Invoicing a PO on Activity Confirmation

Fellow Consultants ,
We are creating a PO with respect to Project/WBS .
The Project will have Activities that Vendor is supposed to Complete  for the created PO.
The vendor will give Confirmation on completion of activities  after which Activity will be manually confirmed in SAP .
How can this confirmation Trigger Vendor Invoicing .

Hey Maria,
we will create project and for that project we will create 1 single PO with 1 line item stating that cost of the constructing project that has to be paid to the vendor for his services (this services will also include materials , but we will consider it as services ).
So in short 1 PO for 1 project -> this will have 500 services to be performed .
Now we have grouped this services as activity for project . first 10 services (1. labour for digging
2. Machines for digging 3. Materials for digging etc. ) as Digging activity in project.
Next 10 services wil be for concrete filling .
Next 10 services will be for wall erection.
and so on.
Now this activity are to be confirmed in Project system and after we confirm activity , the services in PO has to get invoiced .
We can manually update service entry sheet and simultaneously confirm activity in PS.
But we need some link between Activity and services in PO.

Similar Messages

  • Progress Analysis, Plan/actual % comparision based on activity confirmation

    hello guyz,
    I have to monitor the project progress based on activtiy confirmation, can anyone guide how can i see progress of project based on percentage with plan/actual dates comparison.
    The business scenario is:
    One top level WBS under which 2 WBS assign, each 2nd level WBS have one network assigned. The  second level WBSE represent individual site where i have to perform various internal activities without cost involvements, only dates and number of durations to be maintained in each internal activity with finish start relationship.
    The structure is:
    Root WBS (level 1)--SITE 1 WBS (level 2)--
    SITE 2 WBS (level 2)
    > (Network 001) -
    > (Network 002)----
    > 001 0010 (1st Internal activity 2 days) -
    > 002 0010 (1st Internal activity 2 days)-
    > 001 0010 (2nd Internal activity 4 days) -
    > 002 0010 (2nd Internal activity 4 days)-
    > 001 0010 (3rd Internal activity 1 days) -
    > 002 0010 (3rd Internal activity 1 days)-
    > 001 0010 (4th Internal activity 3 days) -
    > 002 0010 (4th Internal activity 3 days)-
    In the above project structure i have entered the start planed dates for each network / site. The system automatically calculate the planned end dates after scheduling.
    In execution phase, i have also maintained actual dates on activity confirmation only.
    Now i need assistance to see the project progress for each network site.
    Regards
    Saqib Usman

    the problum is still there kindly provide assistance...
    I have to monitor the project progress based on activtiy confirmation, can anyone guide how can i see progress of project based on percentage with plan/actual dates comparison.
    The business scenario is:
    One top level WBS under which 2 WBS assign, each 2nd level WBS have one network assigned. The second level WBSE represent individual site where i have to perform various internal activities without cost involvements, only dates and number of durations to be maintained in each internal activity with finish start relationship.
    The structure is:
    Root WBS (level 1)--SITE 1 WBS (level 2)--
    SITE 2 WBS (level 2)
    > (Network 001) -
    > (Network 002)----
    > 001 0010 (1st Internal activity 2 days) -
    > 002 0010 (1st Internal activity 2 days)-
    > 001 0010 (2nd Internal activity 4 days) -
    > 002 0010 (2nd Internal activity 4 days)-
    > 001 0010 (3rd Internal activity 1 days) -
    > 002 0010 (3rd Internal activity 1 days)-
    > 001 0010 (4th Internal activity 3 days) -
    > 002 0010 (4th Internal activity 3 days)-
    In the above project structure i have entered the start planed dates for each network / site. The system automatically calculate the planned end dates after scheduling.
    In execution phase, i have also maintained actual dates on activity confirmation only.
    Now i need assistance to see the project progress for each network site.
    Regards
    Saqib Usman

