Issue in Sub Contracting Purchase Requisition Urgent!!!

Hiii All,,
I have maintained a two BOM's for a finished material one for In House production and one for Sub contracting the components for the Two BOM's are different.
i have maintained Two Versions for the finished material also.
when i covnvert a planned Order to an Sub Contracting Purchase Requisition alternate BOM doesnt explode. i have also maintained a production version in the Purchase info record. Still the main BOM explodes.
i have to manually change the planned order and give the other production version ie not the Inhouse BOM.
After creating the PR then again i have to go planned order and change to the normal InHouse  BOM.
Please Provide me the solution.
Thanx & Regards,
Kumar Rayudu

Hi Kumar,
BOM explosion occurs during MRP run and when you convert into purchase requisition.
If you are using procurement type "X", then logically system does not know whether you will be producing inhouse or go for external procurement.
You may consider to go for MRP areas or manually re-explode the BOM as you are doing now
Regards,
Jayakandan

Similar Messages

  • Sub contracting Purchase requisition not created thru Service Order

    Hi Experts,
    I configured to create Service order automatically from Customner service.
    Now we have the SM03 repair service order .When we try to create Sub contracting Purchase requisition.
    (Selecting Subcontr tick in External tab of Components tab)system gives error saying  --
    Op. 0010 must have exactly one component as 'Rework Material to Subcontr.'
    Message no. AD_SUBCON109
    I checked the notes and It was not help ful.I understand I was doing something wrong in creation.
    The control key used is SM03. Can any body help me in the above problem.
    Regards
    Rammohan.

    Dear Sen,
    The same error message refers to one of the following material provision indicators getting to me also:
    "S" - an entry within table T417 is missing where KZBRS (A&D-Specific Material Provision) is not set
    "X" - an entry within table T417 is missing where KZBLF (Rework Material from Subcontractor) is not set
    "F" - an entry within table T417 is missing where field ADSUB_DEFDLV (Deferred Delivery) is not set
    also, i Insert a row with S and keep MPCust and MPVend blank and Check the A&D MP box
    getting following error "
    Op. 0010 must have exactly one component as 'Rework Material to Subcontr.'"
    Can u tell me the config for MPI??

  • Goods receipt through Inbound delivery for Sub-Contracting Purchase order

    Hi
    I am trying to do goods receipt for the inbound delivery /shipping notification created for a sub -contracting Purchase order. The Finished product and the component part are batch managed, When I try to perform PGR in VL32N , I am getting a blank screen as error message and Goods receipt is not getting triggered . I checked for OSS note and found 645119 close to my issue but not an exact match . We are in ECC 6.0 with EHP 4. Can some one clarify whether it is possible to post GR through inbound delivery for a Subcon Purchase order .
    Thanks in advance for your immediate response.
    with regards,
    Joseph Anand B

    Hi, The issue may be due to this - the component is batch managed but the batch data is blank in the component list of the Purchase Order Item. Or a batch is maintained in the PO item component list but the stock for the same batch is not available with Vendor, i.e. stock with some other batch may be available.
    In a receipt for Sub-cont PO, 101 happens for FG and 543 happens for component. But there is no option to provide the component details in a delivery. So in standard system, when 101 happens via a delivery, 543 will be posted in the background. So any error in posting 543 will result in a blank screen without any error message.
    You can fix this by maintaining correct batch in the PO component list.
    But there is another issue - you cannot do 'cancel posting' and 'return delivery' for this receipt. Only you can reverse the inbound delivery and you should know that the  recevied stock shouldn't have been processed to do reversal of inbound delivery.

  • Sub Contracting Purchase Order

    Hi All
    What is table name and field name to see the alternative BOM status for Sub Contracting Purchase Orders?
    Example:
    I have a Material :Shaft, which has two alternative BOM's.
    When i placed the Sub Contracting order to the Vendor. System will explore the BOM and display the list of components.
    How to know that Which alternative BOM system taken to the PO?
    Can any body please suggest me the table name and field name?
    Thanks
    SUNIL

    Hi
    if you are working with Alternative BOM in sub contracting. the system works as follows
    first of all you should mantian the Sub-Con Info record for subcon  that in purchasing view you will have the production version, here you have to attach which production version you want to use asd as you know that the production version depends on your BOM and this BOM will inturn get exploded into PO, as you know that info record is the combination of Vendor and Material, only for this combination your alternate BOM will explode
    Hope i answered your question
    Regards
    VIkrama

