Is it true that one material can be specified in production order as the output (material to be produced)?
and what is combined order? why the output material in combined order can be different from output materials in subordinate orders?
Thanks

Dear,
In Combination order you can combine the serval planned, production order to one new combine order. This functionality is available in IS mill.
For more details refer this link,
/people/rupesh.brahmankar3/blog/2009/08/03/combining-production-and-process-orders-with-batch-production
Regards,
R.Brahmankar

Similar Messages

  • Production Order for a material without BOM and Routing

    Is it possible to create a production order for a given material without routing and BOM, I know we can
    create a production order for a material without a BOM (with a default routing) just wanted to check with
    the above criteria
    Thanks in Advance!!

    Members:
    Thank you for your valuable replies and time
    Santosh:
    Tried what you have mentioned, but system still picks up a default routing
    Kaushik:
    Maintained Default values in OPJG for the given order type, but system still picks up
    default routing
    Mangalraj:
    have no issue in creating a production order without a BOM, but I am trying to see
    is there a way where I can create a production order without a BOM and routing (not
    even default operation )
    Any suggestions on how to create a production order for a material without a BOM
    and routing (not even default one )

  • Error while converting planned order to production order for config materia

    Hi experts,
    While converting a planned order to production order for a configurable material.I am getting the following error meassage. Message No.CO684,
    "You cannot make an assignment to make-to-order stock"
    ( DiagnosisThe component cannot be allocated to an individual stock because make-to-order production and engineer-to-order production cannot be executed with this order.
    A possible cause is that you are trying to create an order with reference to a sales-order/project, where an account assignment to a sales order/project is not allowed in the settlement profile that is assigned to the chosen order type. This is inconsistant.
    System ResponseThe following responses are possible:
    Order processing is cancelled.
    The system resets the special stock indicator back to the original value.
    Procedure
    Choose another order type).
    I have checked some of the threads related to this error. But no where there is any solution.Please tell me if there is any settings to make so as to work on this scenario.
    Thanks,
    Sham

    Hi,
    This will be a MTO scenario. Please check your requirement type,Requirement class and strategy type config along with your Item category and schedule line category from SD.
    Also check your Production order type config and settlement profiles.
    I mean to say that you need new production order type to be configured for specific above mentioned combination.
    Are you working on a production system..?? is it the first time you are creating the order for this config material..??
    Regards,

  • Purchase order from production order for stock material

    Hi,
    Can we issue purchase order for stock materials (item category L) for components in production order. We want a PO account assigned to production order . How can we achieve that.
    With regards,
    Mrinal

    Dear
    1.Goto MM02-Enter componenet item code -Selec MRP4 view -Keep Individula nad Collective indicator as 1
    2.Goto MM02-FG Material -MRP4 view -Keep Individaul and Collective indicator -1 and in Sale.Org1 view keep item categoery as MTO .
    3.Create Sales Order  and run MRP in MD02 (NETCH , 2,1,1,3,2, 2)-If the compoenets are not available , then it will generate PR  with an Account Assing Categery E with sales order refernce and line item .Converthis PR into PO cnd check the same in Accounting Tab .
    This is only possible in MTO scinarion in case you want to have PO account assinged for FG production Order .
    Regards
    JH

  • Production Order for a Material with two units of measure?

    Hi Everybody I have the following issue.
    In my company there is a new production process with a Material that should be configured in the master data with the field "Base Unit of Measure" as per unit (each). But the production process, should be confirmed by tx CO11N, in Kilograms. I know that I can use the additional Data in tx MM03 to set a Production Unit, but the value of convertion would be fixed. For example 122 Kg = 1 each, the thing is that the value in kilograms for each lot can vary, one lot can weight 122 and another one can weghr 125, and in each case I shoul have two units in stock. And as I have the value of convertion fixed, when I confirm each lot one for 122 kg and another for 125 kg I will have 2.025 units in MB52.
    How can I solve this problems? I need to have the chance the confirm in kg changing for each lote the quantity but in the base Unit of Measure have one unit for lot. As if for tx CO11N I could have a field where I can set tha x quantity of Kilograms is x each.
    Kind regards
    Leandro. 

    Hi Ayoub, First thank`s for your promt answer,
    1. The Quantity is different, because is not a perfect process, there is a manual work in the process that makes this quantity differ, there is no big difference, maybe a Kilo or Two but the production mannager wants to have this registered. And besides in productions they manage kilograms, but for selling the comercials manage units (each - EA)
    2.The convertion rate is known at the end of the process after cutting and packaging a unit, they weight it.
    Regards
    Leandro

  • Creation of Production Order for Deleted Material

    How can I prevent a production order from being created for a material that has been marked for deletion?  Currently, our system generates a warning but allows the order to be created.