  • Activity confirmation concept

    Dears
    Can you any body explain me the concept behind the activity confirmation in QM
    My understanding i  am sharing here i request some expert review on this
    1. The purpose of activity confirmation is for record quality cost
    2. If we have two different task to do a inspection for a material (1-Inspection by machine, 2-labor for cleaning after inspections) so we need to define two activity by the T code:KL01
    3. After defining activity price planing by t Code: KP26 (For the above created activity for one hour how amount is required)
    4.Now when RR is happening we have to do the activity confirmation(for example 1-Inspection by machine how may hour we utilize to make inspection,2-labor for cleaning how many hour we utilize this activity also to finish the inspection)
    5.Now QM cost report will give you for activity one  how many cost incurred so far ,and also for the second activity also
    Pls correct me if my concept is wrong
    Thanks in advance
    Faisal

    Hi expert
    any advice on this will be highly greatfull
    Faisal

  • Activity confirmation issue

    Dear Gurus,
    We are facing issue in confirmation of Activity such as power , steam. As in process industry output is variable.
    accordingly at the time of confirmation activity viz power , steam should varies is it possible?
    In transaction cor6 we can enter manually units actually consumed.
    My second query is
    In T-code CORK and COID  How to / where to enter actually consumed unit of Power and steam in screen? As users  are using all the 3 T-code for confirmation.
    Please guide me as we are facing cost variance in Process order confirmation due to activity.
    Regards,
    J.H.Pert

    COID is just reporting transaction.
    COR6N is single screen entry transaction
    CORK is header confirmation
    When you do confirmation using CORK, all the confirmable phases in the order gets confirmed to the yield qty mentioned in the screen, this also take care of activity confirmation.No option to post activity seperately.
    cor6 you can post actual activities seperately

  • Table for Activity confirmation

    Hi PP exper
    Kindly suggest me  from which table I will get  activity  confirmation detail  when I do the production order confirmation  example my activity 9000( labor)  30 hr , 9001( m/c)  15 kw etc
    kindly suggest me
    Regards
    Akil

    Hi,
    In AFRU.. we can get activity confirmation....suppose if we have many activity which unit are HR.. then we can not differentiate   which activity have confirmed .
    i want activity type and its confirmed
    example Activity type 9000( m/c power)  30kw 1000( labor) 6 HR, etc
    9000----
    30 KW
    1000----
    6 HR
    Regards
    Aqueel

  • Error in activity confirmation using CATS

    Dea all,
    While doing activity confirmation using cats in the transaction CATA following error is occuring:
    CATS: Transfer to Project System
    No records for transfer to PS
    kindly help.
    regards,
    sudhir

    Hi
    First record the time in CAT2 t.code
    Then transfer the time to project system using CAT5 t.code.
    Do you followed the above t.codes?
    In selection screen what are the selection parameters have you maintained?
    Thanks
    S.Murali

  • Quantity not posted to object error in while activity confirmation

         Hello All,
    i am getting below error while activity confirmation , please help me on this below.
    Note : Activity and cost center and KP26 no changes are made compare to preview year and current year , for the fiscal year 2014 i didn't get any error , only for the fiscal year 2015 i getting  below error.

    Dear Hari,
    If the activity type of the confirmation has set the flags as
    mentioned (indicator MANIST in table COKL is set) the system will simply
    NOT post any quantity on the sender cost center/activity type during
    the confirmation.
    So all quantities which are currently missing (as these were not
    updated by the confirmation) must be posted with transaction KB51N.
    If you implement the coding corrections of #760437 you have the
    possibility to change the message BK263 from "I" to "A" in transaction -
    which is however not recommended.
    So the advised procedure is:
    -post all mising quantities with transaction KB51N first
    -then run the report ZRKMANIST_RESET to remove the flag MANIST (which is
    the reason why the confirmations did not post quantities on the
    sender cost centers)
    After this procedure, the quantities will again be updated when you
    post confirmations.
    Best regards,
    Jason

