Invoice verification with reference to purchase order

Hi experts,
May I know is there any setting or configuration that control the data/field copy from purchase order to invoice in MIRO during invoice verification?
How do we control which field should be copied? If I add another new field in purchase order, how can I make sure it is copy over to invoice in MIRO during invoice verification?
Thanks & regards,
JT

Hi Andra
Thanks for your reply.
Actually what I would like to do is that I added a payment method field in PO. And I would like the payment method to be copied into invoice automatically when we perform the Invoice verification in MIRO instead of manually enter.
Is there anyway to do that?
Thanks and regards,
JT

Similar Messages

  • MIRO posting with reference to Purchase Order

    Dear Experts,
    I've created a Purchase Order with reference to a purchase requisition. Now I want to post MIRO with reference to this Purchase Order Number to give payment to Vendor mentioned in Purchase order. But when I going to post miro amount not coming which I mentioned in Purchase Order!!
    How can I post MIRO with reference to Purchase Order Number? Is it possible?
    Best Regards.
    Ripon

    As above it sounds like a GR gasn't been posted but you can still process invoice.  Just manually enter the quantity and value as per invoice.
    Note the invoice will block for payment pending the GR.
    See transaction MRBR if you want to release the invoice for payment immediately.
    Regards,
    Nick

  • Payment Posting with Reference to Purchase Order

    Dear Experts,
    I've created a Purchase Order with reference to a purchase requisition. Now I want to post MIRO with reference to this Purchase Order Number to give payment to Vendor mentioned in Purchase order. But when I going to post miro amount not coming which I mentioned in Purchase Order!!
    How can I post MIRO with reference to Purchase Order Number? Is it possible?
    Best Regards.
    Ripon

    >
    riponkp wrote:
    > Dear Experts,
    >
    > I've created a Purchase Order with reference to a purchase requisition. Now I want to post MIRO with reference to this Purchase Order Number to give payment to Vendor mentioned in Purchase order. But when I going to post miro amount not coming which I mentioned in Purchase Order!!
    >
    > How can I post MIRO with reference to Purchase Order Number? Is it possible?
    >
    > Best Regards.
    > Ripon
    Seems like you are doing MIRO before GR. If GR is done, it will pick the amounts, if GR is not done, the amounts are not picked. You enter the amounts manually with reference to PO.

  • Report for gl accounts with reference to purchase order

    hi
    experts
    Is there any report which can give the gl accounts with reference to purchase order
    thnx

    Use t code ME2N and click 'Account Assignment" from application tool bar or press Shift + F12 to view PO with GL code. If GL code is not showing select from the layout.
    Rgds,
    Vijay

  • Can we create outbound delivery with reference of purchase order

    Hi All,
    can we create outbound delivery with reference of purchase order?

    dear friend,
    as far as i know you can create it with the following references:
    -to sales order;
    -to STO;
    -to subcontract order;
    -to project;
    -without any ref
    are you talking about stock transport order ?
    regards,

  • Goods Issue with reference to Purchase Order

    Hi MM Gurus,
    Is there any settings to do Goods Issue with reference to Purchase order?
    I want to capture the material price in purchase order during goods issue instead of standard price or moving average price.
    Thanks in advance
    Dinesh

    Hello Dinesh,
    Batch valuation is similar to split valuation. Here is the link on how batch valuation works.
    http://help.sap.com/saphelp_47x200/helpdata/en/25/283db54f7811d18a150000e816ae6e/content.htm
    Please check in sandbox environment before using.
    Hope this helps.
    Regards
    Arif Mansuri

  • Function module to create Inbound delivery with reference to Purchase Order

    Hi experts,
    I want to create Inbound delivery with refernce to Purchase Order. But I want to create item wise. For example If one purchase order is there with 10 line items. 10, 20, 30, 40, 50......100.
    If I am showing report for Purchase Order with select option and if I select first 5 line items 10, 20, 30, 40, 50 then my program should be create one Inbound delivery for selected line items only. I have tried BDC for Tcode VL31N, but its not worked. Is there any Function module to create Inbound delivery with reference to Purchase Order for selected line items????????

    Hi,
    Try FM RV_DELIVERY_CREATE or GN_DELIVERY_CREATE.
    For creating a delivery wrt PO u 1st need to have a sales order i guess.
    Regards,
    Amit

  • ARE-1 form with reference to Purchase Order

    Hi All,
    We are having a scenario where we need to send the ARE-1 to our vendor along with CT1. I have tried assigning the Purchase Order as reference document for creation of ARE-1 but its not working.
    Can anybody suggest the way to create ARE-1 with refernce to Purchase Order?
    Rgds,
    Antima

    Hi Rithvika,
    Yes the scenario is for merchant export. Here we are the customer and along with our purchase order, we need to send CT1 and ARE-1 to our vendor. The ARE-1 series has to be same as for our direct export, so i need to create an ARE-1 with reference to Purchase Order.
    If anybody has any idea how to do that and whether its possible in SAP then please guide me.
    Rgds,
    Antima

  • Purchase Order with reference to Purchase Order

    Dear SAP Gurus,
    Can it be possible to have a purchase order with reference to purchase order.
    Regards
    Vinod Kakade