    Thanks for the suggestion of the material status but I am trying to stay away from assigning a code to a delete flagged material.
    The message I am getting is CO732.  I went into transaction OPJB to change the message from warning to error but that message is not listed in that transaction.  I tried adding it and still received a warning message.
    Is there another transaction to check so I can switch it?
    Edited by: Joe Reckelberg on Apr 28, 2009 4:49 AM

  • Production order from sales order with multiple line item(for one material)

    Dear Gurus,
    I am working in MTO scenarios. If there is several line item in a sales order for one material, multiple production order( same as no. of sales order line item) is getting created against each of the line item.My requirement is,since the material code is same in each line item and sales order is one, one production order should be generated for all line item. please tell me how to do it.
    (Here for one material, multiple line item is required for some specific reason)
    Regards
    Rajib Pathak

    Hi,
    This is not possible.
    In Std SAP will create one production order for one sales order. The stock is also allocated to thet particular sales order only. Because each and every sales order may vary in any one of the parameters. Considering this, SAP has designed like this.
    Regards,
    V. Suresh

  • Error in GR for a Production Order for a particular material....Unique case

    Hi Dear Gurus,
    I am facing the following problem:
    There is a production order for a material (say X, matrl type FERT) of order qty 21EA. First we did GR of qty 9EA. but when we are going to do GR for the rest of the qty i.e.12EA it is not happening system showing Error message " Account XXXXX requires an assignment to a CO object".
    But while we are going to do GR for the rest 12Ea qty in two parts i.e. first by doing GR of 11EA then 1EA system is accepting.
    Interestingly if do the GR for the same order as first by 8EA and then the rest 13EA that is also accepting.
    Eventhough, for any other material (of same type and group) if we make a production order of the same 21EA and then doing GR firstly by 9Ea and then 12EA that is also getting posted properly.
    What would be the reason for the error message for that particular case?
    Here the system is SAP4.5B version, material MRP type is M0, lot size  FX & fixed lot size 10Ea, safety stock 8EA, Reorder point 15.
    Thanks in advance for your inputs.
    Regards,
    Arghya

    REfer this link..
    [https://forums.sdn.sap.com/click.jspa?searchID=25161817&messageID=7040673]
    [https://forums.sdn.sap.com/click.jspa?searchID=25161817&messageID=7159723]
    hope the above helps..
    karthick

  • Creating a production order for a semi finished product

    Hi
    I am having a multi level bom scenario over here.
    one of the bom components of the header material is a semi finished product.
    I am using the planing stratagy 40 for that material.
    in standard sap when i create a production order for  header material. the requirement gets transerd to all the components. if the components are not available then only  a requirement is placed. when i run MRP that requirement gets converted in to a planned order. which converts in to a purchase req or a production order,
    well for my semi finished product. its a Work in process item. there wont be any stock for that item in the storage location any time.
    what my requirement is. when i create a production order for my finished product it should automatically create a production order for the semi finished product.
    is this possible with some configuration settings.

    Dear Deepu,
    for ur requirement u need to maintain MRP type PD for FERT material and also for ur HALB.
    If u run  MRP  only, it will create planned order for FERT and for all its dependent requirement(for PD).
    If u create order manually for FERT material then it will not create order for HALB material, u need to create manualy for this also.
    sree

  • Production order for a multiple materials codes...

    Dear...
    Could you please suggest me the SAP solution for the below production strategy.
    This production process is of heat treatment. Actually I am doing heat treatment of Cast and Forge items. These items weights are in the range of 150 kgs to 40000kgs. For example I am having a 40 tons heat treatment furnace. So at a time I can load the materials upto 40 tons. I am having different materials of different sizes and chemical compositions.  But heat treatment cycle(Routing) is same. So I can load different types of materials i.e. upto 40tons for the heat treatment for which same type of heat treatment is required. Sometimes this may be a single item .. if the weight of the items is 40 tons. If it is single item...then there is no problem. If I am loading different items...and if execution process is same for all the items, then how can I map this in the SAP. So that I can create a single order for different Items of different materials and quantity. I need to do the confirmation of these items with respect to the same item. Please suggest me...how can we map this scenario into the SAP.
    Thanks in advance.
    Regards,
    Surya.

    Hi surya,
    As per the heat treatment process concern, total cycle time is constant, and load is also constant (if we havenot changed).
    i hope u have defined workcenter formula and routing accordingly.
    i think creating single production order for multiple material is not possible, instead of thsi, i would suggest one way,
    > Since u have to maintain stock for Heatreated items, create sepearte Material code for each item to be heatreated.
    > Create BOM ,Routing  for New Material code.
    > Acitvate Batch management for New Material Code has been created.
    >Now create Production order for each material to be processed in one cycle, Assign the Batch Number manually.Batch number repersents your Heat treatment cycle number and same can de used for traceability.
    >Confirm the each order seperately, Now the Heatrement process cost will be updated and stock will be posted to heatreated storage loaction.
    But i am worrying about capacity planning and scheduling, For my knowlegde purpose i would like to know your existing scenoria, like workcenter formula and  routing operation values has been assigned , if u wish plz share with us.
    Please come back with your ideas..
    regards
    Pradeep

  • Two prices for one material in sales order according condition type

    Hi,
    I configure the condition type according to following condition record:
    Plant/ Sales Organization/ Distribution channel/ Material / Customer
    (because system should calculate two prices for one material in two plants)
    In the sales order screen, when user firstly select material , quantity, plant ,  system calculate the related price correctly but if user select the material and quantity and enter and after that select the plant, system will show the error message in pricing procedure and to have a price for material, user should update the price in the price condition in sales order.
    It is so difficult for user to update one by one, because there are several sales orders which need to update.
    Is it any way to solve this problem?
    Thanks,

