i am developing report on capex investment measures ,
Please tell me how i will get link of IO to position id of investment measure
Regards
Avadhut

Table IMZO may help you.

Similar Messages

  • Internal Order through Investment measure

    Hi friends
    I need help in the following issue:
    I am creating Internal orders through Investment Measures.
    When ever i create an internal order in the background it creates an AuC.
    When I settle the IO the amount is posting to AuC.
    After that I tried to Capitalize the AuC to main asset through AIBU transaction code, system throwing an error "Line item settlement is not possible for asset XXX XXXX".
    Is this method of capitalizing right or any other method available to capitalize the AuC to Main Fixed Asset.
    Please Advice me.

    Capitalisation wouldn't be possible using AIBU in this case as your IO is an investement measure.
    Options you've got to capitalise such AUC's is
    1. Maintain the settlement rule on the IO with receiver as the final asset, set the status of the IO to TECO and then use T Code KO88  (Processing Type - Automatic) - Final Capitalisation
    2. Maintain the settlement rule on the IO with receiver as the final asset and then use T Code KO88  (Processing Type - Partial Capitalisation) - Partial Capitalisation
    Regards
    Sreenivas

  • Budgeting thru Internal Order with Account assignment category 'A'

    Dear All
    I want Budgeting thru Internal Order with Account assignment category 'A'
    i.e
    Created Assets with Tcode As01
    Created Internal Order and assigned budget amount to IO with Tcode KO01 and KO22
    Created Purhcase Requisition with Account assignment catg as 'A' i.e asstes. Also given Internal Order No and Asset code in PR.
    Releases PR with ME54N
    Created Purchase Order with Account assignemnt catg as 'A' i.e asstes.  In Purchase Order it displays Internal Order No. and Asset code which i have given in PR in Account assignemnt tab on Item level
    Released Purchase Order.
    Now i am checking budget detail in Tcode : S_ALR_87013019  -> List: Budget/Actual/Commitments ,  Here it gives message , "No line item were selected " in Commitment line items.
    Actually  my requirement is , i want budgeting thru internal order and want to use Account assignment category as 'A' (Assets) in PR and PO.
    Why it's not showing detail in report S_ALR_87013019  .
    What is solution for my requirement. Is it possible with some configuration or by other options.
    Thanx & Regards
    Swati Shah

    Hi Swati,
    You can do this in Asset Accounting. By standard MIGO Posting Date is taken as capitalization date for asset. You can configure to make it 'Document Date'.
    So, whenever user is posting thru MIGO, he will have better control on deciding capitalization date by inputting appropriate date in Document Date Field in MIGO.
    Check this thread..
    Re: Depreciation start date for asset thru MIGO
    Regards,
    Sayujya

  • Internal Orders with AUC ( Assets under construction) Config steps

    Dear Experts,
    Can you send me the step by step configuration for Internal order with Asset Under Construction
    Thanks
    Sanjai

    Hi nick,
    you can maintain this in the settlementrule of the internal order, Type ANL
    Best regards
       Horst

  • Internal order with revenues: settling to FI and PSG

    Hi,
    I have this scenario:
    - internal order with revenues has to settle to FI when not TECO - this is working
    - when order status becomes TECO - it has to reverse the previous posting - it' s working
    and settle to PSG, acording to settlment rule - this is the part where I need help, because it's not working.
    Can anybody help me?
    Thanks,
    Lavinia

    Hi,
    Sorry for the delay and thank for you answer, but I have the PA transfer structure configured, also the settlement profile alows PSG and  the transfer structuer is alocate to the settlemnet profile. The thing is that when I don't have a RA key, the settlement to PSG is working fine.
    Anyway, the customer changed his mind and doesn't need  RA for this type of orders and for the moment I don't need a solution
    Best regards,
    Lavinia

