Issue in SNP optimzer

Hi,
Our scenario is the product P getting manufactured at locations X and Y. Now same demand present on both the locations and we want to identify where to produce how much using optimizer.
Im currently exploring optimizer and trying to build up the solution using docs available on net. I want to give priority to production cost , then transportation cost and then storage cost.
can u pls give detail stpes  for building up same in system. Also currently im stuck in creating PPM. is it prerequsite for running optimizer..where to set production cost at location level and how.
Regards,
Vrushali.

Hi,
As suggested by you i've correct demand and i've put demand for product (P) on distribution centre (D) which is connected to two manufacturing locations ( M1 and M2) producing product P.
Before running optimizer i've made following settings,
1) Transport cost i've kept same for product P from M1 to D and M2 to D
2) I've kept production cost higher at M1 in PPM ; PPM is  added to active model.
But when im running optimizer in interactive planning for entire network the cost is coming zero. There is no transportation as well as production cost. No SNP planned order created for any manufacturing location.
Can you pls guide in case im missing any seetings or check points. I've hecked log and demand, transportation lanes, PPM , location product getting read.
Regards,
Vrushali.

Similar Messages

  • APO SNP optimzer & PPDS optimizer

    Dear Experts,
    When i am doing my capacity leving using optimzer method in SNP
    system propose optmizer server is not installed in SNP
    its seems no optimzer server for SNP and PPDS was not installed , i try to run test connection to optimzer server
    it fails
    Just wonder as functional consultant what need to tell to the basis team
    can any one guide me on this technical stuff
    Thanks & Regards
    Raj

    Hi Raj Kumar,
    1) Once you show them the error, they fully understand
    what is the action to be done for that error
    2) You can also tell them to check the RFC connections
    3) Tell them to check the Optimiser installation is proper or not like
    4) Ask them to use transactions /sapapo/opt12, opt03 if required
    This will suffice.
    Regards
    R. Senthil Mareeswaran.

  • Manual Lot Size issue in SNP

    Hi Gurus,
    I have an issue while creating planned orders manually in the planning book as it is not splitting into the lot size which was maintained in the product master.
    Some details on the issue:
    I have a product X and I maintained '4000' as the fixed lot size in product master. When I enter 20000 it should spilt it into 5 batches and which is not happenning and it is placing the entire thing as one bulk order of '20000'.
    (If I run heuristics, it is splitting basing on the lot size maintained).
    It was working correctly for 1 product and for many of the products it is not working. All the parameters for the products are same and there is no difference.
    For the product which was working correctly for one user and for the same product if I try it is not working.
    I probed more into the issue to see if any parameters were added in his profile, there is one custom parameter which is assigned which splits the planned orders basing on the lot size maintained. I even assigned that profile, it worked once and later it is not working.
    The strange thing is for one user it works and for other users it doesn't even work for the same product.
    Note: We recently moved from SCM 4.0 to SCM 5.1.
    Did any one faced such kind of issues before? Any suggestions are highly appreciated.
    Thanks and regards,
    Murali.

    Hi Murali,
    I am surprised to read the issue.  I will never expect manual planned order to get split.  The lot size settings are applicable only for automated planning i.e. heuristic (MRP in R/3)
    If you have indeed observed that the system splits the orders by lot size, I have nothing to comment.  (probably that is why you did not get a reply for almost a day.
    If you have found some settings and find that they do not work, please raise a message to SAP for the same.
    I do not think system should split the manual planned order.
    Regards,
    Nitin Thatte

  • Issue with the SNP Extractor in APO-BI.

    Hi Experts,
    I am facing an issue with SNP Extractor. I have a SNP Extractor in APO system, and it has 4 datasources connected to it.Out of the 4 datasources, we are getting display of records for relevant selections in only one data source, but for the other three data sources, given what ever be the selections, it gives a message saying " 0 records available ".
    Please could you suggest, what can be the issue and also indicate a solution to resolve it. Do we need to apply any SAP Note to resolve the issue?? And where can we see the Current Support Package that is installed in the system??
    Replies in this regard, would be very helpful.
    Thanks and Regards,
    Bhargava

    Hi,
    you can see the Current Support Package in this way:
    Log on in your BW system --> System --> Status --> Component Information (hand lens) -->
    near the SAP_BW software component and  release, there is the level (for example 0006).

