Investment Support Measure-Settlement of IO to AUC

HI Gurus,
I have created investment order and AUC asset through ko04. Also crated budget for this IO in k022. posted invoice through fb60 to this IO. Now i am trying to maintain settlement rule in IO master data. (Settelling to the AUC created for this IO)
While maintaining settlement rule, system gives following error message:
You cannot post to asset 900014 0 (investment support measure)
Message no. AA311
However if i do settlement through KO88 settlement is done automatically (Test Run).  I want to maintain seetlement rule in Ko04
Please Advice.
Regards,
Shekhar
Edited by: Shekhar Sonar on Mar 29, 2010 1:10 PM

Hi,
Your order is not statistical because you cannot maintain settlement rule for statistical order.
Even you see all the entries are displayed, can you check the order balance?
KO03 > Extras > Order Balance
The message informs you that the settlement is done, and there is no balance.
If you need to know when the settlement is done, please check the settlement rule > First used & Last used field.
You can also check the cost analysis as below to see the cost movement for order.
KO03 > Extras > Cost Analysis

Similar Messages

  • You cannot post to asset 150000 0 (investment support measure)

    Hello All,
    I am getting Error while doing KO02 Order settlement
    I selected Cat - FXA and select asset (asset under construction)
    When I am trying to save
    You cannot post to asset 150000 0 (investment support measure)
    with Message Number Message no. AA311
    Regards,
    Kiran.

    Hi,
    You cannot directly include settlement rule for AUC. This is automatically included after settling.
    1. Create an Internal Order through KO01 and from that Extras --> Create AUC.
    2. Then you post expenses to AUC.
    3. You settle the IO through KO88. When you settle the internal order automatically it would be settled to AUC which is in IO.
    4. Check the IO you can see the settlement rule with AUC line item
    5. Now select FXA rule and select the final asset.
    This is will solve your problem and this is the procedure.
    Thanks & Regards,
    Giridhar Reddy

  • You can not post to asset xyz ( investment support measure) ??

    Hi Guru's,
    I am trying to post some spending reclassed to an already capitalized asset. So in order to do this I have reactivated the project, resettled the spending to the asset and now I am trying to finalize the settlement to the asset by using tcode: CJIC... but keep getting this a hard error message:
    You can not post to asset xyz ( investment support measure) .....
    Any idea how I can resolve this ?
    Please help !! Thank You
    Best Regards,
    Yasmeen

    hi,
    it would be better if you write error message number in thread.
    hope you are using im module. if so check the system stastus of appr.request and try to settle to auc.
    check and do revert.
    regards,

  • Documentation on Investment Support Measures

    Hi All,
    Thanks In Advance
    Please I am in urgent need of Documentation on Investment Support Measures b'coz I have to configure the same in my US Project
    Regards,
    KAMAL KP

    Hello Raghu
    Please read the overview from this SAP link and explore and the other topics.
    http://help.sap.com/saphelp_47x200/helpdata/en/2a/f9f273493111d182b70000e829fbfe/frameset.htm
    Reg
    assign points if useful

  • Amortisation adjustsment for Investment Support measures

    I wonder if you can help?
    We have been doing some asset reclassification and changing useful lives etc - we have no problem in adjusting the depreciation up and down using ABAA (unplanned depreciation) and ABZU (write-up i.e. reduce depreciation).
    However, we are struggling with amortisation on investment support measures!
    We can increase the amortision using ABAA no problem.
    BUT we seem unable to reduce it - we have tried lots of combinations under FB05 and although we can adjust the gross value (and therefore the net book value is OK) we need to adjust the cumulated amortisation.
    Has anyone got any ides?
    Thank you in advance.

    Hi,
    In your case you have to create a TTy like in note 67448 descibed  (Lxx (xx for the investment measure) like note 529678 'name convention')  and post the amount with ABIF.          
    Regards Bernhard

  • Investment support measure

    Hello!
    I defined measures for the investment support with the transaction ANVEST, and i put a maximum percentage rate for the investment support.
    When using the transaction ABIF to post an amount for the investment support, the system does not check the amount posted against this percentage.
    Can someone help me?
    Many thanks!
    Kind regards,
    Chiachen

    Is your problem solved? If not, have you defined a base area within your invst support measure? Which area you are posting this against.. area 41 or 51? SAP usually will not allow you to post investment support of more than 100% of the base area... if you post more than 100% of support means that your asset value is negative.
    Let me know if this helps.