  • Internal order with excise problem

    Dear All
    W have internal order budgeting for consumables.whenever we make purchase order , the account assignment category is f and we purcahse against the particular internal order.
    when G/R is done the consumable material gets cosnumed against the particular interla order. ie goods receipt and the issue against the internal order with same movement type.
    here is  the problem
    Whenevere G/R is made the part 1 register(country india version) gets updated .
    But because of goods issue against internal order , the part 1 register shows both the receipt and the issue . so whenever the excise invoice is made through  j1iex thesystem shows that part 1 entry is not vailable.
    In the part 1 register printout  shows the receipt and the removal of goods.
    as per the excise regulations the part 1 entry sholud be there for the particular material. please suggest how to avoid the removal entry in part 1 register. only receipt has to be updated in the part 1 not the removal ie goods issue.
    please suggest how to overcome this issue.
    With Regards
    balaji

    What is G/R?

  • Create internal order with reference - Do not copy distribution rule group

    Hi,
    I'm creating an internal order with reference to another order through tcode KO01. When i will display the new internal order, i already have distribuion rule group that was copied from the reference order. To delete the incorrect distribution rule group i execute tcode KO02, however this information do not appear in tcode KO02.
    What should be done to delete this settlement rule? I do not want to copy the settlement rules from the old internal order.
    Thanks in advance.
    Regards,
    Ana Fernandes

    Hi.
    'What should be done in order to do not copy this information when i create the internal order with reference?'
    in tcode kot2_opa do not maintain Settlement profile for Order category 3
    Also go to KOM2 and delete Settlement rule for order, from which you copying.
    'in table COBRB i can see the information however i can not delete it. The validy period is empty.'-in su53 check authority

  • Internal order with a budget

    I have a real internal order with a budget.
    In case I create the settlement of the internal order by period end- how this will impact from the budget point of view
    (I am steeling the cost with the original account to a cost center).
    I mean to say-  will the system refer the settlement as a deduction in cost - so i will have more available budget- this is  a scenario I am not interested in.
    How can i solved this conflict (in case this conflict is in place).

    Hi
    If you are settling to a Budget controlled object i.e. the receiver also has a budget on it - In that case, settlement would release the budget from sender IO
    Else, it does not
    br, Ajay M

  • Steps to create Internal Order with AUC Number

    Dear All,
              We need to create internal order with AUC number.Kindly provide us the steps to do the configurations. Kindly guide the steps to be followed for creating internal orders with AUC number and way to do the settlement.

    Dear Kishore,
    I am doing the following steps in creating internal orders:
      1) Using the tcode KO01, choosing the order type as GEN i am creating an internal order. At the time of creating an internal order i need to give AUN number. Hence i am going to Extras--> Asset Under Construction by giving the investment profile. When i enter it nothing is happening. I am unable to create AUC no manually.
    Since i am a beginner, plz guide me to create AUC no while creating internal order.

  • Goods Receipt through internal order with movement type 262

    Dear Friends,
    some of our users  making entries like the following
    1. created Internal Order 
    2. Creating Reservation with movement type 262 ( which not issued material through movemnt type 261)
    3. Stock  updated
    i just want to confirm, we not issued like X  material,  even stock not available,  we can make entries like the above, To receive X material from Internal order/ subcontractor using movement type 262.
    kindly advice please  if it is wrong then tell me the process.
    Regards,
    Rajesh G

    HI,
    if we receive material from subcontractor what process we can do...
    can you explain your issue exactly what problem you have at your end .
    I think you want to take subcontracting material inside which is not in sap system now,it may finished material or it may component.If you don't want to show this material as at vendor now
    then you can try movement type 501  or through physical inventory  t-code MI10
    Regards
    Kailas Ugale

  • Line Item settlement of Internal Order through Investment Measure

    Dear friends
    Can we do the line item settlement of Internal order. The Internal order is created through IO as Investment Measure.
    Thank You

    Hi,
    Yes. It is possible to have line item settlement for Investment Internal Order.
    Trust this helps much!
    Cheers!

