Is it possible to release Process Order  with Material Shortage

Hi All,
We are using PP-PI & still wants to have behavior of the PP prod order
i.e. Release Process Order with Material shortage.
Is it Possible.
Regards,
Jatin

Hi Jatin,
Go to Transaction OPJK. Select your Plant, order type and Business function as 2-Check availability during order release.
Under Material Availability tab, maintain '1- User decides on release if parts are missing' if user wants to decide for release of Process order or '2-Release permitted despite missing parts' if you want directly the Process order should be released despite of shortage in Release material field.
These settings are similar to PP.
Please check and revert.
Regards,
Hiren Ramani

Similar Messages

  • Stop user creating process order with material for specific order type

    Hey Team,
    Is there a way where I can stop creating process order with material for specific order type says Z*. We are using ZNMA  order type to create trial batch and we do not want to create process order with material for this order type.
    Any ideas?
    Thanks
    Bhavesh Patel.

    You can restrict the order creation in CO01 based on authorization, Remove the authorization for Z order type for the particular user,  Check with your basis Guy

  • OSSNOTES for releasing process orders with missing parts in background

    Hi All,
    The bapi 'BAPI_PROCORD_RELEASE' is not releasing the process orders
    with missing parts in background.
    Is there any OSSNotes for releasing these process orders in backgound through this bapi.
    Pls help.
    Thanks .

    Hi Suri - Thanks for your response. I tried both with blank(individual and collective) and 2 (collective req. only) but I still get the same result. I found one other setting that can solve this issue and that is checking the activate full confirmation logic at the the MRP group level in OPPR. I will test more and let you know if that works but we dont use MRP groups here at our client and that is why I was little hesistant to set up collective availability check parameters at the MRP group level. But looks like this is the only option that we can use to get this resolved.
    Thanks,
    Bharath

  • Confirming the order with material shortage

    Dear all,
    I am confirming the process order even though if material shortage.
    Again when will consumption will take place for that particluar material?
    Where that stock will be located without consumption?
    Regards
    Rajasekaran

    Hi Rajasekaran,
      stock is not present than it will go to cogi .please check the cogi.
    if you don't want incorrect goods movement than choose following field as ticked in opk4 conformation dependent parameter
    Thanks&Regards
    Sandeep Kumar Praharaj

  • The Prerequisites for releasing process order

    Hi all,
    What are the Prerequisites for releasing process order?
    Can we issue the material against process order, if it is on CRTD status?

    Hi,
    Prerequiste for REL of Process Order -
    Process order should have CRTD status.
    Other with IMG setting, you can have order status directly REL once it is created also. See Prod Sch Profile setting.
    You cannot do goods posting (GI and GR) unless order is REL status. Not possible with CRTD status.
    Srini

  • Problem creating process order with ref of sale order

    Dear all,
    Kindly give solution for this scenerio..............................
    I am creating Process Order with ref of sale order manually in cor1. In the COR1 screen copy from field i gave my ref sale order, so that particualr order and batch is assigned to that order only.
    My problem was suppose if sale order is created for 10 tonns, but my batch size and resource capacity is 2 tonns only. so first time i change my batch quantity 2 tonns instead of 10 tonns and created my order and confirmed.
    if i go to second time the same process i am doing creating process order with ref of same sale order but it comes again 10 tonns instead of 8 tonns. why it comes like this already i confirmed 2 tonns in this sale order?
    my requirement is if any process order is created with ref of any sale order and again if i am creating any process order with ref of same sale order left quantity only system should show.
    for this what i have to do kindly help to this
    regards,
    s.sakthivel

    Dear KK,
    Pls check whether ZKIN, ZKQT, ZKOR have all the properties similar to IN, QT, OR respectively. If they are different, please ensure that you know the reason why they are different. This check has to be done at tcode VOV8
    Some fields like sales document category, Transaction group, screen seq group, Doc pricing procedure need to be similar to the parent document unless you know why you have changed them.
    Once this check is done, check the copy controls in VTAA. Before that try creating these documents separately without reference. This shoudl work fine only after which you need to check copy control. If this is not working fine, then there is some problem with the document type settings in VOV8. Testing this is possible only if Reference mandatory field is left empty. Make sure that is properly configured.
    Once this is done, check copy controls in VTAA. You can just copy the copycontrol between IN and QT and QT and OR and create for ZKIN to ZKQT and ZKQT to ZKOR.
    Once this is done, check whether your item category settings are properly done , also the schedule line settings. The tcodes are VOV7, VOV6, VOV4, VOV5 etc.
    Now check whether your material master and customer master are consistent with the item category settings(Item category group).
    Now create the transaction. It shoudl work fine.
    Reward if this helps.

