Issue services with different Internal Orders within a Plant from one PO?

Hiii... Please advice me of issuing services through one purchase order (one vendor comes and do the service to different machines of different internal orders in a plant) to different  internal orders within a plant.
Thanks
Manoj

what is the problem?  you can have Multiple Line Items in a PO  (one for each internal Order).
And within one Line item you can add multiple service lines.

Similar Messages

  • Design a single template for multiple reports with different column order

    Hi,
    I need to migrate the existing reports from SQL Server Reporting Services to Crystal Report 2008, and the column order in the report is very important to the clients since clients have existing code to ingest these reports into their database. Now I want to create a single template with lot of parameters for all reports. My question is how I might use one template to create multiple reports with different column orders in the reports?
    For example, client A has the following column order in their report: firstName, LastName, DateBirth, SSN. Client B has the following column order in their report: SSN, DateBirth, LastName, FirstName. Can I use one template to create these multiple reports?
    Thanks in advance.

    -As I mentioned you can find Template Field object in Insert menu of crystal report Designer 2008.
    As soon as you select Template Field object you will be able to see a box beside ur mouse cursor. Drag and drop this box at required place. Now when you place this object in report you will get some thing like this "<TemplateField1>" listed under Formula Fields tree. Double click "<TemplateField1>" formula to add your conditions.
    -I have not tested it for large amount of Customers. However as the number of customer increases the number of conditions will get increased.
    For the customer that want the same ordering of columns you can put those customers under one condition.
        for Example...
              if(?Client in ['clientA','clientA']) then
                        <TableName>.<Field>......
    -What do you mean be 40 columns? Do you mean 40 fields or you want to show 40 columns in report? Please elaborate.
    Regards,
    Amrita
    Edited by: Amrita Singh on May 21, 2009 7:54 AM

  • Totally confused about mixing videos with different field orders.

    I have PPcs5 on the pc.
    I edit for many different shooters. As such I get everything: Progressive, upper field , lower field . Not to mention from a zillion different cameras & different resolutions.
    I output 95% so far to dvd ntsc, 5% BR.
    I get dv tapes on some & HD files also.Many times I get a mixure of both on each job. Also Iphone HD files too. Going crazy trying to fiquer out how to set up my sequence when I have upper field  or progressive by themselves & also when they are mixed with lower field dv foot...Do I force everything into a lower field seq if going to dvd?
    Do I have to deinterlace anything?
    If I drag a clip to the new "create seq" icon, it will match the clips properties but is that correct if its a progressive only project or an Upper field project going out to dvd ntsc?
    Do I need to RT click on the clips in the project window & "interpet Footage" & force it into a lower field there 1st? Is there a difference between setting up a seq to be played on a progressive DVD player hdmi to a prog TV as apposed to setting up a seq for a non hdmi or non progressive tv?
    Does outputting to dvd automatically force it to lower field ?
    If my seq isnt set up correctly I notice a big interlace problem when the cams pan from side to side, especially when there are multiple cams with different field orders. Have been unable to find any good discussions or articles on the topic.
    How do you guys do it without going crazzzzzzzy?Are there rules? What are the rules? A rule book would really help:-)  I Yern for the old DVCAM/DV days:-)

    DV is always lower and HD is upper or progressive.
    As you are having all fields in one timeline i would make it progressive.
    Premiere does a good job in deinterlacing.
    Only use Interprete footage when the footage is interprete wrong.
    Set up a progressive timeline and drop everything in it. If a clip does not behave correctly you can change fields in the Field Options.
    Export from Premiere and import into Encore. That is what i would do......

  • My iphone 3gs ran out of power, now wehn plugged in it will not restart, tried plugging in with different chargers, holding home key and other one but nothing works, screen is either battery icon or Apple iconn

    my iphone 3gs ran out of power, now wehn plugged in it will not restart, tried plugging in with different chargers, holding home key and other one but nothing works, screen is either battery icon or Apple iconn

    Hi, beth.lau.gr.
    Thank you for visiting Apple Support Communities.  
    I understand you have been experiencing issues with your iPhone restarting and showing you a blue screen.  I wont be able to give you an exact answer as to why this is happening.  However, this is the most relevant troubleshooting article for this issue.  This article also provides options to reach out to us via phone for additional assistance.  
    If your iOS device restarts, displays the Apple logo, or powers off while you're using it
    http://support.apple.com/en-us/HT203899
    Cheers, 
    Jason H.  