  • Linking for Internal Order with Profit Centre

    Hi Gurus,
    Can anybody help me out with this query that a particular Internal Order to be matched with a particular Profit Centre
    If anybody have solution pls share with me
    I'll assign points for your feedback
    Usha

    Hi,
    Thanks for your reply, but my problem is i need to assign profit centre to the internal order and there is no field in that screen only company code is displayed
    could you guide me what can be done to pop up that field, is it the matter of field status group? if it is, then where we can go to active this field status group, pls suggest
    Your initiative in this case will be highly appreciable
    Rgds,
    Usha

  • Internal orders with no profit centers or profit center wrong

    Hi There,
    Business recently made a decision to change profit center 8009 to 8014.
    Now when the status of internal orders are changed, something is triggered that changes the profit center back to 8009 or makes it blank, meaning there is no assigned profit center.
    Any help would be highly appreciated as to what can be done to fix this problem.
    Regards,

    It appears that you have ticked the indicator "Revenue postings allowedu201C in the order type to control whether revenues can be posted to an order.
    Please discuss with business/ functional team and if they agree, then you can remove the tick, that would solve the problem.
    Otherwise, you have to correct PCA assignment entry at posting level.

  • How to create Internal Order with LKD status

    Hi All Experts ,
    Can anybody tell me how can we create IO directly in LKD status ? Or it is manual acitivity by clicking on Set / Rest button and then check LKD and save. I tried in KOT2_OPA but not no any option found. If any experts can guide for the following configuration would be great.
    1 ) Is it possible to create IO with LKD status directly ?
    2 ) Where that configuration needs to be done ?
    3 ) What is significance of JEST Table relating to Internal Order ?
    Exprerts help would be great !
    Regards,
    Sharvari Joshi.

    Hi Ajay,
    It worked fine exactly. Thank you !
    Can we have facility to create IO with LKD ststus in System Status ?
    Is it true that there are only 4 SAP Standard system status CRTD, REL, CLSD, TECO.
    Is it possible to add LKD in that ? When I clicked on to the up / down arrow I am getting only these four values.
    Can we define additional values to this point ?
    Regards,
    Sharvari Joshi.

  • Book expenses against Internal Order with reference to PO which is created against Cost Center.

    Dear Users,
    We have an issue, we created PO against Cost Center and now we want to book its expenses(MIR7) against internal order. So if possible suggest me any solution for this.
    Thanks,
    Manoj.

    Hi
    The only other way is to post a manual JV for such a PO where in you debit the expense account with reference to IO and credit the cost center with expense account. Now do the GRN against the PO with reference to Cost Center.
    If you cannot modify the PO, unfortunately, this can be the only way out.
    Regards
    Sanil Bhandari

Maybe you are looking for

  • Itunes won't work due to audio configuration

    Help! Just downloaded / updated to Itunes 7.3 on Window XP laptop. Itunes, however, will not work due to problem with "audio configuration".

  • ORA-01019: unable to allocate memory in the user side

    hi, I have a windows desktop with Win XP. It has a few Oracle software on it. Oracle 8i Oracle 9i DS Rel2 Oracle Pl/Sql Dev Oracle_Sid is set as the env variable. Now when i try to log into sqlplus from bin directory of the 8i database, i have no pro

  • Exceptions in QuickTimes for JAVA examples - plz help!

    Hello, I have a problem with the QuickTime for JAVA Applet Demos. I set the correct CLASSPATH and the examples with the Frames are working fine. The Compilation of the Applet examples also works. set CLASSPATH=C:\Programs\Java\j2re1.4.2_02\lib\ext\QT

  • How to manage playlist for Zen with Windows 7?

    After upgrading to Windows 7 (with WMP2), I noticed that I can no longer make or edit playlists for my 32GB Zen with either WMP2 or the Zen Media Explorer. Anyone know if there is a solution to this, apart from installing another third party media ma

  • Problem with BOM Quant while creating Sales order with reference using BAPI

    Dear All, I am facing problem with creating a slaes order with reference to other sales order by using BAPI_SALESORDER_CREATEFROMDAT2 . Sales order is getting created but 1. It exploding the BOM means the line items which are not there in the referen