  • Prevent reschedule on released process order in APO

    Hi,
    We have a business requirement that does not want APO to reschedule on released process orders regardless of production posting quantity.  (don't want to change the order end date/time)  It is similar to R/3 scheduling type "only capacity requirements", but with visibility on APO for resource capacity.
    I tried to implement CIF user exit  EXIT_/SAPAPO/SAPLCIF_ORD_001 with different logics, but still not able to achieve it.  How can we make the system do what we want?  What is the key for remain process time calculation?  Please advice.

    For example: we have a released process order that starts at 10/01/2007 00:00:00 and ends at 10/06/2007 23:59:59 with quantity 7000 KG (1000 kg of production rate per day).
    When a production posting is made (for example: 700 KG was posted on 10/01/2007 23:59:59), CIF sends the update to APO and APO reschedule the order based on the remaining quantity 6300 KG) and the end time of this order becomes 10/07/2007 07:12:00.   In our lines, the production order may not be started on time and posting may be different than what we expected, but we want the order still shows up in APO as start time 10/01/2007 00:00:00 and end time 10/06/2007 23:59:59 with daily distribution of 1050 KG for 10/02 ~ 10/06.  This way, it won't mess up the receipts and resource capacity on PPT for next week's production. 
    Thank you.

  • Regarding Error Message while releasing Process Order

    Dear friends,
                              While releasing process order i m getting following error message.
    " Storage location in PUB(loc1) is not same as storage location (loc2)''.
    how to remove this error and release the order.
    Thanks & regards,
    Sandip Sonar

    Hi Sandip,
    The error message LP 099 'Stor. location in PUB X is not the same as prod.stor. location Y' is issued when the system finds  inconsistancy in your customizing of the couple storage location - Production supply area for your components in your process order.                                                                               
    The logic of the storage location determination is the following ...
    The issuing storage location is determined in three steps:                                                                               
    1. First, the issue storage location of the material to be issued   (MARC-LGPRO) is transferred to the material master from the  MRP    data if it is filled.                                                 
    2. The system overwrites this value with the issue storage location from the bill of material (RC29P-LGORT, STPO-LGORT) if it is     filled.                                                               
    3. If the operation to which the component is assigned in production  order contains a work center with supply area, the storage    location is transferred from this supply area (PVBE-LGORT).     However, this transfer is only carried out if storage location  data (MARD) is maintained for this storage location for the    material.                                                                               
    The logic of the supply area determination:                              
    Priority of supply area determination for WM staging is as follows :     
    1. Supply Area of Work Center               (highest priority)   If no supply area defined look to                                     
    2. Supply Area in item of Bill of material  (second priority)   If no supply area defined look to                                     
    3. Material Master View MRP2                (third priority)         If no supply area defined -> Error message LP 099                                                                               
    I hope this helps in sorting the issue.  
    Regards,
    Mauro

  • Released Process Order

    Hi All,
    From Which table we can fetch the RELEASED Process Orders.
    Regards
    Deekshitha.

    Hi Deekshitha
    There are 2 scenarios  that i can see here :
    1. I assume that you have a list of orders with you say in s_aufnr and you want to  
       check which one of those have a system status of REL i.e. Released.
       a. Goto table AUFK to get the list of object numbers(OBJNR)  for all the orders
       b. Use FM 'STATUS_READ_MULTI' for getting all the statuses for the orders.
           CALL FUNCTION 'STATUS_READ_MULTI'
    EXPORTING
      CLIENT                           = SY-MANDT
                 ONLY_ACTIVE                = 'X'
      ALL_IN_BUFFER              = ' '
      GET_CHANGE_DOCUMENTS       = ' '
      NO_BUFFER_FILL             = ' '
               TABLES
                 OBJNR_TAB                   = gt_objnr
                        status                      = gt_status
      JSTO_TAB                      =
      JCDO_TAB                     =
      JCDS_TAB                     =
        This is an unrealeased FM from SAP but can always be used to read data.
       c. Once you get the list of object numbers with statuses , for each object
           number read table gt_status to see if it has a STAT = 'I0002'. If yes then this
           order is  a released process order . We take I0002 value to compare   
           because if you see table TJ02 that has all system status values , you will see
           that I0002 stands for 'REL' which means released.
           In this way you will be able to get all the object numbers and corresponding
           orders which have a status 'REL'.
    2. The second scenario is where I assume you do not have a list of orders with 
        you and you still want to find out the orders which have a status of 'REL'.
        In this case:
        a. Goto table JEST and get all the object numbers for which STAT = 'I0002' and
            INACT NE 'X'.
        b. Goto table AUFK and for the object numbers obtained above and you can get
            the  corresponding order numbers(AUFNR).
    I hope this helps. If so please reward some points .
    Cheers
    shivika

  • Released Process Order No

    Hi All,
    From which table, We can get the Released PROCESS ORDER NUMBERS.
    With what field reference we can fetch.
    Please help me in this regards.
    Regards
    Deekshitha.