  • User are getting kicked out of SNP planning book

    Hello Experts
    I hope you can help me out here!
    From time to time we are experiencing strange issue for SNP user's .. User are getting kicked out from SNP planning book
    Please help us.
    Thanks
    Ramesh

    Hi Ramesh,
    As far as I know, users should not get kicked out unless someone terminates their session.
    Even if they lock some data and the same data is needed by some job, it's the job that would fail showing data lock. Similarly, if some other uses tries to access the locked data, the user who is accessing later would face the issue of not being able to go to edit mode.
    It's possible to write programs that could specifically do this work of kicking out users before we run batch jobs, but let me assume that this is not the case with you.
    One possibility is that there is issue in livecache and so users are not able to access livecache or get kicked out from their active session (e.g. your log area gets full, then users would soon get kicked out after seeing the system hanging initially). This you would need to check at the time when users face issue. This would also mean that other processes that need livecache should also fail e.g. GATP, or SNP planning or PPDS planning related jobs would fail at the same time.
    If you could share exactly what error message the users are seeing, that could be helpful in resolving the issue.
    Thanks - Pawan

  • SAP APO SNP planned order

    Hi,
    I am basically from PP background and just started working in APO SNP. after running SNP optimzer,not able to see the operation details in SNP planned order ( SNP planned order has only receipts, requirements ). could you please help me how to get operation details in SNP planned order.
    Thanks
    Krishna.

    Hi,
    SNP Planned Order:
    1 . SNP Planned Orders wil give details about Order start date and finish date .
    2.  During  SNP Planned Order creation a basic scheduling will happen.
    PPDS Planned Order
    1.  PPDS Planned Orders will give details about when the actual production is start and finish.
    2.  During PPDS Planned creation the Machine time details defined in the routing routing or recepie will be take into account.
    3.  Leadtime scheduling will be carried out to calculate the exact production start date and finish date.
    Thanks,
    nandha

  • Questions: SNP Optimizer - Pros/Cons/Pitfalls

    Hello Everyone,
    I have few general questions for the folks who have implemented SNP Optimizer. Please share your experience.
    1. What are the pluses and minuses using SNP Optimizer?
    2. What are some of the pitfalls using SNP Optimzer?
    3. For successful SNP Optimizer implementation, what are things that the project team need to watch out for and focus on?
    4. Any Tips on how to calculate relative Costs and penalties
    5. What type of reporting can be done on SNP Optimizer?
    Thanks,
    Sanju

    Hi
    The following link may help you in comparing Optimizer with other Planning engines.
    http://help.sap.com/saphelp_scm70/helpdata/EN/1c/186b398c15ef59e10000000a114084/frameset.htm
    Thanks
    Amulya

  • Read data from SNP planning book

    Hi Frnds,
    We are faced with a situation in which we need to read certain key figures such as PIR's, Goods Issue from SNP Planning book.
    We tried using BAPI "BAPI_PBSRVAPS_GETDETAIL" to retreive data. But it seems that we are giving wrong input data to the BAPI. Could you please let us know what to be fed into the BAPI in simple terms? If there is any example code for the same , would be very much appreciable.
    Orelse if there is some other way to retreive this data kindly suggest us accordingly...
    Many thanks in advance.
    Regards,
    Karthick

    Hi Karthick,
    The parameters for calling BAPI_PBSRVAPS_GETDETAIL really depends on your Planning Area and Planning Book configurations. The planning book configuration will limit what Characteristics and Key Figures will you be able to read using BAPI_PBSRVAPS_GETDETAIL. Let me give you an example.
    Assumptions: The planning book is configured as follows:
    Name = ZPB1
    Data view  = DV1
    The DV1 data view contains the characteristics 9AMATNR and ZCNTRY and Key Figures ZKF1 and ZKF2.
    Assuming also that we have the following data currently in livecache:
    9AMATNR-ZCNTRY-ZKF1-ZKF2
    000001234-PH       - 143  - 567
    000007891-PH       - 245  - 782
    000007891-US       - 124  - 890
    Let's further assume that you want the data aggregated to country level (e.g. char ZCNTRY), you have 1 planning version 'ZPAV1' and you only want the data for Country=PH, then here are the parameters that you need to pass to  BAPI_PBSRVAPS_GETDETAIL:
    PLANNINGBOOK = 'ZPB1'
    DATA_VIEW = 'DV1'
    SELECTION =  9AVERSION I EQ ZPAV1, ZCNTRY  I EQ 'PH'
    GROUP_BY = 'ZCNTRY'
    KEY_FIGURE_SELECTION  = ZKF1, ZKF2
    Hope this helps. Please post again if you have any questions. I can give you sample code if you can post your email address.
    Message was edited by:
            Emmanuel Nepomuceno (added planning version to selection)