  • Best Practice while creating Contract, Purchase Requisition, Purchase Order

    Hi
    What is the best practice with respect to Contract & Purchase Requisition?
    IN T Code ME31K, there is a button Reference to PReq, meaning that we can create contract with using Purchase Requisition. (We have done the same)
    While creating the Purchase Order using Contract, we could find Purchase Requisition reference in the Purchase Order; similarly when we created the Purchase Order using Purchase Requisition, we could find Contract reference in the Purchase Order.
    I have done the following:
    1. Create a Contract.
    2. Create a Purchase Requisition
    3. Assign Requisition and Create Purchase Order using T Code ME57.
    4. Create Purchase Order
    Here in this case we could find references of both Contract & Purchase Requisition.
    I just want to know what Practice should we adopt / advise while creating Contract, Purchase Requisition. & Purchase Order?
    Regards,

    Hi,
    In ME51N Screen, enter Contract number in the "AGREEMENT" TAB and if more items in the contract, you can mention the item number in the next TAB to the AGREEMENT TAB and then proceed with creating PR by entering other details. This TAB you can find in the 4th column from extreme right end of PR screen.
    Regards,
    Biju K
    Edited by: Bijay Kumar Barik on Sep 10, 2009 2:23 PM

  • Issuing storage location for purchase requisition

    Hi All,
    Anyone knew how to have a default issuing storage location on purchase requisition (source of supply tab) created through MRP?
    Thanks.
    Jump

    Hi,
    For this you need to implement BADI MD_EXT_SUP in combination with special procurement type 40 or 45.
    Documentation of this badi:
    Business Add-In for Determination of Issuing Storage Locatio
        Use
        You can use this Business Add-In (BAdI) to control the determination of
        the issuing storage location during stock transfer processing.
        The BAdI is used in the following components:
        Material requirements planning (PP-MRP)
        The BAdI runs both for manual creation of externally procured planned
        orders, and in the MRP during creation of stock transfer procurement
        proposals.
        Purchasing (MM-PUR)
        The BAdI runs as part of the source determination for purchase
        requisitions and during purchasing.
        Standard settings
        o   The Business Add-In is not active in the standard.
        o   The Business Add-In cannot be used multiple times.
        Example
        Sample coding is stored.
        Further notes
        Documentation on BAdI method GET_SUPPLYING_SL
        Documentation on BAdI method GET_PLIFZ
    MZ

  • Batch determination for Sub Contracting Purchase orders

    Hi
    I want to allocate automatic batch number while creating the Sub Contracting Purchase order (item cat: L).
    System should dynamically allot the batch, no manual process.
    This automatic batch number allocation should be work for sub contracting PO's not all Purchase orders.
    Please suggest the process.
    Thanks

    Hi SUNIL,
    I haven't done such thing so I'm nut sure whether it works what I'm writing, but according to the manual is it possible to assign automatic batch creation to movement types.
    As I understood in SPRO you can:
    1. Set the internal batch assignment:
    Logistic General > Batch Management > Butch Number Assignment > Activate IBNA
    2. Define the creation for the movement type you want:
    Logistic General > Batch Management > Creation of New Batches > Define Batch Creation for Goods Movements
    But I think you can't make difference between 'normal' MVT 101 and 'L' MVT 101. Isn't it possible to create a new MVT for subcon-GR?
    In this case maybe you could realize your idea.
    But defining a new MVT just because of thi might be troublesome...
    Maybe you can find better solution.
    http://help.sap.com/saphelp_46c/helpdata/en/25/283c3f4f7811d18a150000e816ae6e/frameset.htm
    BR
    Csaba

  • Issues in sub-contracting

    in subcontarcting scenario i have one issue
    issue 1:
    Materials (both excisable and non excisable) are supplied to
    subcontracting vendor.
    At this time in 57Fc challan only excisable items are maintained.
    But in sap while creating the sub contracting challan it is showing all
    excisable items and non-excisable items.
    But as per client requirement non-excisable items only should be displayed
    while creating /reconciling/completing the sub contracting challan.
    issue 2:
    when semi finished material is returned back to client by sub contractor
    some raw material is still with the vendor.
    while raising sub contracting order to the vendor  against the same
    material ,system should pop up how much raw material left with that
    subcontracting vendor .
    Kindly give me solution for this scenario.

