Hi All,
I have a requirement of transferring data from ECC to APO. I am using EXIT_SAPLCMAT_001 fro this purpose. The problem is, I need to transfer the data of a field that is not present in cif_matloc but present in /sapapo/matloc.
How should I proceed...Please help....this is an urgent requirement
Thanks & Regards,
SriLalitha

Hi,
you may want to go to the transaction /SAPAPO/SNP_SFT_PROF
Determine Forecast of Replenishment Lead Time
Use
In this field, you specify how the extended safety stock planning determines
the forecast of the replenishment
lead time (RLT). The following values are available:
Supply Chain
The system determines the RLT forecast using the supply chain structure by
adding the corresponding production, transportation, goods receipt, and goods
issue times. If there are alternative procurement options, the system always
takes the
longest
option into account.
Master Data
The system determines the RLT forecast from the location product master
data.
Master Data/ Supply Chain
First, the system determines the RLT forecast from the location product
master data. If no RLT forecast can be determined, the system determines the
forecast using the supply chain structure (as described under
Supply
Chain
Dependencies
You can retrieve the replenishment lead time forecast yourself by using the
GET_LEADTIME
method of the Business Add-In (BAdI) /SAPAPO/SNP_ADV_SFT.
Replenishment Lead Time in Calendar Days
Number of calendar days needed to obtain the product, including its
components, through in-house
production or external
procurement.
Use
The replenishment lead time (RLT) is used in the enhanced methods of safety
stock planning in Supply Network Planning (SNP). The goal of safety
stock planning is to comply with the specified service level, in order
to be prepared for unforeseen demand that may arise during the replenishment
lead time. The longer the RLT, the higher the planned safety stock level.
Dependencies
The field is taken into account by the system only if you have specified
master data or master data/supply chain in the RLT: Determine
Forecast field of the safety stock planning profile used.
Hope this helps.
The RLT from ECC is in MARC-WZEIT which is transferred to APO in structure /SAPAPO/MATIO field CHKHOR.
May be if you maintain the setting in the profile, you may get the value in RELDT.
Thanks.

Similar Messages

  • Master/Transaction data from ECC to APO-BW

    Hi All,
         Normally we come across scenarios where Master/Transaction data is pulled from ECC to BW and then pulled into APO-BW. What are the pros and cons of CIF (direct connection between ECC and APo-BW) rather than pulling data from ECC to stand-alone BW and then into APO-BW?
    Regards,
    Joy

    Hi Santhana,
    If you want to add data of ECC to APO BW & Then in to DP, then follow the following Steps.
    1. Create Generic Data Source in ECC for thet Sales Order table.
    2. Replicate that data Source in to APO BW with Source System.
    3. Create whole data flow process by using created Data Source.
        Data Flow Process: 1. Info Package
                                      2. Info Source
                                      3. Info Cube
                                      4. Transformation between DS & IS, Then IS & IC
                                      5. Data Transfer Process.
    4. Load data from ECC to APO BW
    5. Use transaction /n/sapapo/tscube, for copy Info Cube data to Planning Area.
    Hope this will help you.
    Regards
    Sujay

  • Fetching data from ECC to APO

    Hi,
    I have fetch to data from ECC custom table to APO and create data, can anyone let me know the procedure.
    Thanks in advance

    Hi Santhana,
    If you want to add data of ECC to APO BW & Then in to DP, then follow the following Steps.
    1. Create Generic Data Source in ECC for thet Sales Order table.
    2. Replicate that data Source in to APO BW with Source System.
    3. Create whole data flow process by using created Data Source.
        Data Flow Process: 1. Info Package
                                      2. Info Source
                                      3. Info Cube
                                      4. Transformation between DS & IS, Then IS & IC
                                      5. Data Transfer Process.
    4. Load data from ECC to APO BW
    5. Use transaction /n/sapapo/tscube, for copy Info Cube data to Planning Area.
    Hope this will help you.
    Regards
    Sujay

  • Transaction data from ECC to APO DP

    Dear All,
    Can you tell me if i can directly load transaction data directly from ECC to APO BW Infocube.
    For example i want to load say sales orders from ECC.
    Can i directly load from ECC --> APO BW Infocube --> DP Keyfigures.
    Or any staging is required inbetween ECC and APO BW
    Thanks
    Santhana.