  • Data available in RRP3 view but not coming in SNP planning book

    Hi All,
    I am facing an issue in SNP book. I can see forecasts in RRP3 view. But when I load the same data in SNP planning book, the forecasts are not coming there (forecast KF)
    I ran LC Cons check, PA cons check, OM17, but still the same result.
    Any pointer would be highly valuable.
    Regards,
    Manotosh Bhattacharya

    Hi
    If you look at the standard Forecast KF 9ADFCST in your planning area, it is usually assigned the Category Group of DF1. This category group only contains the category FA for forecast. If you create Forecast in /SAPAPO/RRP3, this will create Additional Forecast or category group FC. Therefore any forecast generated this way will not appear against the standard planning book KF.
    So you have two choices, if your forecast is only FC category then use the KF 9AAFCST Forecast (Addittional) in your data view or create a new Category Group with both FA and FC assigned to it and then assign this Categotry Group to 9ADFCST in your planning area.
    Regards
    Ian

  • SNP optimiser selection and customization

    Dear Experts ,
    Optimzation of demand with differnt storage location
    I in a phase of configuring SNP optimzer
    I have
    Planning Plant - 1
    Supply Plant  - 6  which is nothing but a storage location  in R/3
    The Requirement is  when there is a demand in the planning plant
    for Instance 100 Tons  (PIR FROM DEMAND PLANNING ) MUST BE OPTIMIZED TO
    SIX LOCATION (APO)  on the basis of  capacity, cost of production and distance from supply plant
    so is there any standard optimzer for this requirement , or i need to customize
    and please guide me is there any sap document for configuring optimizer and how to use optimzer in SNP and PPDs
    Thanks & Regars
    Raj
    Note : if you are not clear about my saying , please ask for more details

    Hi Raj,
    "Note : if you are not clear about my saying , please ask for more details".. sorry but I am not.
    You can model your optimizer profile as you need.
    Please follow the link : http://help.sap.com/saphelp_scm70/helpdata/EN/21/186b398c15ef59e10000000a114084/frameset.htm
    Thanks,
    Satyajit

  • SNP PPM Generation error

    Hi ,
    I am facing an issue in SNP PPM generation from PPDS PPM and getting an error as /SAPAPO/PPM_GENERATE124-u2018Start date of the generation period is in the pastu2019.
    I tried changing dates in field u2018Start of Gen. Periodu2019 to future in /SAPAPO/PPM_CONV_310 std TCode but still this error remains.
    Please let me know the missing part here u2026
    Regards,
    Digambar

    Hi Digambar,
    Please check SAP notes 737991, 524601 and 1036685.
    Whichever is relevant for you, implement it
    Regards
    R. Senthil Mareeswaran.

  • Product variant constraint in SNP optimizer run

    Dear All,
    I have a business scenario where I require a constraint on the number of FG variants produced per day. A number of FG SKUs come under a particular variant. On any day the factory is able to produce only a fixed number of variants (say 5). I am looking for a way to map this constraint in optimizer run.
    Will appreciate your thoughts to solve this problem.
    Regards,
    biplab

    Hi,
    Does SNP Optimzer considers the Set up costs in the planning run ?
    SNP Optimizer considers following factors for the optimizer Run:
    Factors Considered During the Run
    u2022        Valid transportation lanes
    u2022        Lead times
    u2022        Transportation capacity
    u2022        Transportation costs
    u2022        Handling capacity
    u2022        Handling costs
    u2022        Production capacity
    u2022        Production costs
    u2022        Storage capacity
    u2022        Storage costs
    u2022        Time stream (location master data)
    u2022        Lot size (minimum, maximum, and rounding value)
    u2022        Scrap
    u2022        Alternative resources
    u2022        Penalty costs for not fulfilling demand (supply shortage)
    u2022        Safety stock violation penalty costs
    u2022        Procurement costs
    u2022        Shelf life
    u2022        Cost multipliers
    u2022        Location Products
    u2022        Fixed PPM/PDS resource consumption
    u2022        Fixed PPM/PDS material consumption
    Regards
    Datta

  • % Remaining SL Field in the APO product master

    Hi All,
    Any body have used the field % Remaining SL field maintained in the product master. Does CTM or SNP Optimzer does consider this?
    What is the significance of the field?
    We have distribution center DC1 and plant PL1
    We have two minimum shelf life requirements for given product X e.g. Minimum Shelf life guarantee of 30 days for X at PL1 and Inter-company minimum shelf life of 45 days between DC1 and PL1.
    How can we design solution for this where for the stock transfer requisitions from DC1 to PL1 we want to use Inter-company minimum shelf life and Minimum Shelf life guarantee for sales order at the PL1. I am just thinking % Remaining SL (where I can define Ingtercompany Shelf life) is the one which helps me meet this inter-company shelf life, but it seems to be not working. May be I am not sure how do define and use it.
    Please share your thoughts, experience and ideas on addressing these two minimum shelf life requirements.
    Thanks.
    J.