    Hello,
    All the materials which are declared for excise have to be maintained against the respective chapter ID's. Please refer the settings in excise rate maintenance.i.e j1id.
    If only the non excisable items have to be appeared then only maintain the same.
    Please check if it helps. As I suppose you will get the help in J1id.
    Regarding issue 2:
    Is it the scrap that is produced at the the subcontractors level or the main parent raw material which is left??
    If scrap is left then that has to be mentioned along with the components provided at the sub contractors level.
    If the parent material is left then it has to be checked at the stocks at the subcontractor level and brought back by GR against 101 mvt type.
    The BOM has to be defined accordingly. If semi finish of 1 is to be produced by supplying 2 parts of raw material then mentioned only the one which is required. Do not supply additional extra Quantity.
    Regards,
    Prasanna.

  • Sub-contracting purchase for by-products

    Hi
    I am doing Sub-Contracting PO for By- Products. I have maintianed in BOM , the by-product material code in "-ive" qty.
    Consider Material A - Main Product
                   Material B - By_Product
                  Material C - Raw Material
    When i do GRN, Material A triggers 101 movement Tpe, Material B triggers 545-0 Moveent Type and Material C triggers 543-0 Movement Type.
    But When i check the stock of material, Material B is lying as Vendor Stock.
    Kindly let me know whether this transaction and movement type updation is correct.
    Else let me know the steps.
    I need to Receive Material A and Material B in my Stock.
    Thanks & Regards
    T.Madhesh Kumar

    HI
    Thanks for u r reply. But i need to receive the material A and material B same time during Goods receipt itself. Is there any possibilities that i can receive both the material in Un-restricted stock during goods receipt.
    Thanks & Regards
    T.Madhesh Kumar

  • No BOM explosion for sub-contract purchased materials

    Hello,
    I have searched google and this forum and have not found any info on this.  Hopefully someone has run across this same situation and can help.
    We do not want to have a bom explosion happen for externally procured materials (using CU51).  We are using user exit CCUX0800 (EXIT_SAPLCUKO_008) to set no_expl_ext_procurement = 'X'.   This works good, except if the material is set up for external procurement (marc-beskz = "F") and also has a special procurement (marc-sobsl) of "30".  Include LCUKOFFB says to still explode the BOM if the special procurement is "30". 
    Does anyone know why it does this?  We don't want the bom to explode for externally procured parts even if they are set up as subcontracting ("30").  Any way we can do this with a different user exit?
    Thank you.

    Melissa,
    Since you are using Special proc 30 ( subcontracting) system assumes BOM components will be supplied by purchaser.
    When a Subcontract purchase order for subcontracted material is cut on vendor, the components of the subcontrated product is typically supplied by buyer to the vendor. Hence MRP(system ) typically explodes BOM to plan for those compoments in buyer's plant.
    If however you do not want BOM to be exploded &/or components planned in buyer's plant you can set that in BOM of subcontract material at the component level. In the BOM component item detail screen (under tab status/long text) there is a field called Material provision indicator. Set that to L(material provided by vendor).
    This should prevent planning of components (or explosion of BOM) for the subcontract material ( with settings F, 30).
    Hope this clarifies & solves your issue. else please come back with further questions.
    Thanks,
    Ram

  • Sub-contracting Purchase order not functioning properly

    Hi
        We are having issues with a PO 45007xxxxx. This PO is set-up as a subcontracting PO. In the component section I have a material 1232  that it is supposed to consume material 1232 when material 97 is received against this order. At the end of March 2015, the 1232 consumption stopped. When we receive material 97, there is no longer a line for the 1232 consumption that automatically populates and occurs simultaneously with saving the GR. If I look at the GRs against this PO prior to 27.03.2015,  I can see the accurate 1232 consumption.  what ever I did GR after 27.03..2015,there is  no longer aline for the sonsumption material when I save my GR.
    Can some body guide me,please for this issue?

    Hi Hussain,
            As you told one Po entered item category L and another PO not entered " L".  If not entered means its normal PO and will not get BoM components in MIGO.
    And also what Patra told is correct. If you are not selected in MIGO for components then it will be post the line which is ever checked..
    For these you have reverse and do again transacation...