    Hi DeeK ,
    Process Order contains Status called Release , etc .
    It may contain 5 - 6 diff types of status,so u have to use this FM.
    STATUS_READ by passing OBJNR of thart Order ,  OBNJR u can get it from AUFK.
    Re: Plant Maintenance
    Regards
    Peram.

  • Can't relase Process Order with missing parts

    Hi seniors
    I want to relase my process order with missing parts. it is available in PP but not in PI in my system.
    help plz

    Hi
    1. Kindly check the setting for thePlant / Order type combination in the OPJKDefine Checking Control
    2. In this check for the fucntion 1 and also 2 Business function.
    3. Check the indicator for the ""Release material"" in the material avaialability screen.
    Reg
    Dsk

  • Link process order with PM Module

    Hy,
    I know it looks crazy but, is it possible to link the process order with the Measuring counter and counter reading.
    We are working with pharma compny and due to some of ragulatroy reasons it is required.
    if possible then pls guide?
    Regards,
    Dhaval

    Hy Rambabu,
    Thank u for the taking intrest.
    Actually we are using Filters which we have maintain as a Measuring Counter in PM. Our intention is just to track the which filter is used during the production process and also how much product is passed through that speciifc filer.I know my second point is covered through the measuring counter reading but I want to link it with PP module.
    Regads
    Dhaval
    Edited by: Dhaval Choksi on Jun 3, 2008 2:46 PM

  • Goods receipt against process order with inbound idoc

    Hi Experts,
    We need to post good receipt against process order with movement type 101 and for By-product 531.
    Can we use inbound idoc-WMMBID02,with message type WMMBXY to achieve this functionality?
    Or please advise if we can achieve this  from any other Idoc type.
    We are getting below field values for external system
    1. process order number
    2.plant
    3.material
    4.quantity in unit of entry
    5.unit of measure
    6.storage location
    7. movement type
    8.Batch
    Kindly advise how can we achieve this.
    Best Regards
    CS

    261 and 262 are two different movement types INDEPENDENT of each other. I definitely know for the fact that SAP allows you to create a 262 without a 261. if you were to restrict it... you can disable access through a tcode for that mov. type 262 and ask users to use MBST to cancel any material documents created via 261 movt type.. that would ensure a smooth process

  • Is it possible to make an order with danish keyboard and documentation

    Hallo
    I need a computer with danish keyboard so my question is
    Is it possible to make an order with danish keyboard and documentation
    Jesper Nielsen

    You can give each track its own artwork. iTunes will normally display the artwork of track 1 in album listings. The individual track art will show in the small window at the top of the screen when playing, or the artwork panel of the mini player, or the now playing window on a device. Try it and see.
    tt2

  • Process order with reference to sales order

    Dear All,
    Is there any provision to create a manual process order with reference to a sales order .
    Regards,
    venkat

    If you would like to create a process order with assignment to sales order item, then you have to enter the sales order item on the initial screen of the Transaction COR1 via the Arrow besides the input field for  reference process order. This is the standard way to assign sales order for process order in COR1.
    For production orders, there is a separate Transaction CO08 for this purpose. But for process order, there is no such separate transaction available.

Maybe you are looking for

  • Time Machine doesn't appear in Launchpad since upgrading to Mountain Lion

    Since upgrading to Mountain Lion (I'm using 10.8.1), Time Machine doesn't appear as one of the apps when using Launchpad. I can't figure out where it "went" but how do I get it back into Launchpad? It's still in the Applications folder and in my Dock

  • Curve 9300 connecting to boot rom problem

    Hi everyone, I have a curve 9300 and I tried to install an update to the OS. The problem is when i get to the part that says "connecting to the boot rom" the phone starts rebooting and goes like this 3 or 4 times, resulting on a failed update. I alre

  • Save keynote as word document?

    In Powerpoint, it's a snap to send a presentation to Word and save it there (very convenient when you want to e-mail the presentation as a simple text document.) In Keynote, there seems to be no way to save, copy, or send a presententation as/to Word

  • Office 2011 not working on OS x version 10.9.4

    I recently updated to macOS x version 10.9.4 due to some hardware problems Then i download the office 2011 service pack 2 but while installing gives some issues. Could some please help me,It will be really appreciated

  • Flash or WMV video

    Hi experts, One question, couldn't find it through the search, but how can I embed a flash/wmv video files in the portal? We want to store those files in KM and we wont to select them through an iview. Can some one plz give me some pointers on this!!