Hi,
I,m working in a Project System implementation project, where all other modules are already in use.As per the existing process, Internal orders are created for asset accounting.Those are of statistical. All the purchase orders & costs are booked referring to the internal orders, the same cost is directly settled to Asset Under Construction or Asset.As the internal orders are created as statistical, there is no seperate settlement process & all the costs are directly settled either in AUC or in Asset as & when they are incurred(posted).
Now as we are implementing Project Systems, Internal orders are going to be replaced by WBS Elements. Customer requirement is the same process of online settlement of costs to Assets from WBS Element & he doen't want to settle seperately.
Now the issue is, 1) how the process can be mapped in SAP?
I feel creating the WBS elements as statistical, the same process can be mapped. Is it possible/
2) As one project is already in progress & some postings have been taken place against internal orders, customer wants to see all those postings on new WBS element, now how to migrate the same to respective WBS element in the new system?
Thanks
Kishore

Hi Kishore Ji,
For your question, simple answer is, you want to continue all AUC under Project Systems.  So far, you have considered statistical internal orders, anyway, which is not possible for you to settle directly.  So, please take that amount generate uploading document by using same account and using WBS element as debit and internal order as credit and status you release for internal orders.
WBS elements you create as statistical without selecting account assignment category.
Your problem will be solved.
Assign points without fail.
ALL THE BEST.

Similar Messages

  • TX CNS41 - settled cost from internal order to WBS element not displayed

    Hi PS Expets,
    I have a question regarding transaction CNS41 "Structure Overview" where cost settled from an internal order is not displayed in in the report for a selected project. This is in a ECC version 5.0
    Settled costs from internal orders are posted with transaction type KOAO on WBS elements and when you check report RCNSTFCO you can see that the following transaction types are deselected when executing transaction CNS41:
    delete t_rpsco_m where vorga = 'KOAO' "<   insert
                          or vorga = 'KOAL' "<   insert
                          or vorga = 'KOAP' "<   insert
                          or vorga = 'KOAQ' "<   insert
                          or vorga = 'KOAR'."<   insert
      CALL FUNCTION 'HFPM_RPSCO_TO_RPSCO_LIS_CONV'
    This is implemented according to OSS note 51971 in order to eliminate internal business volume in the project structure when executing a PS hierarchy report.
    But this also eliminate the display of the cost  from the internal order.
    Any ideas or a work around in order to display settled cost from an internal order on a WBS element in transaction CNS41
    Kind regards,
    Anne

    Hello Tison.
    I guess you have the Project created with a BAPI in your system in background. As far as I have seen I'd try the following in ABAP to create Partners in the Project Definition: BAPI_BUS2001_PARTNER_CREATE_M or the corresponding method ProjectDefinitionPI.PartnerCreateMultiple. This should happen in background when the Project is created also.
    Best regards.
    Jens Schmid

  • BAPI KPF6 POST PLAN COST FOR INTERNAL ORDER AND COST ELEMENT

    Hi all gurus,
    I would like to use in a custom report a BAPI/Function Module that help me to simulate KPF6 in order to post planning costs for internal order and cost element (layout 1-401).
    So the input should be:
    1) Version
    2) period from
    3) periodo to
    4) year
    5) internal order n.
    6) cost element n.
    7) value
    I found a lot of BAPI but don't know the correct one and how to use it (example how to fill the input value).
    Can anyone help me on that?
    Kind Regards

    In additio  to the previous I found the BAPI_COSTACTPLN_POSTPRIMCOST but don't know if it's the correct one and how to use it (some example fitting the my case will be very appreciated).
    If the quoted BAPI is correct.
    I tested it filling all fields as following:
    HEADERINFO:
    CO_AREA=FFCA
    FISC_YEAR=2008
    PERIOD_FROM=001
    PERIOD_TO=012
    DOC_HDR_TX='blank'
    INDEXSTRUCTURE:
    OBJECT_INDEX=000001
    VALUE_INDEX=000004 (hope this point at Interna Order)
    ATTRIB_INDEX=000000
    COOBJECT:
    OBJECT_INDEX=000001
    ORDERID=ZO53-08IMZ
    TOTVALUE:
    VALUE_INDEX=000004
    COST_ELEM=3224048
    FIX_VALUE= 200,0000
    DIST_KEY_FIX_VAL=2
    The Return table is set to 0. Nothing happens.....I suspect something related to indexstructure or index is wrong..
    Could anyone help me on that?
    Kind Regards

  • Link of vendor in sales order through WBS element

    Hi
    My sales order line items are having WBS assigned.All these line items are direct bought out items from vendors and supplied to customer.
    Please suggest me link of vendor in sales order through WBS element.
    I want to use the same logic for billing split criteria for individual line items(hence for individual vendors) Presently my client is getting common invoice for all line items but they want separate invoice for each line items.
    Awaiting for your valuable inputs
    Thanks
    Manoj

    Hi Manoj,
    I need to understand your process in more detail.
    How do you procure?  Create a sales order with TAS item category to create a PReq and PO?
    Very simple explanation: Resource Related billing/DIP profiles are used to accumulate costs on WBS elements and then bill the client as needed.

