Is planned delivery time is considered in scheduling agreement ????

Hi experts
problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
I have mentioned the Planned delivery time in .
1) Scheduling agreement for 1 day.
2) In material master for one day.
3) In info record 1 day.
e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
Now when i run the MRP on 4.07.2008.
Schedule line is generated on - 10.07.2008
Please Guide . How i can take care of that time which is requiered at vendor ends.
Regards
Rahul Bhardwaj

Go to OPPQ for that plant
Click on "External Procurement " tab and check if you have maintained any planned delivery time?
Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

Similar Messages

  • Planned Delivery time in case of Scheduling Agreement

    Hi All,
    Does system consider the planned delivery time in case of Scheduling Agreement for Vendor like in normal Purchase order and requisition?
    I am doing the MRP run, but system is taken planned delivery time into consideration. I have one material that is Inhouse produced material for plant X and Y Plant needs this material for further making of a finished goods.
    Y plant have scheduling agreement for STO from plant X. After MRP Run required Delivery date in plant X for Material is same as plant Y. but from Plant X to Y, it take 4 days to reach. So Ideally in Plant X this delivery date should be less than 4 days as plant Y.
    Please look into the issue and reply if you have some answers.
    Thanks
    Pavan

    Hope you have maintained different Planned Delivery times in plant X and Plant Y as per your requirement. For procurement in Plant Y the system would consider the planned delievry time maintained in Plant Y. If you want in-house production time to be considered with Basis date sheduling during MRP run in PLant X then enter the in-house production time approprietely. Else if ou want to consider the exact routing times then consider Lead time scheduling in plant X.
    If the above are maintained properly then you should get the desired result.
    Regards
    Ramanujan

  • Planned Delivery time not considered after MRP run for scheduling

    Dear All,
    After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.
    Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.
    Any idea as to what might have gone wrong?
    thx for your help in advance.
    Rgds,
    Ranjeet

    Hi,
    Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.
    Rgds,
    Ranjeet

  • Planned delivery time in Scheduling agreement and MRP

    Hello,
    Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
    Regards, jaana

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • System is not considering Planned Delivery time

    Dear Gurus,
    As iam planning for the month of January and running the MRP,schedulelines are getting generated but system is not condering Planned Delivery time maintained in the material master ie. 7days.Following is the example:
    I have a FERT-X with a component A-1PC in its BOM and its planned delvery time from vendor is 7 Days.If iam running the MRP on 13/12/2010 for FERT-X  100 PCS for January1,2011 then the schedule lines are getting generated for for component A is on 01/01/2011.But PDT is maintianed in material master is 7 days and same has been maintianed in vendor inforecord.But system is not considering it.
    Kindly help to resolve the issue.
    With Regards.

    I have one ROH which has two different vendors.
    Two scheduling Agreemnt with target qty 100000 kg each.
    Two different Vendor info record with Min. order qty maintained.V1-1000Kg,V2-6000Kg.
    One source list with two vendors and with respective scheduling agreement.
    Quota arrangement is there in which SOB is maintiained 50:50.
    I hv the requirement of 3084 kg of ROH.
    I run the MRP and two diiferent schedule lines are getting generated with 50:50 qty as mentioned in Quota arrangement.
    Not considering the minimum order qty maintiained in vendor info record.
    The above process is correct
    Only One doubt In Quota Arrangement?
    IS two schedule line is created after MRP run?
    Generally System will  select a vendor Whose Quota value is less
    quota rating   = quota base quantity + quota-allocated quantity/ quota
    Edited by: Sundaresan . E. V on Dec 14, 2010 3:26 PM