    Hi,
    there is an option to give document date in the Purchase order selection in Document overview, what you can do here is that you can get a TVARVC variable created with date range of today - Today - 179 Days, in the attributes of the variant enter the TVARVC variable so that when the user uses this variant, he will get PO's only for that date range, if you  have any confusion on this then please speak to your ABAP Consultant.
    Regards
    Chandra Shekhar

  • Invoice verification with reference to billing document in cross company

    Hi Gurus,
    We need to do "Invoice verification with reference to billing document in cross company code scenarios".
    At present I am processing through MIRO by calling the PO.
    What is the alternative for this and how to do it?
    Thnx

    Hi
    It is not possible to do the invoice with reference to billing document.
    You can create the Invoice referncing the PO used for STO or the delivery note (as mentioned in the Material document) or directly on the vendor.
    Thanks & Regards
    Kishore

  • Consignment withdrawal with reference to purchase order

    HI All,
    In case of consignment withdrawal i.e. 411 + K ; is there any way by which we can tie this withdrawal with the consignment purchase order that brought the material in inventory?
    THanks,
    Ritesh
    Edited by: Jeyakanthan A on Nov 15, 2011 9:14 PM

    Hi Ritesh,
    This is not a standard functionality but you can most certainly achieve this thru customer enhancement (A Badi or FM exit) for the transaction code.
    Please take help from your ABAP team!
    Thanks,
    Reetesh

  • Invoice verification with reference to material document

    Dear Experts;
    i want to make invoice verification (MIRO) with reference to good receipt document not the all quantity in the purchase order. is this possible ???

    Hi,
    Option - 1
    If you have done 3 separate GR's for the above qtys then if you do MIRO with reference to PO then 3 line items will appear with the respective qtys. You select the one you want & delete the rest.
    Option - 2
    Check whether you have entered any values in the delivery note field while doing GR. If yes then do MIRO with reference to Delivery note rather than PO so that qty in the GR material doc will flow to MIRO automatically.
    Thanks & Regards,

  • Invoice verification(MIRO) for blanket purchase order

    Dear All,
    I am tring to enter invoice via. MIRO againest a blanket purchase order. The blanket purchase order is a Frame workorder  with account assignment category 'U' & item category 'B'. I am getting error 'Enter G/L Account'  while entering invoice varification in MIRO.  I am entering the Amount in the 'Acct assgt' column (error mark). However the GL account & cost center field is gray out. System not allow me to enter the GL account & cost center in MIRO. Also I am unable to change the account assignment category from 'U' to 'K'  in MIRO.
    Can some one guide me how to resolve the above problem.
    Your earlier input would be highly appriciated.
    Thanks,
    spsahu

    Hi
    Please check the Variant being used as per the Standard All the fields are in Entry Mode only.
    Please use the Layout  7_6310 All information & Check
    Check in OLMRLIST  the Layout for transaction MIRO & Program SAPLMR1M
    Please ensure that you use Document type FO in Creating Blanket PO's
    Thanks & Regards
    Kishore

  • MIRO - Invoice Verification with reference to Delivery note.

    Dear All,
    In our organisation we are doing MIRO with reference to Delivery note. As same number of delivery note is being submiited by multiple vendors, after entry of that delivery note in MIRO system shows large list (Closed & Open for MIRO). This becomes difficult to select the required delivery note.
    Is it possible to make display of only those delivery notes against which MIRO (Invoice verification has not done).
    Also MIRO with reference to GRN number is possible or not ?
    Please suggest.
    Regards,
    Shekhar Kisan Gaikwad

    In our organisation we are doing MIRO with reference to Delivery note. As same number of delivery note is being submiited by multiple vendors, after entry of that delivery note in MIRO system shows large list (Closed & Open for MIRO). This becomes difficult to select the required delivery note.
    Is it possible to make display of only those delivery notes against which MIRO (Invoice verification has not done).
    Also MIRO with reference to GRN number is possible or not ?
    HI,
    To avoid difficulties post miro with Reference document (PO Reference Tab) - Delivery note click on Radio button a possible entries for delivery note screen will appear. Here you can search specific delivery note by a lot of criteria which will save ur time and effort also you can see MIGO Document.  Click and put tick to adopt and post Delivery note / migo and enter required field.

  • Sales order with reference to purchase order

    Hi
    I have a scenario where i need to create a sales order from PO raised in another company code
    My client has 4 company codes
    1000 company code
    2000 company code
    3000 company code
    4000 company code
    Now
    2000 company will raise a PO on company code 1000
    So in company code 2000 i need to create a sales order with reference to PO from compcode 1000
    where all the data has to copied from PO with schedules
    so when i create a order in VA31 i have to create scheduling agreements with refernce to PO all the schedule line items should be copied?
    Is there any standard process or do i need to go for development?
    Regards

    Hi,
       As per my Understanding,
    I guess, you can do this same as creating Purchase Order-NB ( In ordering Company code)-ME21N,
    Vendor- Plant of Supplying Comp code ( Create this Plant as Vendor in ORdering Comp code)
    Purchase org/Group-
    Comp Code - Ordering Comp Code
    Material-
    Plant - Receiving Plant.
    Try n Revert-
    No Need to go for Userexit,
    My Query is: -
    Why you want to create Scheduling agreement wrt "PO" of Diff Comp Code.
    We can use the PO from Ordering Comp Code is a ref for any dispatches ( To Pass the PO requirements to Production in Supp.Comp code, while creating PO by maintaining Checking rule )

Maybe you are looking for