Hi Experts,
can we settle investment order cost to AUC?
I am able to settle order cost to Fixed Asset (After clicking on 'Complete Asset'), It is creating settlement rule for that fixed asset.
But can't we settle order cost to AUC (Before comleting asset)?
Pls guide.
Regards,
Kedar

Dear,
For Investment orders let us say the project usually takes a year or two so during course of time we will settle cost to AUC i.e. asset under construction and after completion of the project finally we will settle amount to Fixed asset.
regards
satish

Similar Messages

  • BW for Investment Management

    Hi all!
    Can anybody say about integration between BW and Investment Management?
    I have no information about this.

    Hi Dmitry,
    Please, refer to this link:
    http://help.sap.com/saphelp_nw70/helpdata/en/4c/10193c66f5dc1ce10000000a11405a/frameset.htm
    Regards,
    Eli

  • Appropriation request - Investment management. (configuration)

    Hi All,
    I am going to implement appropriation request and Investment management.
    1st. What kind of configuration required?
    2nd. How can we activate the workflow for the appropriation request ?
    3rd. Can we linked the appropriation request to IM module ? in another word, let say we have put some amount in appropriation request, then can we make it automatically allocated in IM module
    4th. Please advice.
    Cheers,
    Nies

    I don't have any better configuration guide than what's already there on help portal (Best Practices)
    Q06: Investment Management:
    http://help.sap.com/bp_bblibrary/600/BBlibrary_start.htm
    Also refer few SAP tutor files (offline demos on IM/PS Integration) available under below link;
    Business Information>Preconfigured Scenarios>U71: Equipment Construction Management
    http://help.sap.com/bp_utilitiesv1500/UTL_India/index.htm
    Regards
    Sreenivas

  • Budgets in Investment Management

    I am looking to introduce Investment Management.  I am finding budgets very clunky, and far from user friendly, and I am wondering if there is a better way to deal with them.  can anybody advise on the following.....
    1. I am currently inputting anual budgets via IM32.  By default the transaction shows the overall view for the whole program.  The proposed process is to switch to the annual view, enter budgets, switch back to overall view, select budgets input to, Copy cumulative, reselect busgets, total up.  Its a very error prone and long winded process in my opinion, and I'm hoping theres a better way to get them in?
    We only have 1 year available in each annual program so the overall and the annual figures will always be the same.  do I need to enter the figures in both views?  can I just use the overall view, or is there another neater way to do them?
    2. If I go for entering overall values only, are there any implications on budget distribution, Availability control, or reporting?
    3. There may be times when we agree to proceed with a project that was not budgeted for.  If a distribution exeeds the budget total, it generates an error message, can this be reduced to a warning?
    Thanks for any advice
    Graham

    I'm afraid I still haven't found a solution to this very poor transaction, and as I've had no responses, I'm doubtful I will get one.

  • Internet Download Manager cannot integration with firefox4 itis Look in the menus it works but it does not actually work ?

    internet Download Manager cannot integration with firefox4 its Look in the menus it works but it does not actually work

    IDM may need to be updated to work with Firefox 4.0. You could contact them and make them aware of the problems you are having with their program.

  • Authorization for Investment Management program positions by Plant Code

    Hello!
    I am looking for a way to restrict data on Investment Management reports (program positions) by plant code. I found the following auth objects, but none for plant code:
    Company code (A_IMPR_BUK)
    Business area (A_IMPR_GSB)
    Controlling area (A_IMPR_KOK)
    Profit center (A_IMPR_PRC)
    Persons responsible (A_IMPR_VER)
    Any advise?
    Cheers,
    Alex

    Refer BPGE, BPJA.
    Regards

  • Investment management : which module

    Dear SDN,
    I would like a clear view as to which module Investment management comes under.
    Is it part of Fi or controlling?
    or is it an independent module by itself using controlling and fixed asset sub module of  FI.
    Regards,

    The application component hierarchy classifies IM as its own module under the Accounting area (AC).  I would consider the APCO to be the official designation of such a question.
    AC:
    - FI
    - CO
    - EC
    - TR
    - IM
    - PS
    - RE

  • AUC measure in investment management

    Hi Experts,
    i have the below requirement for AUC measure in investment management can any one please guid me how to configure for this.
    u2022 Ability to create unique capital projects that could be made up of multiple fixed assets (New Store Opening, New DC, Office Remodel, Software Implementation)
    u2022 Ability to forecast the time period / month the cash outlays will take place
    u2022 Ability to report on Capital Project achievement in relation to planned time frame as well as in relation to Budget
    u2022 Ability to assign capital projects to individual company codes and cost centers
    Thanks in Advance.
    RVI

    Check here all nodes
    SPRO-Financial Accounting (New)-Asset Accounting-Transactions-Capitalization of Assets under Construction..................
    Srinivas