  • How can consider Planned delivery time for subcontracting dependent of qty

    Dear guru ,
    How can mrp schedule delivery date of a subcontracting purchase requisition in order to consider planned delivery time and quantity to purchase.
    Thanks

    dear guru ,
    I want to create a self-defined info structure similar to S013.
    I want to add field purchasing group from EKKO-EKGRP. The other fields are similar to S013 with the same rules.
    What do you suggest i can do consider note 397864 :
    You are not permitted :a) to use info structure S013 as a template for self-defined info structures (This is prevented as of Release 4.5 due to a termination message).b) to create any update rules for S013 with a self-defined update group.c) to include the enhanced update rules that are used for S013 during the definition of key figure updating into the definition of the update of a self-defined info structure (compute...).
    Thanks

  • Consider planned delivery time field in MRP Areas

    Hi,
    I would like to know if the "Consider Planned Delivery Time" field in the MRP areas is taken into the scheduling of materials during MRP run? From the help documentation, it seems to be yes. Otherwise the system will take the Planned Delivery Time from the Plant level. May I ask how we can tick this field for all materials? We are currently in the process of activating the MRP areas in our system. Before, we didn't use the MRP areas but we think the need for it has arrived. Is there a mass maintenance tool to do this? Or do I have to use LSMW? Thanks!
    Regards,
    Chester

    Hello Chester
    If you flag the field "consider planned delivery time" the planned delivery time defined on the MRP area will be considered by MRP. You should tick it for all the materials if the value from the MRP area should be considered.
    Also, the report RMMDDIBE can be used for mass processing of MRP areas.
    BR
    Caetano

  • MRP - Auto creation of del schedule lines based on planned delivery time

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Nirav,
    This subject has been discussed repeatedly in this and other forums.  I must assume that you overlooked the rules of engagement, which state that you should first search the forums and other public sites, before posting questions here.
    Standard SAP MRP cannot be made to generate multiple items in a Purchase requisition.  The functionality you seek is usually achieved when converting purchase reqs to Purchase orders, where many single purchase reqs can be adopted into a single Purchase order.
    You also might want to investigate use of Vendor Scheduling agreements.
    Best Regards,
    DB49

  • Planned Delivery Time of Schedule Line

    Dear Gurus,
    I have done the setting in SPRO >MM>PURCHASING>PP>PROCESSING TIME from 1 day to 0 day bt still  it is picking up one day for schedule lines.There is 0 days planned delivery time in VendorMaster,Material Master,Vendor info record.
    I hv run the MRP  on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    With Regards.

    I hv run the MRP on 06/01/2011 and system is generating schedule lines for 07/01/2011.I want it for 06/01/2011 only.
    During MRP, System will do the backward scheduling... from FG reqmt to Raw material,
    Compare the order start date  of header material in plan order or in prdn order  with the reqmt date for  the schedule line material - Is any difference in days?

  • Schedule Agreement - Planned delivery time

    Can you still use planned delivery time when using Scheduling Agreements?  Or does this field need to be set to 0 for the delivery lines to get created properly when using JIT/FRC schedules?  If we cannot use Planned delivery time, is there another field that can be used to hold the Vendors lead time.  We want to take this into consideration when determining the end date of the Scheduling Agreement.

    Hi,
    the planned delivery time field on the material master is designed to be used when it cannot find the correct data from the info record. It should always contain the planned delivery time that should be applied if the vendor is not specified.
    the same field on the info record should contain the planned delivery period for the appropriate vendor.
    This field does not have to be 0 if you are using JIT etc.
    Steve B

  • How planned delivery time effects delivery creation?

    Dear All,
    Some time before, while placing order thro' CRM, we came across a typical error (hard error).
    "date (11/12/2011) lies afterthe end of validity calendar". 
    we could not place order in CRM but in SAP we could create save the order despite of same error but soft. However system didn't allow to create delivery for same order & same error message populated"
    Later it was found that it is because for material  " Planned Deliv. Time  maintained for say "X "days in material master MRP2 view" & was corrected.
    How planned delivery time effects delivery creation?
    For material even though planned delivery time was maintained as say for 500 days, sales order requested delivery date & delivery date in order schedule line got determined as order date (Considering avaliability of funds & material).
    i.e order date/req. delivery date/delivery date in schedule line are same as date on which order is placed.
    Regards
    Suhas W