    > In the sales order screen, when user firstly select material , quantity, plant ,  system calculate the related price correctly but if user select the material and quantity and enter and after that select the plant, system will show the error message in pricing
    Hi,
    Why to let the user press Enter button before entering plant value Obviously, system will give error, because it doesnt get all the required value based on which you have maintained condition records.
    Ask the user to enter all the value at item level otherwise you will have go for the option that you are doing currently.
    It is said prevention is better than cure
    Hope you get some inputs
    regards,
    Sagar

  • How to create production order for multiple items having common raw materia

    Dear all,
    We are running a sheet metal fabrication company at Vadodara Gujrat.
    Please guide us how to create single production order for multiple items using single raw material??
    For example, We want to produce baby shirt(item code AAA001), shirt with full sleeve(item code AAA002), shirt with half sleeve(item code AAA003),shirt slim fit (item code AAA004),shirt loose fit(item code AAA005) from single raw material say(item code XXX001).
    Right now we have to create 5 production order to produce above 5 items of single sales order  in SAP B1 though it is made from single raw material which is foolishness and time consuming too. (Please also note that to produce any finfish good item, raw material required for that item may vary every time in our process.)
    Kindly guide us how to solve the problem.
    Thanks.
    RUPESH  +91-9227744273
    WEB : www.gorasia.co.in

    Hi Rupesh Gorashiya,
    This is possible through MRP for that you have to put Sales Order first and Run MRP Wizard
    MRP Wizard Put Multi Production Order as per Item Taking in Sales Order just click it on and execute.
    Thanks,
    Srujal Patel

  • Lock the production order creating without material for order type zp01

    Hi all,
    Good morning.My client wants to lock the production order creating without material for order type zp01.He does not want to create production order without material.Its very urgent.Please guide me the settings if any.
    Thanks and Regards
    Sukumar

    Hi Sukumar,
    You can do by applying user exit.
    Use PPCO0007 - Exit when saving production order.
    Function module - EXIT_SAPLCOZV_001.
    Include Program - ZXCO1U06
    Write your Code:
    *&  Include           ZXCO1U06
    Regards,
    Sankaran

  • Costing the production order for the configured material

    We are trying to cost the production order for a configurable item.  But the system is not calculating any cost in the production order.  Sales order related to this configurable material is costed.  What additional setting I need to cost the production order for the configured material ?

    Hi Niki
    If your SO is costed, thats enough from a System's perspective... Planned cost will be the sales order cost estimate because SO saves the Chars required for the Configurable material
    Planned cost in Prod order depends on the Costing variant you have assigned in the order type... Check the error log if there is any error in cost calculation in prod order
    br, Ajay M

  • In the production order for 1 of the component material no 261 movement

    Hi SAP Gurus,
    In the production order out of 8 components for 1 of the component material 261 movement is not happening ( Not getting backflushed) Please give some input on this issue.
    Thanks and Regards,
    SHARAN.

    Hi Dhaval,
    In MRP2 view the backflush indicator has been set. But in the parent material BOM setup this material itself not there I informed the user about this, please refer the below user comment ( In BOM the material:Q7829-60184 is appearing and mat:Q7829-60140 not there in BOM, in production order for both the materials 261 movement not happened ) Please give your input on this issue.
    Hi Sharanappa
    We just did a PCO roll  PCO #4619999R3 on Tuesday 30th Dec.
    From Q7829-60140 to Q7829-60184
    All options for Q7840A, Q7829A, Q7830A (except #ACJ, already completed), Q7831A.
    That's why you are not able to see the part in BOM
    How can we rectify this from here?
    Thanks and Regards,
    SHARANAPPA.

Maybe you are looking for

  • How do you include CLOB data in XML document? Is there a size limit?

    Im actually using the Oracle API's to create an XML document as a clob. But for the columns that are CLOB columns they just put <column>(CLOB)</column> in the document and not the actual CLOB. Anybody know the direction I need to resolve this?

  • How to share files with media player kaiboer K670 ?

    I am trying to share a file between my macbook air and my media player Kaiboer K670. The issue I have it's this : - When I find my macbook air on the media player, it ask me for a login and password that I cant find.......i tried my usual login name

  • Weird invisable indent/tab

    Dear anyone, Does anyone else have a problem with a weird "space" that makes your text indent to the right? Like, no matter how much you move your text box around, the "space" stays in the same spot and your words just flow around it (like text wrap)

  • Recovery partition has been removed

    Hi sir  I recently purchased a HP pavilion g-1202 TX series, I have installed Windows 7 64-bit OS, I found that I had only single drive i.e. C: for use, thought of creating another partition and shrunk the C drive, after this I found that HP RECOVERY

  • What is photoshop?

    What is it exactly? I know you can do some cool stuff with it. Is it already installed on the macbook? If not how much does it cost? -Thanks for all the help