    Checking Rule.

Maybe you are looking for

  • Template issues

    I am trying to apply our template to all pages, but the background color is not applied. I didn't create the template and I can't find the part of the code that is causing this issue. I actually would like the whole template to be uneditable except f

  • Screen Sharing Works, File sharing does not work

    Up until yesterday everything seemed to be working fine, I could connect to my mini over my network and get files from it. Now I am not sure what I did, but everytime I click on the mac mini in the finder it says connection failed. I can still do scr

  • [Solved] Using Artwiz lime with DWM

    Hi all, I have dwm configured with statuscolors and pertag, but changing the font to lime doesn't work. It keeps falling back on the "fixed" font. For the font line in config.h, I've tried: static const char font[] = "-artwiz-lime-medium-r-normal--10

  • How to make Firefox access the internet from Oracle Ent. Unbreakable Linux?

    Hello I have a Dell Duo Core x86 laptop that multiboots Windows 2003 Server, Windows XP and Oracle Enterprise Unbreakable Linux. I use Internet Explorer to access my email while at the library so I know my laptop can access the internet. I just insta

  • Registration of packaging (for example glass, plastic, aluminum, metal)

    Dear Experts, Could you please exchange some idea's on how we could deal with (for us in the Netherlands) mandatory registration of the amount of glass, plastic, metal etc that houses the the finished materials we have in stock in our warehouse for o