    Hi,
    Extended your factory calender in SCA3.
    Regards,

  • Planned delivery time

    Hi,
    I have created a sale order on 1/7/2009 with a material which has planned delivery time of 4 days.
    Now when I go to the schedule lines screen I see that the delivery date corresponding to the confirmed quantity is 1/8/2009.
    Why is not SAP taking the 4 days into considerations while determining the delivery date?
    Please see below the screen shots:
    Scheduling configuration in material master:
    [http://i40.tinypic.com/14b2fyc.jpg]
    Schedule lines screen shot:
    [http://i44.tinypic.com/9pxkzc.jpg]
    Sincerely.
    Ketan

    Hi,
    You seems confused with planned delivery time in MRP 2 view of material master to Sales order delivery date.
    Material master Planned delivery time is for the material which is procured externally  through PR -- PO process.
    In Sales order the delivery date is with respect the ATP--Avalible to Promise.
    If the stock is avalible in the storage location on the date of Sales order creation, then system will consider the delivery date an the basis of confirmed qty in the sales order. You can check in CO09 for confirmed qty.
    rgds
    gsc

  • Planned Delivery Time from Material Master instead of PIRs

    Hi SAP Gurus,
    Do you know if there is a way to have MRP look at the Planned Delivery Time from the Material Master (MRP 2 tab) instead of the PIR?
    We would like to create global PIRs with a PDT of 1 and have the Material Master PDT set to a different number (example 5).  So when MRP runs it will read 5 instead of 1.
    Any additional information is appreciated.
    Thank you
    -nic

    Hi Nicholas,
    In Standard SAP will consider Planned delivery time maintained in Inforecord and than time maintained in Material master. Inforecord has higher priority than material master. When a requisition is manually created, the Planned Delivery date will always be taken from the material master.
    For MRP you can make setting OMDT for your plant or MRP group to determine planned delivery time.
    Deactive the flag 'Scheduling according to purchasing info record or agreement' in Customizing (Plant or MRP group). and test the same.
    Regards,
    R.Brahmankar

  • Purchasing: Planned delivery time

    I have a material that are being purchased from 2 vendors.  one vendor delivers the material in 2 days.  the other takes 20 days.  In the material master, I have to maintain the planned delivery time.  As per the help info, I will need to maintain the average time here.  So, that would be 11 days.
    So, when I run MRP, 11 days will be taken as the planned delivery time.  My planning is not going to be accurate if I choose any of the vendors.
    Can anyone guide me how I can take care of this scenario?

    Raj,
    You maintain your planned delivery times for each vendor in your info records.
    You need to ensure you have flagged the <i>scheduling info record/agreem.</i> flag (Determine Planned Delivery Time) in transaction OPPQ.
    You also need to ensure that you have maintained source list entries for your vendors that are relevant for MRP.
    Now the MRP run will consider the planned delivery time in the info record and not the material master.
    Hope this helps.
    H Narayan

  • Plannned Delivery time not considered while calculating delivery date

    Hi PP Gurus,
    We have a situation is that after MRP run system is not taking into account planned delivery time while calculating delivery dates in schedule lines
    It is taking into account GR processing time.We have GR processing time of 3 days.requirment date is 13.10.2011 & delivery date created by the system is 10.10.2011.
    We have maintained correct master data i.e.Materail Master , Info record & Scheduling agreement.
    Please advice why it is happening & what is the significance of planned delivery time in externaly procured materail with scheduling agrement schedule lines?
    Thanks & Regards,
    Sandesh

    Hi Sandesh,
    Is this happening for particular materials or for all materials
    Couple of checks -
    1) Check with material master changes, might be after MRP run PDT is updated in material master etc ..
    2) Check in OPPQ, for option external procurement , whether scheduling info records/agree is marked or not
    Best Regards
    K.Madhu Kumar