Investment Program in Budget Profile

Hi Experts,
I would like to know on how to create and assign an Investment program in Budget profile.
Is an investment program mandatory for Investment Project and for New Product Development Projects?
Will there be any implication if we do not assign an Investment program in Budget profile settings in OPS9.
Please suggest & advise.
Thanks & Regards,
Kabir

Hi Virendra,
Thank you for the reply.
Please clarify this in your 2nd sentence, "if you do wnat to budget for opex in your project" . Is it do or do not want to?
Awaiting your reply.
Regards,
Kabir

Similar Messages

  • Creation of Investment program and budget upload

    Hi,
    I need to create a investment program using th data in a excel file. Once the structure is uploaded, I need to do the budget upload. Is there any BAPI for achieving this functionality. Kindly share your valuable inputs if you have worked on similar kind of requirement.
    Regards,
    Mamta

    To find out bapis , go to BAPI transaction - take the alphabetical order tab - find your business object ( budget ) - on the right side you will see the tools option - create bapi select and click the search button.
    This will give you all the bapis associated with that business object.
    Also searching SE37 with BAPI_EXPENDITURE* will be good idea.
    Mathews

  • How to release investment program  budget

    Hi expert:
            We distribute original  budget  in investment program using Tcode Im32,  but our customer  require to release
    original  budget ,  because  two position require to approve this budget.  
             We use Tcode Im52 to distribute budget to project,  our customer also approve this operation. but i donot know
    whether the system provide standand release function.
            how to  realize this two functions?     thank you

    You are distributing  budget from Investment prog.  to project.
    In IM there is not concept of Budget release. If you want to control your budget at Release  ( which is called Active budget control ) you have to does the same in PS.
    Your flow would be like that
    IM32 :Change origional Prog. budget
    IM52 : Budget distribution from Prog to measue i.e. Project/ WBS.
    CJ32: Change release Budget. ( so, sys will check budget against this release budget ) 
    For using Release budget funcation you have to activate avalability control in your Budget profile (OPS9 txn ) for the Release & assign that budget profile to budget profile.
    Refer this online material
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/c4/5dbfa8e7cc11d496eb0000e835339d/frameset.htm
    Regards
    Nitin

  • Budget Return to the Investment Program (module IM)

    Hi All,
    I need your advice regarding my case :
    *. My company use PS (project and allocate the budget in WBS) and also Investment program.
    *. There are some unused budget in 2005 and 2005 as well as some PR/PO in 2005,2006 (open commitment). They want their budget can be used in 2007 thru investment prog or in other words, the unused budget can be return to the pool/investment prog.
    *. The company policy doesnot allow to do the carry forward budget.
    Plz correct me / give some ideas about my plan :
    1. I suggest them to force close all PO 2005/2006 on this year . as well as delete all PR. Then, close the project/wbs . Therefore, there is no posting anymore in particular project/wbs.
    2. Automatically,there will be no commitment. All money will back to available budget in 2005/2006.
    3. I suggest them to do the budget return (IM52) to the investment program.
    4. As a result, the unused budget in 2005/2006 will be back to the pool/investment program and can be distributed to 2007.
    Do you think this one a good solution ? plz give me another ideas regarding this case. Really appreciate.

    Hi,
    you might use budget carryforward.
    Check out IMCAOV in IM and CJCF / CJCO in PS.
    Cheers
    Hein

  • Carry Forward of Budget in Investment Program

    Dear Experts
    I am trying to carry forward the budget of the Investment program from FY 2010 to FY 2011. I have used IM27 for copying the program structure and Internal Orders. The Budget Values, Commitments of IO has been carried forward but I am not able to carry forward the budget at the Position ID and NODE Level.
    Kindly help.
    Vikash

    Hello,
    You can run the BPCARRY01 program to copy the most recent budget structure to a target year. In doing so, you no longer have to maintain BS elements that already exist.
    You execute the program, under Accounting - Public Sector Management  - Funds Management - Master Data - Budget Structure - Former Budgeting  -Transfer from Previous Year. This is, as Eli said, FM9Z.
    Helene