    Hi Santhana,
    If you want to add data of ECC to APO BW & Then in to DP, then follow the following Steps.
    1. Create Generic Data Source in ECC for thet Sales Order table.
    2. Replicate that data Source in to APO BW with Source System.
    3. Create whole data flow process by using created Data Source.
        Data Flow Process: 1. Info Package
                                      2. Info Source
                                      3. Info Cube
                                      4. Transformation between DS & IS, Then IS & IC
                                      5. Data Transfer Process.
    4. Load data from ECC to APO BW
    5. Use transaction /n/sapapo/tscube, for copy Info Cube data to Planning Area.
    Hope this will help you.
    Regards
    Sujay

  • CIF of transaction data from ECC to APO

    Hi,
    I wanted to know where we maintain the configuration for real time transfer of transaction from ECC to APO.
    I know for master data we have an option in CFC9 for real time/periodic transfer. Is there any similar config for transaction data too like sales orders etc.

    Hi Alok,
    To allow online transfer of changes to transaction data from SAP R/3 to SAP APO, you have to activate generally the BTEs in SAP R/3.
    This is done in R/3. This is the path:
    SPRO --> Integration with Other SAP Components --> Basic Settings for the Data Transfer --> Change Transfer --> Change Transfer for Transaction Data --> Activate Online Transfer Using BTE
    You can read about it here:
    Change Transfer for Transaction Data - Integration via APO Core Interface (CIF) - SAP Library
    Then of course you will need to generate and actiave your IModels.
    Kind Regards,
    Mariano

  • Transfer of PIR from ECC to APO - Time stamp

    Hi Friends,
    We are transferring Planned Independent requirements from ECC to APO through CIF.
    In APO Product view Forecast requirements Date is sync fine with ECC date however the time is setting default to 03:00:00 am.
    we want the time to be set to 06:00:00 am by default.
    How we can we archive this?
    Regards,
    Krish

    Dear Tiago,
    I changed Product view Time zone settings, and issue resolved.
    Thanks for your valuable reply. Awarded you the points.
    Regards,
    Krish

  • How to transfer Sales BOM from ECC to APO DP

    Hi,
    Demand planning require Sales BOM from ECC. Sales BOM in ECC will not have Routing & Work center, then how a PPM with Sales BOM can be transferred.  If i have to create a dummy routing & WC for those sales BOM it will be tidious job to create all the master data. Is there any way to transfer the BOM alone from ECC to APO.
    Please throw some light on it.
    Thanks & Regards
    Shan

    Hi Somnath / Ritesh,
    Are you sure about ciffing Sales BOM(usage 5)to APO as PDS ? Did you test it or your comments are based on SAP documentation?
    I tried to CIF Sales BOM as SNP PDS, it is creating PDS with only parent item.Child items are missing.I have not used any production version here.
    If i use production BOM(usage 1), it is creating PDS with both parent and child items.I have not used any production version here also.
    SAP says BOMs can be ciffed to APO as PDS. No productions versions are required. but it has not mentioned about BOM's usage. May be , Is it by default production BOM?
    One more question, Is it possible to create production version with BOM usage 5? It has no meaning right..
    I think system does not allow you to create production version with BOM usage 5.
    I also tried with BOM usage 2. In this case also it behaves like sales BOM.
    looks like only production BOM can be ciffed with proper BOM structure in APO.
    if required i can send you the link to share screen shots.
    Pls comment..
    regards,
    Umamahesh

  • Transfer product division from ECC to APO

    Hi Experts,
    To transfer product division field from ECC to APO, I have made changes in FM EXIT_SAPLCMAT_001 to add entry in table OT_CIF_MATKEYCUS. And it is populating record correctly.I have added a field for product division in table /SAPAPO/MATKEY.but product division field value is not transfered to APO side. Is there any change I need to do at APO side ??