  • Configuration setup forLow Value asset 'Investment support measures'

    Hi all
    User requested us to enable the u2018investment support measuresu2019 option for low value asset for that if any configuration setup is required to enable the option for low value asset.
    Please help us to resolve the above issue and attached screen shot for your reference.
    Note: In high value asset user is able to view the u2018investment support measuresu2019 option.
    Regards
    K.Gunasekar

    Thanks
    1. Our current requirement is adding new grant book leg to LVC Classs.
    2. what will be the impact to our existing assets database?
    if not can we follow the below step
    we will need to create new LVA class so that grant book leg for LVA can be created. In this case, we will need to transfer assets from the existing LVA class to new LVA class. 
    Please clarify

  • Settle an AuC with investment support

    Hello Gurus,
    I have the following problem:
    I have some AuC with investment support measure assigned.
    If I settle the AuC created in prior-years the system settle the costs and the investment support to the final assets but If I try to settle an asset created this year, the system does not settle the investment support to the final asset.
    I need that when the asset under construction is created and settled to a final asset (within the same year), the investment support iis posted to the final asset aswell.
    Thanks alot for your help.
    Christine

    Normally settlement  needs to be performed twice, if the investment support measure is there.
    1) for Investment object to AUC ie WBS / IO to AUC. This called automatic /AUC settlement.
    2) From AUC to Final Asset: This is called final / periodic settlement.
    But both these settlement needs to be executed with KO88/ CJ88.

  • How to post a reduction of Investment support creted by ABIF?

    Hi All,
    in 2010 for an asset Iu2019ve posted an Investment support, by t.code ABIF.
    In 2011 a part of that Investment support has been revoked.
    Could anyone tell me how to post this reduction? Which t.code? Which transaction type?
    My investment support measure is u201CZIu201D. For this measure, SAP has created the tree follows transactions type:
    - IZI
    - JZI
    - KZI
    My SAP release is 6.0
    Thanks for your help.
    G.

    Hi : )
    I know this thread is quite old, but I recently had the same problem and was able to change an automatically created transaction Type eg. I, J and K using transaction AO73_INV.
    This allowed me to copy transaction type K and I was able to conigure my own transaction type for investment support which now allows posting of investment support refund without the retirement of the asset and reduces the amorisation as expected.
    Hope this helps : )
    Tanja

  • Investment support

    Hello,
    I'm having the following problem, I'm trying to create a new transaction type for investment support measure like K61 but with an inverse sign (instead of being a credit transaction it should be debit). Nevertheless I'm not succeeding because I can't find a way to create a new transaction type in support investment...
    Can anyone help me, please?
    Thank's in advance.

    Hi
    When you create  Define Investment Support Measures it create automatecly transaction types.
    You can manual make little changes on it.
    The transaction types that are created like:
    EI1 Capitalized asset Credit
    II1  Capitalized asset Credit
    JI1  Deactivate asset  Debit
    KI1 Credit transaction
    I never found a way to create new one's, i think these are direct linked with the Investment message and that when you found a way to create one you can't use

  • How to repay Investment Support on the asset? thru which TTY?

    Hello guys,
    Have anyone used TTY J01/J02 to repay investment support? Because SAP does not allow you to configure custom TTYs under tcode AO83 for repayment of invest. supprt. and J01/J02 uses TTy group 52 "Extraord. write-off invest supprt" which gets classified as unplanned depreciation under Area 41 instead of reducing the Investment support posted under same area 41. Is this the correct way of repaying/refunding?
    If not, what TTY to use to refund or repay the support (either partially or fully) and if there is any way to customize TTY specially for repaying/refunding this support.
    Open for any suggestions.
    Thanks,
    Kartik.