  • Sales order value flow to internal order without cost elements.

    Dear Sap Friends,
    My client have a requirement, when sales people creating a sales order, sales value flow into internal order without a cost elements. normal case when SO, Deleivery, and billing data automatically can flow into CO-PA. Here i want to know how value can flow into I.O. without a cost elements please give me advise.
    i created a  statistical internal order  and that internal order i assigned in sales order account assingment. but i know that there is no value going to flow this  I.O. becasue there is no cost elements.(becasue client dont want to create a cost element for internal order)
    There is any option when i crate a sales order  values can go into internal order without cost elements or i can create a statistical Internal Order and assigned into  CO-PA? if i can dothatt what is the steps. kindly explain to me. if some have can explain to me please leave contacts number or send me reply.
    Regards
    Paul

    By standard configuration itr is not possible.
    You ought to have user exit in place.
    For DC A & B, where you need a redetermination of pricing component, take help of an ABAPer for user exit USEREXIT_XKOMV_FUELLEN (module pool SAPLV61A, program RV61AFZB).
    So now, for DC C, you need to change the copying control in VTFL - item, where your pricing type ought to be D-Copy pricing elements unchanged.
    Regards
    JP
    ASSUMPTION: I assume that your all DC uses the same Sales Doc type & Billing Doc type

  • Uploding the order to wbs element

    Hi Guru's
    Plase any one suggest me
    How to make data transfer orders to WBS elements.
    Thanks and Regards
    siva ala

    Yes you can....if you use Easy cost planning & Execution services....In ECP you will add materials to WBSE...and use Execution service to create PR directly for the material assigned to WBSE

  • Service order and WBS Element

    Hello Experts,
    I have a question regarding WIP service order costs. Can we post the costs of a WIP service order to a WBS element? IF so where do we link the service order and project/WBS Element? How do we post the costs to WBS elements?
    Appreciate your help and time in this regard.....
    Thanks,
    Harish R

    My problem scenario is like this.
    We have two plants A and B of the same Co.Cd. We are physically closing plant A and moving everything into B. Now the open service order costs from plant A have to be moved to plant B. How do we do this?
    Do we have to create a new service order/WBS element for all old open service order/wbs element?
    Also where do we connect the service order and wbs element?
    Appreciate your help and time.
    Thanks,
    Harish R

  • Assessments expenses and revenues / orders and wbs elements

    Hello gurus,
    I have created two different structures:
    - Statistical WBS Elements for allocating all the planing data.
    - Internal Orders assigned to the WBS Elements for allocating all the actual data (expenses and reveues: item category of cost elements is 1).
    The issue is that periodically i need to distribute these things:
    - Plan data from one Statistical WBS element to others Statistical WBS elements. As the WBS Elements are statstical i really do not know how i can distribute those plan costs, i mean, how i can create the assessment cycle? which steps i must follow up? which transactions allow me to do this?
    - Actual data from internal orders to others internal orders. Exactly the same questions that in the paragraph before... The problem here is that i know how to create assessment cycles using cost centres as senders, but the transaction (KSV5, KSU5) do not allow me put order as a sender
    Thanks in advance for your help.

    Plan data for Statistical wbs elements are not eligible for assesments/distributions and settlements.
    In actuals , orders can be set as senders and receivers. Use trans KCAU to customize yur assesments.
    I hope it helps.
    Pan

  • Internal Order Report - Cost Elements by Order

    Dear All,
    When I run the report S_ALR_87012997 - List: Cost Elements by Order, the system shows the report like
    Cost Element: 500000 -  Actual: 8900    Plan : 833.33 Abs. Var: 8066.67  Var (%): 968
    Order: 100219 (stat. order): Actual: 8900  Plan: 833.33  Abs. Var: 8066.67   Var(%): 968
    how should I understand the report?
    Please guide me - urgent.
    High points will be awarded...!
    Regards,
    Ranesh.