    Hi,
    have you checked documentation for FM EXIT_SAPLCMAT_001? It's written there that you need to implement user exit APOCF005 in SAP APO.
    Cheers

  • Transfer purchase requsition from ecc to apo

    Hello,
    When creating purchase requirements in ECC, they are not transferred to APO although there is model integration. If I activate again the model, the pur req are trasnferred.
    In CCR
    It gives the error 181 in Schedule line does not exist in APO
    Schedule line does not exist in APO
    Message no. /SAPAPO/CIF181
    And the Queue is not bloqued, and the model is active.
    Thanks

    Hi Fernando,
    Based on the information given, it seems there is problem in
    activation.
    1) Check is there more than one model activated for purchase
    requisitons
    2) Check the master data (purchasing view) has been
    maintained for those items in R/3 level
    3) Check distribution definition is maintained in APO
    customisation
    4) I have a query in which, in general PR transfer will be
    from APO to R/3, in your case it is reverse, is there any
    business requirement?
    5) Check transfer to SNP orders to OLTP system in APO
    customisation
    Regards
    R. Senthil Mareeswaran.

  • CIF - Master/Transactional Data From ECC to APO

    Working on CIF Data From ECC6.0 to APO(SCM 5.0)..
    If i choose MRP type XO in ECC - Master Data & Transactional Data is moving properly to APO.
    As we are using MRP in ECC6.0..and the MRP Type is PD...
    I want to CIF the Master Data & Transactional Data using MRP Type PD? is it possible?How?
    Regards,
    Rajesh Patil

    Hi Rajesh,
    As visu rightly indicated, it is always safer to use XO while planning in APO.  Still, if the business requirement compels to use PD, you can cif with PD, then copy the data from active to an inactive version and then carry out the simulation planning.  Once results are copied, you can change the mrp type to xo in R/3 and re-cif it.  Then you can compare the result in APO between active and inactive versions.
    Regards
    R. Senthil Mareeswaran.

  • Transfer field Value from ECC to APO

    Hi,
    I want to transfer a field from material master to APO. For this i am, using a CIF user exit... The field is not available in the ECC side (EXIT_SAPLCMAT_001), but i found a user exit on APO which has this field (EXIT_SAPMMDUSER_005) which i m not sure if it is called.. please help...

    Hi,
    Could you please send the details..What field you are checking..Field name ?
    You can explore the below 2 table in ECC EXIT EXIT_SAPLCMAT_001. It has the option for expansion.
    OT_CIF_MATKEYCUS
    OT_CIF_MATLOCCUS
    Thanks
    RKS

  • Transfer HR data from ECC 5.0 to CRM 5.0 via HRMD_ABA

    Hi there.
    We are implementing CRM for the first time using version 5.0.
    We wish to use ALE distribution via message type HRMD_ABA.
    We have researched all main notes (312090, 550055 and 934372 to name a few) and have set up configuration accordingly.
    We copied the HR to SRM/CRM 4.0 (with Qualifiations) distribution model template with data filter, distributed the model to CRM and succcesfully generated both partner profiles.
    The outbound parameter generated a HRMD_ABA04 idoc type. 
    We note when using the RHALEINI program that IDOC segment E1P0006 is not included against our employees.  Also IT0006 is not available as a selection in update mode.
    We confirm the template filter includes settings for object P, IT0006, subtype 1 and such addresses are maintained for our employees.
    Can you please advise suggestions why E1P0006 segments are not being included against the outgoing IDOC's.
    Thank you and kind regards.
    Stephen.

    Hi Pratik,
    Yes the IDOCs are passing successfully through to CRM with status of 03 (IDoc sent to R/3 System or external program).  However segment E1P0006 is not included within the IDOC.
    I performed an authorisation trace via ST01 whilst performing the distribution via RHALEINI and found no authorisation issues.  The trace did note authorisations were passed for IT0000, IT0001 and IT0002.  IT0006 was not checked.
    It appears the data filter as copied from the template for object P, IT 0006, subtype 1 is being ignored?
    Kind regards
    Stephen.

  • Transfer of fields from ECC to APO

    Hi All,
    I have a requirement where in I need to implement logic for Repl. Lead time as follows -
         1. check if the purchase info record exists
              if exists, then check if the current date is between lifba and lifbi of EINA table
                   if exists then pass EINE-APLFZ to AT101 field of cif_matloc
         2. if purchase info record does not exist, then pass the lead time from Material Master data.
    I have done the coding in Exti_SAPLCMAT_001 (ZXCIFU01).
    the issue is, its not checking for the existence of info record, directly the lead time is being taken from material master data.
    Pls help...this is an urgent issue.
    Thanks & Regards,
    SriLalitha. 