    Try MAT_SET()
    MAT_SET ( ‘field name’ ;  field_value' ; <'product'> ;  '<version>' ) sets the value of the specified field in the product master record for the specified product in the specified version. The arguments for product and version are optional. If you do not specify an argument for the product, the system uses the currently planned product. However, it is better for performance reasons to use the function ACT_PRODUCT.
    MAT_EXTRA_SET() i think sets the fields in the extras tab

  • Factors influencing creation of a planned order

    Hi,
            What are the factors that lead to creation of  a planned order during a Heuristic run?
    When does a system decides to create a planned order? at what stock level? and how is the planned order qty. decided?
    I have a material in a location that has planned orders generated.
    I am trying to understand why the system created this order?
    There is no safety stock, safety days supply or target days supply or rounding profile  defined in Product master in Lot size tab.
    Lot sizing procedure is by period (Days)  - number of periods = 1
    Lot size strategy blank
    When I look at the product view,
    the requirements pileup with category SNP:DepDmd and after some days, a planned order is generated for some qty.
    I am trying to understand when the system determines to create a planned orders? What is the upper limit of the demand when the system generates a Planned order?
    In the system, some times the planned order is generated when the stock is at 2,484.567 PCs some times 13.645 PCs.

    Planned Order creation is based on a MRP calculations (net requirements planning) and ofcourse APO takes into account various factors such as min or max lotsizes, time-phasing requirements, calendars or safety stock requirements etc.
    Keeping aside the safety stock complexity in your situation, some of the reasons why a planned order could be created even with lots of stock in hand could be:
    1. Check projected stock on hand may be going down under 0 if the planned order were not created on time
    2. There would be a window of time for planned order creation due to production and other calendars that if lost would force projected stock in hand below 0
    3. the stock in hand is blocked stock not useful for planning
    4. Issues with SNP planning book configuration where key figures are not mapped correctly to ATP categories. Makes sense to double check in Product View
    5. Due to min lot size being high, it might appear that system is over planning production.

  • Date Problem in Scheduling Agreement  Creation

    Hi,
            When I create a scheduling agreement (Category : HG) say 31st bucket it automatically gets shifted to next bucket ( Weekly Bucket) Creating the scheduling agreement within the planned delivery time. Pls let me know the reason for this.
    Thanks,
    Siva.

    Check OSS Notes 770315 and 757870.
    There was a code issue for SNP Purchase Reqs which is corrected by notes 989857, 1045636 ad 1045891.
    Also note that the normal process for Procurement Proposal creation is a Backward and then Forward Scheduling. Due to varying calendars (receving and shipping) at the locations the results of Backward and then Forward Scheduling can give differences. However it should not create the receipts late (as is your case).
    Thanks,
    Somnath

Maybe you are looking for

  • Microsoft Outlook 2010 & 2013 cannot set automatic reply settings

    Hello, We cannot seem to set automatic reply's within outlook 2010 & 2013.  We have an exchange server 2010.  We can setup automatic reply through OWA absolutely fine.   The error that we receive is 'Your automatic reply settings cannot be displayed

  • Is my HD dead?  Mini won't boot but I can still Xfer my data from it??

    Yesterday I installed the recent updates for Java, Security, iTunes, and QT. after it was done I got a message that one or more did not successfully install, and that I could use the finder to try again (or words to that effect). I also got the resta

  • HELP:  Need to reinstall Acrobat X Pro

    I own Creative Suite Suite 6 Design and Web premium ver. After the last maintenance update to Acrobat X Pro I was getting hundreds of Distiller errors and Bonjour errors.  After trying a "repair" of Acrobat Pro X with no joy I uninstalled it.  Downlo

  • Fonts not updating in Illustrator CS4

    Dear Adobe Community: I am using the text tool and adding text to a document.  This is "artistic" text, not paragraph text without any appearance filters or effects applied.  When I try to choose a different font than the default which I believe is M

  • Dynamic Image Gallery AS2

    I have dipped in almost every search engine and this site to locate some easier way to create dynamic image gallery in Flash 8 AS2 using ASP (as i am conversant with ASP only, although i found many sites suggesting PHP and XML). I'd be very greatful