  • Investment Management Configuration Materials

    Hi All,
    Could you pls provide me the related documentation for the entire process flow as well as the Configuration Document for the Investment Management for my mail ID :[email protected]
    Thanks in advance,
    Edu

    hi
    see below link for config of Investment management
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/IM/IM.pdf
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/MYSAP/SR_IM.pdf
    nagesh

  • Tables in Investment Management

    Dear All,
    We need to develop an ABAP report for Budget distribution in investment management in the format specified by the user. The client uses Investment management for budgets in Marketing budgets.
    I got tables IMTP, IMPR, IMPU for Investment program, position id etc.
    But I could not find the tables where the Budget amounts get stored when we distribute amounts in Tran.Code IM32.
    Please tell me the tables where Budget amount, Distributable, Distributed etc get stored when we post IM32.
    Reply me soon.
    Thank you very much in advance.
    Vishnu,
    VST-IT.

    Hi,
    When we assign budget in IM32, lower level WBS budget will be total up to Top Level WBS, which can see in Distributed.
    My question is If we add budget at Top level WBS at certain intervals, that total budget added will be available in DISTRIBUTABLE.
    Is there any Distributable report which can help me how much is added at each interval and distribution of that budget.
    Please help me with Tables / Report which can give us the detailed information.

  • Tables for Investment Management

    Dear All,
    We need to develop an ABAP report for Budget distribution in investment management in the format specified by the user. The client uses Investment management for budgets in Marketing budgets.
    I got tables IMTP, IMPR, IMPU for Investment program, position id etc.
    But I could not find the tables where the Budget amounts get stored when we distribute amounts in Tran.Code IM32.
    Please tell me the tables where Budget amount, Distributable, Distributed etc get stored when we post IM32.
    Reply me soon.
    Thank you very much in advance.
    Vishnu,
    VST-IT.

    Refer BPGE, BPJA.
    Regards

  • What is RPM portfolio Item in Investment Management?

    Hi All,
    We are trying to install business content for Investment Management module. There is a web template in this module, we have installed all these properly. Now when i run this template i see a message "No RPM portfolio Item has been specified".
    In the underlying queries there is info object Item Detail on which a SAP Exit variable. I tried to study the SAP Exit code but this is not of much use. Even while debugging the query the value for this variable is not being set.
    So i wanted to know more about RPM portfolio item, what is this, where do we have to set/specify it?
    Any inputs are highly appreciable.
    Thanks,
    Anjum S N.

    Hi,
    May help you:-----
    http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/00cfa0ca-f11c-2a10-eb8f-b69a103f6caa?quicklink=index&overridelayout=true
    Regards,
    Suman

  • How to process Fisacl year change for Investment Management with Project?

    How to process Fisacl year change for Investment Management with Project as measure

    hi
    check this menu path
    Accounting  --> Investment Management  --> Programs  --> Periodic Processing  --> Fiscal Year Change

  • Process step for Investment Management

    Hi SAP Gurus
    Our client is into BOT projects - Build, operate adn transfer projects.
    Till the time of transfer the asset is the property of our client. So the client builds an assets, maintains & operates and transfers the rights only after certain years.
    For this I am suggesting using Investment Management module but I am not very clear on the process steps right from creation to Investment order for project - build & for operation.
    Request you to suggest me the process steps.
    Thanks,
    Srikanth

    Hi,
    For more information about Investment Management, click the below link.
    http://help.sap.com/saphelp_47x200/helpdata/en/2a/f9f273493111d182b70000e829fbfe/frameset.htm
    regards,
    Venkatesan Anandan

  • BAPI in Investment Management

    Hello
    Could you please help me in getting the BAPI to upload 'Budget Distribution' ( IM52 )  in investment management ?
    I am also looking for a BAPI to load data for transaction IM32 ( Change Original program budget ).
    Please let me know, if anyone is aware of the same.
    Thanks
    Sarang

    Hi this are the BAPI's use for the Investment programm.
    BAPI_INVPROGRAM_CHECKEXISTENCE Check Existence (of Sub-Tree) of Program
    BAPI_INVPROGRAM_GET_LEAVES     Output End Nodes of an Investment Program
    BAPI_INVPROGRAM_GET_REQUESTS   Output Appropriation Requests and End Nodes of an Investment Program
    BAPI_INVPROGRAM_SAVE_ENTITIES  Save Assigned Entities in Summarization Database
    BAPI_INVPROGRAM_SAVE_VALUES    Save Summarized Values in Summarization Database
    BAPI_INVPROGRAM_SELRE_ENTITIES Select Assigned Entities and Replicate Them in Summarization DB
    BAPI_INVPROGRAM_SELRE_VALUES   Select Values, Summarize Them and Replicate in Summarization DB
    Perhaps you will get better result in ABAP forum.
    Regards
    Nitin
    Edited by: Nitin  Patoliya on Dec 3, 2008 6:42 PM

Maybe you are looking for