  • I have a question about using multiple ipads in our school.  Each of our teachers have a iPad and AppleTV in their classroom.  The issue is, with our classrooms so close in proximity to one another, is there a way to pair teacher

    I have a question about using multiple ipads in our school.  Each of our teachers have a iPad and AppleTV in their classroom.  The issue is, with our classrooms so close in proximity to one another, is there a way to pair teacher #1 iPad to its AppleTV without effecting/projecting onto the adjacent teachers #2 classroom AppleTV?

    Not as such.
    Give the AppleTV units unique names and also enable Airplay password in settings with unique passwords for each teacher.
    AC

  • I have a document made up of separate PDF files which reside in a folder and are linked to each other via hyperlinks. Each pdf file is set to open with bookmarks displayed, however if I link from one PDF file to another and use the "Previous View" button

    I have a document made up of separate PDF files which reside in a folder and are linked to each other via hyperlinks. Each pdf file is set to open with bookmarks displayed, however if I link from one PDF file to another and use the "Previous View" button to navigate back to my starting point the bookmarks are replaced by "page thumbnails". Is there anyway to stop this from happening?

    Hi Pusman,
    While setting up the links, if you choose to open the file in a new window then you won't face this issue, then you can simply switch to the previous file and bookmark view will remain as it is.
    Does that helps with your query?
    Regards,
    Rahul

  • Adobe InDesign CC 2014 Custom Panel Built With Extension Builder - Problem: Can't tab from one entry field to the next; Hitting tab instead hides all palettes; Is there a fix? This didn't happen in Adobe Indesign CC

    Adobe InDesign CC 2014 Custom Panel Built With Extension Builder - Problem: Can't tab from one entry field to the next; Hitting tab instead hides all palettes; Is there a fix? This didn't happen in Adobe Indesign CC

    This is planned to be fixed in the next release.

  • Services with different IP address subnets over CSS 11500 series

    Hi all folks!
    I have two CSS 11500 series...
    In just a few months i will have ready a DRS (Disaster Recovery Site), where i will have 2 more servers to add to the environment.
    But this servers will be in a different subnet from that today i have for the servers who are configured in the current services of my CSS.
    So then the doubt i arises is:
    Is correct to add two new services with these servers, but using the IP addressing of the DRS site???, and including on the CSS a static route to this network, (of the DRS) in order to reach them?? is it correct, it will work well?
    This would be so....
                 ________________LAN to LAN_____________________
                 |                                                                                |
                 |                                                                                |
    |------SITE A------|                                                        |------SITE B------|  
         [Firewall] ===============IPSEC============= [Firewall]               
               |                                                                                |
               |                                                                                |
    [CSS-A]-[CSS-B]                                                            [SWITCH]
           |          |                                                                     |         |         
         [SWITCH]                                                                    |         |                                                                 
    [srvA] [srvB] [srvC]                                                          [srvD] [srvE]
    So, at [CSS-A] & B, i will put a static route to firewall that know the subnet of site B through the IPSEC tunnel.
    So In the CSSs, i will add the new services for the Servers "D" & "E" with the IP address of Site B.
    This should be seen as well:
    !*************************** GLOBAL ***************************
    ip route 0.0.0.0 0.0.0.0 [IP FIREWALL]
    ip route SITE B [IP FIREWALL]
    !************************** SERVICE **************************
    service srvA
      ip address A.A.A.x
      port 8080
    service srvB
      ip address A.A.A.x+1
      port 8080
    service srvC
      ip address A.A.A.x+2
    port 8080
    service srvD
      ip address B.B.B.y
    port 8080
    service srvE
      ip address B.B.B.y+1
    port 8080
    I know that this practice is not the most desirable, in fact should use"Basic Global Server Load Balancing Site Redundancy Using the CSS with DNS", but I don't have much time to change the entire environment today, and in this first stage i have to begin with this poor but quick solution that i thought and i wanted to be validated if there is posibliidades this to work
    Within their experiences that they say? Will operate?
    Thanks in advance!
    Regards!
    Esteban =)