    Hi Kartik,
    You have first to Define Investment Support Measures. In the asset in the tab allocation you have to fill in the investment support  area.
    When you save this it will create direct a transaction type that you have to use:
    In our case I have:
    I1     Investment Support Area 81 US GAAP
    I2     Investment Support Area 82 LO GAAP
    Created the transaction types:
    EI1     Investment Support US and LOCAL GAAP
    EI2     Investment Support LOCAL GAAP
    With EI1 I post in I1 and I2 and with EI2 only in I2
    When you want I can sent you some screen shots (see me bussines card how to contact me)

  • Distribute AuC (Investment Measures) to a number of AuCs  AIAB, ABUMN

    Dear All,
    maybe you can help me with this problem we have here:
    Why isn't it possible to define an Asset Class (TCode OAOA ) as an Investment Measure ( ANKA-XINVM ) and line item settlement ( ANKA-XOPNVW ) at the same time (i know that a radio button allows only one of it).
    So that you are able to distriubte/split defined Investment Measure AuCs to a number of AuC with the TCode AIAB (the usual way to distriubte normal AuC to a number of AuCs).
    The TCode ABUMN isn't able to distribute/split one AuC (Investment Measure) to a number of AuCs.
    Maybe some has a solution for me.
    Thanks for your help!

    First of all thanks for your help.
    I have done your suggestions already. But my problem is, that I have an AuC (which is defined as an investment measure with an investment profile and the transaction type 348/349). On these AuC i have some values from an internal order (settled on the AuC with KO88).
    Now I have to move the values from the AuC wich has the Asset Class 1520 (AuC as investment Measure) to a number of  finished Assets (i.e. xxxx, yyyyyy) with the Asset Class 1161 Machinery.
    And with the TCode ABUMN wich is mentioned in the SAP library for the investment measures you are only able to transfer one asset to another asset.

  • How to settle the expenses after AUC has been capitalised.

    Hi All,
    I have a understanding that after AUC has been settled, we can edit the settlement rule in WBS element and settle directly to the capitalised assets.
    I can not see the settlement rule but investment profile since the project being a Capital comes from Investment measure and automatically created.
    Can you tell me how to create a new settlement rule in this case. It is Urgent
    Regards
    VK

    Hi Vijay,
    This requires a change in the settlement rule since the AUC is no more and it must be the settlement reveiver earlier which should be changed to the main asset after capitalisation.
    Please go to Transaction code CJ20N, select the WBS and go to settlement rule via edit > Cost and set the receiver as the fixed assets itself instead of AUCV since AUC has been transferred to main assets.
    You can then settle using CJ8G or CJ88 but CJ88 is a better option.
    I think, I have answered the same query.
    Regards
    Bharat

  • How to post a reduction of Investment support posted by ABIF?

    Hi All,
    in 2010 for an asset Iu2019ve posted an Investment support, by t.code ABIF.
    In 2011 a part of that Investment support has been revoked.
    Could anyone tell me how to post this? Which t.code? Which transaction type?
    Thanks

    Hi,
    To reverse investment measures is described in notes 67448 and 529678.  
    you have to create a transaction type and post the amount with ABIF (note 67448)                                            
    Please follow not 529678 in creating the new transaction type.
    Do not hesitate if you have further questions.
    regards Bernhard

  • Without IM how can i settle construction project to AUC and asset

    Dear all
    without IM, how can i settle construction project to AUC and asset.
    can someone explain it in details?
    thanks a lot.
    Judy

    thanks for all of your answers.
    i create the investment profile and assgin it to the project profile.
    when i release the project, i see the system status changed from crtd to release and AUC.
    when i do cj88, the costs are settled to the AUC No. automatically.
    could you tell me how the AUC No. is created? where does it configure?
    when AUC is settled to FXA, what are the procedures?
    first TECO the project and then do CJ88, am I correct?
    thanks a lot
    Judy

Maybe you are looking for

  • How can I insert into a view cache???

    I have a problem in JClient like that: A form that have 3 JTable: - Table1 get data from UserTable in DB - Table2 get data from GroupTable in DB - Table3 get data from GroupTable in DB and 2 buttons: btnAdd, btnRemove. When I select a row in Table1,

  • My hp laserjet m2727nf will not work until i shut off power and power back on.

    My laserjet will not work until i power off then power on after every printing job. It first started happening over the weekend when it sat idle for 2 days. Then it was once a day and now every time i need to print. What could be the problem?

  • To create a procedure in a procedure

    Hi, I am trying to do sth like this. I am trying to create a procedure within an anonymmous PL/SQL block and i am basically trying to execute the newly created procedure there. This example (although wrong) would give a fair idea of what I am trying

  • Apple news mails in wrong language

    For a while I keep receiving mails from [email protected] in dutch whereas my appled Id preferences indicate english as communication language. How / where do I have to set up the language for these mails ?

  • Where can I download Adobe Encore full version for CS6? Any link?

    I would like to reinstall Adobe Encore CS 6 Full version? Where do I find download link?