    Hi SriLalitha,
    I have loaded a document explaining how you can set defaults values in APO MAT1 when the material is CIFfed. See this document, here you have the ABAP code:
    http://scn.sap.com/docs/DOC-56755
    This need to be done in APO, thru BAdI: BADI SMOD_APOCF005. In the ABAP code in APO you will need to use function: 'RFC_READ_TABLE' in order to get the details from table EINE. In my example, I am doing something similar checking values from tables MARA and MARC.
    Thanks and Regards,
    Mariano

  • CIF STEPS to load data from ECC to APO from Process chain

    Hi,
    i try to create on ECC system a process chain in order to execute the CIF program for updating APO Material/Plant Master data on DELTA mode .
    I am not sure that the procedure is correct, at the moment i put on a chain:
    - Step 1 Program RIMODGEN with a specific variant
    -Step 2 Program RIMODACT2 with a specific variant.
    Is necessary a third step with RIMODACT2 in order to deactivate the integration model?
    On APO we have to insert other standard step in order to complete the delta update?
    Any experience on similar situation?
    Thanks,
    Veronica

    Veronica
    You do not need a third step. You do not need to deactivate the model. In fact, it is not recommended to do so. You do not need any step in APO.
    If your CIF setup is correct, the first two steps should be enough.
    If by 'Delta', you mean field value changes to material/ plants in an existing integration model, you dont even need to do CFM1/ CFM2 if you have setup transaction CFC9 for BTE (online transfer).
    Rishi Menon

  • How to delete Master Data transferred from ECC to APO via CIF

    Hi, all
    I'm connecting SCM 5.1 with ECC 6.0 via CIF.
    When activating Integration Model in ECC, the following error occurred;
       "Location 0001 of type 1001 (BSG 592BUSGP) already exists in APO"
    This is because Location 0001 was already transferred from different ECC client via CIF, and not cleared.
    I'm now trying to initialise master data transferred from ECC to APO via CIF, but in vain.
    I suppose I have to first delete all master data CIFed from ECC in APO, or have to execute initialisation of APO master data with ECC data in ECC.
    Please tell me how to do this.
    For details, please read the followings;
    I connected APO client with ECC client 590.
    I transferred Plant and Material Master from ECC to APO via CIF.
    After that, I wanted to change ECC client from 590 to the other.
    I created the other client (592) by client-copying from 590 with SAP_ALL copy profile.
    I deactivated Integration Model in ECC 590, and activated the same in ECC 592.
    Here, I faced the problem.
    The initial data transfer failed due to the duplicate of data.
    Now I'm wondering how I can initialise master data in APO and transfer initial data from ECC.
    Due to testing purposes, I have to change ECC clients from one to the other this time, but I cannot initialise master data in APO and cannot tansfer initial data from different ECC client.
    thanks in advance,
    Hozy

    Hi all,
    Thank you very much indeed for lots of your replies.
    Thanks to all of your advices, I'm getting to understand what to do.
    Well, I'll say I have to create one more client for testing with other ECC clients or I have to rebuild the client by client-copying from 001 and implementing all transportation requests, for marking del flags to each master data and running del programme sound like tough work, and sound like odd ..
    Then, I've got next issue here.
    In SCM-APO, I use BI objects, and , if I have to create several clients for testing, I have to set up clients where you can use both BI objects and CIFed master data.
    I suppose I have to change 'BWMANDT' in RSADMINA and make RSA1 accessable in other SCM clients and implement tests.
    Also, I have to register BI System for newly created SCM clients in RSA1-SourceSystem.
    Well, if you have any experiences on this kind of use, and if you have any advice on it, please give me any tips.
    Particulary, I'd appreciate very much if you give me advice on which way you have chosen; creating several clients or rebuilding the one client in SCM-APO when you use both BI objects, CIFed master data and Demand Planning.
    Thanks in advance.
    Hozy