    Daniel!
    Sorry by delay!
    Thank you so much for you time for reply.
    You have given me a great help to this doubt!
    But..using "source group" let me know..
    I can´t undertand the really difference between NAT with ACls as you can see at this link: (http://www.cisco.com/en/US/products/hw/contnetw/ps789/products_tech_note09186a0080093dfc.shtml)
    and
    this other link, using NAT (from the piont 5), (http://www.cisco.com/en/US/products/hw/contnetw/ps789/products_configuration_example09186a0080093dff.shtml)
    where the NAT is configured under a method different from the previous one..
    So.. for this scenario described above, which would you recommend using? I would think that the second is the most indicated truth? What do you think?
    Thanks in advance again!!!
    Have nice day!
    Regards.
    Esteban.

  • Issue While Executing the Internal Order in KO8G

    Hi,
    Whle executing the internal order in KO8G,I am getting the below error.
    Complete Allocation Structure A1   and Message no. KD503
    I have reversed/cancelled all the relevent Material documents related to that PO,even after i am getting the same error.
    Error is as follows-
    Complete allocation structure A1
    Message no. KD503
    Diagnosis
    During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
    Cost element 414126 cannot be assigned to a settlement cost assignment in allocation structure A1, and therefore it cannot be assigned to a settlement cost element.
    Procedure
    Possible solutions are as follows:
    If the posting under cost element 414126 was made to the sender because of an incorrect entry, and you can reverse the posting, and do not need to update the allocation structure. You only need to reverse the incorrectly assigned posting before repeating the settlement. Exception: For an investment measure with a line item settlement, you need to extend the allocation structure, even after the reversal.
    If the posting was made correctly, you can do the following:
    a) You can assign a different allocation structure to the sender: In the master data maintenance for the sender, choose "Settlement rule -> Goto -> Settlement parameters" and then enter a different allocation structure.
    If necessary, also check whether the correct allocation structure is entered in the settlement profile. The allocation structure is defaulted in the settlement profile when you create sender master data or when you maintain the settlement rule.
    You can update allocation structure A1
    Kindly advice me how to fix this error
    Thanks
    Supriya

    Hi,
    Thanks for your reply,I have added that cost element in allocation structure.Now i am getting one more error related to this even i have maintained Receiver type FXT and settlement cost element for that.Kindly help me on this.
    Define a settlement cost element for receiver type FXA
    Message no. KD506
    Diagnosis
    In allocation structure A1 (controlling area AFCO), you did not define which cost element should be used when settling costs/revenues of the sender. Nor did you define receiver type FXA.
    Procedure
    Assign a different allocation structure to the settlement sender (-> Master data -> Settlement rule -> Goto -> Settlement parameters), or maintain allocation structure A1.
    Thanks
    Supriya

  • Issue in closing an Internal Order

    Hi SAP Gurus,
    I need assistance for closing a very old IO in SAP.
    The IO was setup with a certain profit center and cost center. The cost center is now closed.
    I tried to change the cost center to another active cost center.Now when i used t-co KO88 for settlement run = message " There is nothing to settle ".
    Using t-co KO02 for closing the IO and i get the error message  " Balance of ORD xxxxxxx is not zero ".
    So I setup the system status in SAP to TECO GMPS SETC. But i want to close this IO. What could be the issue behind this?
    Regards,
    Priyank

    Hi,
    First check whether the Line items are there or not - KOB1
    If yes, settle them first and set the status
    If no, you can directly set the status in KO02.
    KOB1 - Internal order - set maximum date and execute
    See the line items
    or
    KO02 - Menu bar -> Extras - Cost analysis
    You can ind the status
    Find the value which hasn't been settled in the below report
    S_ALR_87013015 - List: Actual Debit/Credit
    Thanks