  • Copy Internal Order between Investment Programs

    We have a investment program in approval year 2014  which has 1 Internal Order assigned to it and the budget has been fully allocated.  We want to budget against this internal
    Now we have created a new investment program in approval year 2015 and want to the use the internal order(measure from the invesment program in 2014. We have tried the following:
    IM22 Change program - assignments add internal order get error message "There is already an existing assignment to program position 2014"
    IMCAOV Budget Carryfoward - No impact on the measure as there is no budge to carry forward.
    Can anyone advise how we can budget on the same Internal Order in the new fiscal year ?
    thanks
    Joe

    Hello,
    the little late answer to your question is the table IMZO. It links the investment program / positions to internal orders. I found this thread while searching for my own problem which is quite the same:
    In my WebDynpro for ABAP investment planning tool I'm using the FM BAPI_INTERNALORDER_CREATE to create internal orders as a result of the planning process. This BAPI is similiar to the transaction ko01 except that I can't assign an investment program / position to my internal order (this is also pointed out in the help to the BAPI/FM).
    But how can I assign an investment program / position to my internal order NOT using an ABAP insert/update statement on the table IMZO (which links the internal orders and investment programs/positions).
    Does anybody know a FM or BAPI I could use? I really don't like the idea of a self made insert/update into a sap table...
    Thank you in advance,
    Christian Bracht

  • Not possible to delete link investment program position from Appropriation request

    Dear specialists,
    We have a problem with deleting a linked investment program position in an appropriation request (IMA3, IMA11 or IMA12).
    We could edit some of the appr.req.'s but a few give an error.
    Steps done:
    We deleted the status BUDG from the linked projects (budgets deleted and OPSX for deletion of status).
    The we run the IM27_repeat.
    For the most of the appr.req.'s the linke was removed (table IMZO).
    For a few of our req.'s the link is not removed so that we can't link the new progr.pos. to this appr.req.
    Regards,
    Marcel

    Hello Marcel,
    Please check Customizing of the investment program type under 'assignable operative objects' in t-code OIT3 or in following path
    SPRO --> Investment Management --> Investment Programs --> Master Data --> Define Program Types
    Also check in following SAP note
    130216 - Program position not allowed for measure
    Regards
    Tushar

  • Changes to investment program

    I've made a few changes to the investment program, throguh t-code IM05. I can see the changed made through t-code IMV2, but I cannot select the measure code to see those changes. That is, I can select the position ID of an investment program and see what happenede to it, but not the project number.
    My question is, does anybody know if there is report which tells me the reassigments of measures made? That way I could answer this question: Where has the project xxxxx been assigned in the last year?
    Thank you all

    HI,
    db profile 000000000005 doesn't exist....
    000000000001     Std profile: structure overview (desc.)
    000000000002     Std profile: structure overview (sched)
    000000000003     Std profile: structure overview (d/s)
    000000000004     Std profile: structure overview (d/s)
    1                             Std profile: structure overview (desc.)
    2                             Std profile: structure overview (sched)
    3                             Std profile: structure overview (d/s)
    4                             Std profile: structure overview (d/s)
    SAPPS_EV0001     Std profile: earned value analysis
    I've tried all and , unless I'm doing something wrong, I don't get it....

  • Change in budget profile

    Dear Gurus,
    Greetings,
    Please suggest me can I uncheck overall budget values in budget profile. already we have been using budget profile which is both oevrall values and annual values is checked. its configured 2 years back. Now I want to use on annual values budget profile.
    My querries is can i uncheck over all values in between project duration?, is there any adverse impact on project? , wheteher any reconstruction program is needed for the exixsting project?
    Please revert.
    and thanx in advance

    Hi,
    mohd ansari wrote:
    My querries is can i uncheck over all values in between project duration?, is there any adverse impact on project? , wheteher any reconstruction program is needed for the exixsting project?
    Impact: No impact on existing project budget consumption. Budget profile changes will impact project if you was using only annual or only overall. And also that needs some manual work.
    Reconstruction Needed: Yes, it will correct if some inconsistencies occur. Run CJEN and CJBN in sequence after changes in budget profile
    Note: Don't forget to run a cycle in testing server to double sure.
    Regards
    Shishir