  • Activity Confirmation  -  Gantt Chart  -  Planning board

    Hi
    suppose i have a activity duration from 1st february 2009 to 28th february 2009
    on 15th february i confirm 0nly 10% of the work as completed in the activity confirmation screen in the degree of processing field and also enter the start date as 1st february 2009 and the finish date as 15th february 2009.
    when we look at the planning board in CJ20n transaction subsequently (gantt chart) the activity bar shows a colouring from 1st february to 15th february instead of showing only 10% of the activity bar coloured for completion of the work
    where is it possible to see the percentage completion of an activity graphically as 10% this data is available in table format in CN48N transactio

    Hi,
    we can view in table format by selecting the fileds related to percentage of completion in the project planning board (gantt chart).
    The requirement you had explore is possible in MS projects, but in standard SAP we can't view in the graphically mode.
    Regards,

  • Activity Confirmation

    Hello all,
    Scenario is- A FERT material assigned in the project which creates WBS reservation. FG is produced by production order and then delivered from Project stock.
    Before delivery of the FERT, I want to check the activity confirmation to which FERT is assigned.
    I have a WBS number as an input to call the BAPI, in the user exit for deivery @ save.
    Which BAPI shall I call in to check the activity and reservation stauts for perticular WBS? and which FM will be useful to perform the confirmation of perticular activity?
    Please reply..
    Thanks and Regards

    Hi,
    Make use of the folowing BAPIs 
    1) BAPI_PROJECT_GETINFO - get all the activities for the mentioned WBS.
    2) BAPI_BUS2002_GET_STATUS - get the status of required activity. Not sure how to derive the activity to which the component is assigned out of the all activities for WBS.
    3) BAPI_NETWORK_CONF_ADD - to confirm the activity.
    Regards
    Sejo

  • Activity Confirmation workflow

    Dear Experts,
    I am using BO AFVC_NETW for network activity confirmation workflow. The start events of workflow are confirmed, partially confirmed, manually confirmed. I made a zcopy of the BO AFVC_NETW and added these 3 events and delegated the Zbusiness object. Once the wf triggers i have user decision step assigned to first level approver. If he approves it then i have one more user decision step. if second level approver also approves it i complete the workflow.
    When I confirm the activity using tcode CJ20N two events of my wf are getting triggered which i saw in SWEL.
    I expect to get only one workitem for first level approver. But i am getting 2 workitems instead of one. Can you please tell me why i am getting more than work item. Am i getting 2 workitems due to the reason that two events of my wf are triggered or am i missing something. I have no loop step in my wf.
    KR,
    S Bharath

    Hello,
    Two events are being created. If they both act as triggers for the workflow, then you will get two workitems.
    If you really need both events as starting events then perhaps you should create a start condition that checks if there's already a workflow instance running with the same object key.
    regards
    Rick Bakker
    Hanabi Technology

  • How to pick activity type from HR mini master during activity confirmation

    Hi,
    How to pick activity type from HR mini master during activity confirmation via BAPI "BAPI_NETWORK_CONF_ADD".
    I have confirmed activity via bapi BAPI_NETWORK_CONF_ADD, and it is picking activity type from activity. but i wants from HR mini master. In BAPI i am passing Personal no.
    Thanks in advance.

    Hi,
    Did you mention Activity type information in HR Master-315 InfoType (TimeSheet Default value).
    then you can get the value.
    Vemula

  • Getting Error Msg " System Status INCM is active (confirmation 7300012896)"

    Hi ,
    Whlie confirming Goods in "Confirm Goods/ Services" user is getting Error " System Status INCM is active ( confirmation 7300012896)
    Can you please tell how to rectify this error message and confirm goods against PO.
    Regards,
    Avdhut

    check - click before doing confirmation
    there many other error message thrown at bottom side
    any user locked of for network / PM order  order in the PO
    some message will be thrown
    share taht message for more help.
    Muthu

  • Automatic Material Issue on Activity Confirmation

    Dear All,
    I am trying to setup the system so that on internal activity confirmation material assigned to the activity is automatically Issued to the WBS.
    Issue:
    BS, but when i confirm the activity system does not issue the material automatically when stock is available as unrestricted stock in the correspondign WBS.
    When there is stock available in the Storage location mentioned in CJ20N for the material automatic GI happens on activity confirmation.
    Can you please let me know why is system not issuing the material available as unrestricted stock on the corresponding WBS??
    Warm Regards,
    Jatinder