  • Lync Implementation with different internal and external domain sync

    Hello Experts,
    Having Windows 2012r2 with Lync 2013 frontend and Edge 2012 server on Win2012. Internal domain name is test.local and Internet domain name is : tgroup.com. Internally all the clients are able to sync with frontend
    server using [email protected] or [email protected] Internal CA and External Digicert works fine. But only problem is with external clients who want to communicate through edge server. 
    Edge server has 3 LAN ip address (nat with public IP), 10.10.10.2, 10.10.10.3, 10.10.10.4 and another Internal network interface which has ip 10.10.20.3
    which uses that to communicate with front-end. 
    How to achieve this ?  We dont have reverse proxy configured and we have only two servers. 
    Regards, Ganesh, MCTS, MCP, ITILV2 This posting is provided with no warranties and confers no rights. Please remember to click Mark as Answer and Vote as Helpful on posts that help you. This can be beneficial to other community members reading the thread.

    The reverse proxy is used to publish URL's like the meet and dialin url, the address book url and the lync mobile client (smart phones and tablets) urls. This doesn't impact the external desktop user access as thats via the edge server. There is more to
    it than that but for the sake of keeping this simple lets stick to that for now.
    As far as SIP domains go. Think of your Lync users as having a SIP address similar to email addresses. You wouldn't have a user with an internal email address but with a different external email address. In fact best practice is to have the Lync SIP address
    match the email address.
    My reccomendation is to use the ttgoup.com as a sip domain and not the test.local
    Please remember, if you see a post that helped you please click "Vote As Helpful" and if it answered your question, please click "Mark As Answer"
    Lync Sorted blog

  • Is there any Web Service to create Internal Order?

    Hi,
    I have to find out a suitable Web Service which can create internal order. I have searched in SOAMANAGER but did not find any such WS. Does anybody have an idea whether there is any such WS?

    Hi Tirth,
    If you are using a bapi for webservice then these threads may help you.
    How to create WebService from BAPIs
    How To Expose BAPI As a Webservise
    If you are creating your own webservice then create an application in java,then expose it as webservice.
    Regards
    Sreedhar

  • Maketing Plan & Campaign link with ERP Internal Orders

    Hello,
    I have a requriemnt where we need to do maketing  Planning & budgeting . We will create marketing plans & Campaings in SAP CRM but will store planning data in SAP ERP Internal Order due to some reason.
    My question is: is there any way to link Marketing Plan & campaigns from SAP CRM to SAP ERP Internal Order. We can not use SAP ERP PS (WBS) intergation due to project limitation.
    Thanks in advance,
    Sufi

    unfortunately, the standard function doesn't support use internal order with campaign
    so if you need to realize it ,I think you can build a customize field in campaign to fill the internal order, and store the link in your customize table.
    If any expense happen on your campaign, you need to create your FI document through some BAPI to FI, and fill the internal order this the BAPI.  I believe you need to develop this functionality, as the standard design doesn't include this

  • To enable 'Service Object' for Internal Order (KO02, KO03)

    Hi All,
    Can anyone share me how to enable the 'Service Object' icon for the attachment functionality in Internal Order (KO02, KO03) sap.
    Thanks,
    Jamie

    Hi ,
    If you click on Settelemnt rule there you will find the Service object  .
    Doe this solve yyour problme

  • Unable to start services with different

    Hi,
    We have installed OBIEE 11g on a 64-bit Windows machine. When we start the services with the same user id which was logged in while installation the services go up successfully and everything seems fine. However, when we try to start the services with any other user id, the weblogic server fails to start.
    Please let me know if anyone has any idea why this could be happening. Any help will be appreciated.
    Thanks
    Naman

    Hi,
    I added the user to BIAdministrators but still it is unable to start the services. Also, the ID with which I installed OBIEE is also not added to the BIAdministrators group but is still able to start the services.
    Thanks
    Naman

Maybe you are looking for