    When I run the report S_ALR_87012997 - List: Cost Elements by Order, the system shows the report like
    Cost Element: 500000 - Actual: 8900 Plan : 833.33 Abs. Var: 8066.67 Var (%): 968
    Order: 100219 (stat. order): Actual: 8900 Plan: 833.33 Abs. Var: 8066.67 Var(%): 968
    how should I understand the report?
    Please guide me - urgent.
    Internal Order 100219 is statistical order. Under cost element 500000, actual expenses posted are 8900 against planned values of 833.33. The absolute variance is (8900-833.33) is 8066.67

  • Getting Billing Element in Purchase Order Using WBS element.

    Hi,
    What is the process and logic to get the billing element and the corresponding Sales order details using the WBS element or network of the account assignment category in the Purchase order line item.Please suggest the tables to be used to fetch the Sales order details using this procedure.
    Thanks
    Anand

    Project PO can be generated in following methods.
    1.When a Material attached to Activity in the Project, PR can be generated with A/C assignement Q. System wil copy the WBS element to which activity is assigned in the account assignment tab of PR. When PO is created with reference to PR, system wil automatically copy the  WBS from the PR in to PO account assignment tab.
    2. U can directly create PO with account assignment Q and assign WBS in account assignment tab.

  • Settling of Cost for Production Order via WBS Element

    Hi Gurus,
    Just would like to briefly understand, how I can make use of the WBS Element in the Production Order (Assignment tab) to use as cost settling for a production order? How do i automate the WBS Element in the production Order for a set of given parameters? Is there a config I can use to set a profile?
    I have a scenario here as below:
    I have various types of production orders:
    PO 1 = Production A
    PO 2 = Production B
    PO 3 = Production C
    And for each of the above, I will individually have a WBS Element.
    PO1 - WBS Element A
    PO2 - WBS Element B
    PO3 - WBS Element C
    And WBS Element A, B and C is a Level 2 WBS Element which are tied to WBS Element Z (Level 1 WBS Element), which will be settled to a project.
    Appreciate your kind feedback on the above on how I can make it work in the PP Order.
    Thanks.
    Rgds.

    Hi Manoj,
    I need to understand your process in more detail.
    How do you procure?  Create a sales order with TAS item category to create a PReq and PO?
    Very simple explanation: Resource Related billing/DIP profiles are used to accumulate costs on WBS elements and then bill the client as needed.

  • Internal order, cc, wbs

    Hello friends
    If a department gives me an old account number do I have to look up the new SAP (Internal Order, Cost Center, or Work Breakdown Structure Element) number?
    regards,

    Hi
    Yes, you must look up the new SAP number in order to process the transaction.  The crosswalk from old to new account can be found at the link below.  Select “Cost Object Crosswalk” on the right hand bottom corner:
    http://www.jhu.edu/hopkinsone/Secure_Private/ProjectAreas/Finance/index.htm
    Alternatively, use the on-line crosswalk tool found at:
    http://orchid.hosts.jhmi.edu/hopkinsone/xWalk/index.cfm
    assign points if useful

  • Budgeting -Internal order - monthly -cost element wise

    Hi!
    Got a problem! Want budget for single internal order - cost element wise. We created one employee as internal order. For this internal order, want budget for Telephone exp Rs. 500 /- per month, Travelling Rs.1000/- per month.
    I checked in budgeting and came to know that we can budget for one internal order for one year not month wise. Another thing is we cannot budget cost element wise.
    Is there any solution for this requirement. Pls. let me know.
    I appreciate your efforts and thanks in advance.
    - SRK

    As you righly mentioned budgeting is not possible cost element wise/period.
    If you want for planning/reporting purpose alone (and not for availability control) you can create a seperate plan version and use cost planning with cost element and period wise.
    Regards
    Sreenivas

  • Prevent time entry in CAT2 when Internal Order or WBS is in TECO status

    Hello Team,
    We need to prevent time entry in CAT2 when an internal order is in TECO status. Looks like CAT2 is calling business transaction RFBU (FI: postings) which is allowed in TECO.
    I'm wondering whether I can isolate CAT2, so that we can prevent just the time entry. Any suggestions, please.
    Thanks!
    VJ

    Hi,
    Try creating a user status which will prevent the posting when WBS Status is TECO.If not, use the many user exits available in CAT2 and put in a custom code check for the status.
    Regards
    Sreekanth

  • Sales Order with WBS Elements

    Hi,
    I have a sales order having lot of WBS elements assigned.....but I am not able to generate revenue  for one WBS element out of them.
    Can anyone tell what should I do for the same.
    Regards,
    Krishna Singh.
    Edited by: Krishna Prakash Singh on Oct 30, 2008 7:53 AM

    Hi,
    Please check in CJ20N , whether this WBS e has been marked as a billing element or not.
    I think this is not marked as a billing element.
    Thanks,