  • Tracking Sub contracting Purchase Order

    Hi ,
    We have a Subcontracting Purchase Order.
    The users have created a delivery from ME2O and PGied it.
    They have forgot the PO number for which they have created the delivery and PGied..
    How can we track the subcontracting PO if we know the LB delivery type number??
    Can anyone let me know ??
    Thanks

    Hello, Srikanth
    There is another way to findout the (if you forget the PO number for which Delivery and PGI is done).
    How,
    instead of Delivery document type (i mean LB for SC-PO)
    you can try with Item catagory (i.e, L is for Subcontracting) or with several options like, PO Tracking number and Delivery date also through t.code: ME2B
    (i.e, PO by tracking number)
    Suggestion: Because, anyhow you or the user (SC PO processer) might be knowing that the delivery is for Subcontracting PO. 
    then
    based on Item catagory (i.e, item catagorey L is for Subcontracting) he can list the SC PO. Try with that.
    Hope this will clarifies you,
    Reward, if it helps,
    Regards,
    Srin.K

  • Issue with ME53N - Display Purchase Requisition

    Hi All,
    When i am opening the t-code ME53N, am getting the following error :
    "Company was not supplied in function module interface."
    Could anybody tell me the reason for the same.
    Regards,
    Guddan

    I think you're posting in the wrong forum, this is rather a question for the MM-part.
    A quick search gave me this result :
    br,
    Björn

  • Sub contract MRP Settings

    Hello
    Can any one guide me , how to do MRP settings for subcontract Proces.We want the system to generate MRP for the subcontract Process, We need B & C Material to Make A.  A is a finished goods , B is going to Produce and ship to subcontract Vendor  and C will be Procured and directly shipped to Subcontract Vendor . We are going to get back A as a finished Goods. Can any one please tell me what will be the MRP Settings required to create a Sub contract Purchase Requisition ?
    Thanks
    JJ

    Hi,
    For material B, it is a inhouse production. Set E - inhouse production in MRP2 view.
    For material C, it is a External procurement - F, assign in MRP2 view. For material C, maintain delivery place at Subcontract place in MIGO screen, so that material directly dispatch to subcontract place.
    For material A, external procurement - F, maintain in MRP2 view. Maintain BOM for material A.
    When BOM explodes, P.R will create for material A.
    Send material B by ME2O 541 mvt.
    And receive material A by MIGO 101 mvt.
    Regards,
    Dharma

  • Sub-Contracting material Issued to Vendor and balance to be Issud

    Hi,
    Sub-Contracting material Issued to Vendor and balance to be issued against the Sub-contracting Purchase Order.
    Please suggest T.Code for the same.  (Same Like ME2O, but PO number should be an input parameter)
    For example I have Created PO with header Material for 1 quantity which having one child item and qty say 20 numbers, and issued child material to vendor 10 numbers (541) and balance is to be issued to vendor is 10 numbers, now I want a report which gives PO number, Header item with qty, total requirement of qty for the child item with line item number, issued child item with qty and balance to be issued child item with qty.
    Thanks
    Ramesh.G

    Report MB51 is there. Here you have to input your Purchase order number and execute but, it will show only material issued to subcontractor through 541. It will not show the balance quantities.
    And there is no such standard report which will show information how much issued to subcontractor and how much is balance based on Purchase order.
    You can develop a z report with the help of abaper.

Maybe you are looking for

  • I am unable to update  apps on my iPhone 5.

    I am unable to update my apps on my iPhone 5. As I select the update button it asks for my password but the goes back to like it was. I have already rebooted a couple of times & even logged out & signed back into my iCloud, iTunes & App store. Nothin

  • IDVD Slideshow picture glitch

    I keep getting a rogue image in one of my slideshows that pops up at the end of the slideshow. It doesn't appear in the preview mode and I already deleted the entire slideshow and redragged all the pictures back into the slideshow. This one image kee

  • How to determine (sub)work-item in bpm

    Hi all, is there a way to determine the actual workitem in a bpm. I want to map this workitem in a xml-structure and send to a receiver just for log function. Best regards Mathias

  • Can the Acrobat SDK be used to turn off protected mode(Sandboxing mode)?

    Can the Acrobat SDK be used to turn off protected mode(Sandboxing mode)?

  • [AS CS3] Export JPEG options, setting, export selection

    Hi all, I am having trouble getting a JPEG export of a selected group of items to adhere to the export options I'm setting. I swear I've done the same thing with PDF export prefs and it works OK. I need to export a group that is selected, not the who