    Dear Gokul, Srikant,
    Fine i can use CN25 for confirmation.
    Requirement is that i want to track stock on WBS level, and then issue it to Network/Activity from WBS stock? is this not possible via activity confirmation??
    Is it that if i want to automatically post GI on activity confirmation, it is not possible from Project/WBS stock?
    Warm Regards,
    Jatinder

  • Network activity confirmations

    1) Hi guys please advise is it  possible to avoid (by means of error ) the second confirmation of an activity whihc was already fully confirmed and completed.
    2) The milestone once it has received an actual date should not be possible to change the first actual date. So may be is it possible to get the field greyed out after doing the actual postings to milestone.I am not using the confirmation by means of a percentage completion of milestone and activity, instead my scenario requires the confirmation manually.
    3) How can we control that the milestone actual date should not be less than 3 days of the system date.
    The issue is important and urgent .Kindly advise
    Thanks
    RKS

    Hi,
    Thanks once again.
    I have been trying the SPRO and Enhancements listed under Confirmations node, but have a feeling that they may work for controlling network activity confirmation and not for milestones.
    Can you please confirm if these can work to control the milestone actual dates as per my requirement i.e. the actual dates once posted manually to milestone should not be possible to be changed.
    Kindly let me know of any other enhancement or exits if you are aware.
    Thanks and Regards
    Rajeev

  • Network activity confirmation

    Dear Experts,
    I am triggering a workflow when activity is confirmed in CJ20N. Confirmed, Manually confirmed, Partially confirmed are the start events of my workflow. I tested the workflow in sandbox. In SWEL tcode i can see only confirmed event is triggered. I am getting one workitem for confirmed event.
    I transported the same workflow to quality and tested there. But in SWEL tcode i can see all three events are triggered twice for same scenario. As a result i am getting 6 workitems. Can you please tell me reason for this.
    KR,
    S Bharath

    Dear Swami,
    Thanks a lot for all your inputs. I have solved the problem.
    Reasons for why I got more workitems in quality.
    1. In BSVW tcode I put three entries for confirmed, manually confirmed and partially confirmed events
    2. For doing activity confirmation in CJ20N there will be 2 steps first create the activity save it and then open activity again and confirm it and save it. As you see I will click save button twice for the confirmation process
    3. BSVW tcode responds to every change in CJ20N tcode. So first time when I create activity and save 3 workitems for 3 events in BSVW are created. When I confirm activity and save again 3 more workitems are created so totally 6 workitems.
    4. I removed the BSVW entries and opted for BADI WORKORDER_CONFIRM.
    5. In method BEFORE_UPDATE of this BADI i inserted the below code. Note: This method will be called only when the user clicks save button after confirming the activity.
    type-POOLs: cobai.
    data: AFVC_NETW TYPE SWETYPECOU-OBJTYPE,
          EVENT     TYPE SWETYPECOU-EVENT,
          OBJKEY    TYPE SWEINSTCOU-OBJKEY,
          lv_aufpl TYPE afrub-aufpl,
          lv_aplzl type afrub-aplzl,
          wa_aafvc type afrub.
    READ TABLE it_confirmation into wa_aafvc INDEX 1.
    lv_aufpl = wa_aafvc-aufpl.
    lv_aplzl = wa_aafvc-aplzl.
    CONCATENATE lv_aufpl lv_aplzl into objkey.
    if sy-tcode = 'CJ20N'.
    CALL FUNCTION 'SWE_EVENT_CREATE'
          EXPORTING
            OBJTYPE                       = 'AFVC_NETW'
            OBJKEY                        = OBJKEY
            EVENT                         = 'Confirmed'.
    CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'.
    ENDIF.
    This perfectly solved my problem and now I am getting only one workitem.
    KR,
    Bharath