  • Investment program management

    Currently my company's configuration of SAP handles investment programs in the following way:
    - All investment program are managed within the same investment year. In doing so, the entire investment program remains open until the last project is closed. (N investment programs, 1 time period)
    The plan is to manage each project within its own investment year. (1 investment program, 1 time period). In this formulae, the investment program contains the suprlusses of previous years as well as new budget allocations).
    What are the advantages of the proposed plan? How would this impact corporate functions like Administration, Asset Controlling, Engineering etc. ??
    Best Regards,
    Veronica

    Hi Veronica,
    I am afraid your question is not clear enough.  Please try to rephrase it and maybe giving any specific examples might also help.
    Investment programs do not need any start or end dates, they are endless under business continuity principle.  You can have for example one for CAPEX and one for OPEX (it does not really matter that they called "Investment", at the end this is the tool for budget/program management) per country.
    Kind regards,
    Paulo

  • Assign Investment program Position for IW31 through exit/BADI

    Hi
    My requirement is, I've to assign investment program details to Maintainence order (IW31) in creation mode through enhancement. I am able to do so in change mode using the FM "AIPP_ALLOCATE_POSITION_DARK", but when I use the same FM in creation mode it is throughing "Update Termination " error.
    Please let me know is there  any BADI/User Exit/Enhancement Point to achieve the same.
    Regards,
    Chandu
    Edited by: Poorna Chandrasekhar on Nov 13, 2009 11:10 AM

    I've created enhancement point in the FM CO_ZV_ORDER_POST

  • Assign Plan/Budget profile to Internal Order

    While executing KO22 for particular internal order for order type 0800, I am getting the error - Assign Plan/Budget profile to the object.
    GMR

    hi
    while defining the order type in IMG ,you have to define the buget profile and then check
    regards
    thyagarajan

  • Archiving error message - order linked to old investiment program

    During CO-Order object archiving, error message saying that order is linked to investment program. Check it is an 2001 old investment program. Tried, but could not settle balance/order. Is there any CO flag to allow access to 2001 investment program?
    Thanks.

    During CO-Order object archiving, error message saying that order is linked to investment program. Check it is an 2001 old investment program. Tried, but could not settle balance/order. Is there any CO flag to allow access to 2001 investment program?
    Thanks.

  • Budget Exceeded Issue - Activated budget profile for existing project

    Dear Experts,
    I have a Project and not using any budget profile, already actual data exist only in CJI3 no data in CJI5.
    Now I assigned Budget Profile in that project.
    While entering Budget in T-code CJ30, I can see values in assigned values for a wbs elements.
    Example -
    WBS Element - XXXXXX-02  - 2000 (Assigned) - Here Budget Profile not assigned in the project
    Same WBS Element - Once Budget Profile assigned, when am assigning same 2000 budget am getting budget exceeded issue.
    If I give 2500 I am not getting any errors, My tolerance as only Warning message.
    Please Suggest - Screenshot attached
    Thanks,

    Hi Pavan,
    As soon you enter your budgeting fig the availability control triggers, this check your assignment with available budget.this the reason you are getting error as you say there are already actual posting in CJI3.In this you need to balance first the fig which is appear in assigned column in CJ30.
    Its a good practice to give budget first release it & then start procurement,confirmation etc.
    Check this in budget profile availability control.
    Regards,
    Sachin.

  • Planned costs for investment program

    I am having a problem configuring planned costs for inv program positions, which should reflect as the planned cost for the investment measure being created.
    Appropriation request is being used in the scenario to create measures automatically. these measures will require to have the same plan values as the position to which they are assigned.
    Please help.

    The Measure is the cost collector through which spending will be controlled & measured, which is a key integration object with IM.
    WBS Elements are the collectors associated with PS, whereas IO’s are cost collectors found in the CO module.
    The Measure is always assigned to the lowest program position within IM. Program Position is found on Investment Program Hierarchy at its lowest level which may relate to a capital project or project component.
    Hence accordingly the appropriation request serves as a tool to plan the spending and which is therefore upon approval becomes the Measure for the IO or WBS.