Issues in Process chain after Transporting to Q

Hi All
I have couple of issues with my process chain (in Q). We have recently upgraded from BW3.5 to BI7.0. After upgrade i have a change made to one of my Process chain. i have transported it successfully to Q system. I have collected all the related objects associated with the change in the transport. But when try to see the changes changes in the process chain in Q system i have the following issues.
1. i do not see my changes in display mode. But i am able to see all the changes if i go to change mode (this looks weird and i dont know why)
2. i am unable to schdule the process chain in Q system as i was able to do earlier. Now it is asking for Transport when i try to schedule the process chain. this was not the case earlier.
3. In the transport i also collected a newly created infopackage and added it to the Process chain. But i do not see any link between the infopackage and the process chain (it was supposed to have a link as it had in DEV), i mean when i go to  infopackage it used to give me a mesage saying the infopackage is already available in Process chain which i got in DEV.
All the above cases were working per normal in DEV systems tested and were collected as required in the transports and moved to Q
Please let me know ASAP if any of you have encountered similar problems before and have solutions. i saw couple of related threads (some suggested to directly activate the process chain in Q system by opening the Q systems as an alternate) but could not find a solution
Any sort of help will be really appreciated
Thanks
HK

1. Display mode shows only the active version of Process chain. When you go into change mode, it displays the inactive version (if any available). Make sure you activate the process chain in the change mode. Then the chain you see in display and change mode will be in sync.
2. When you try to schedule, the Process chain will be activated as well. If your Q system is prompting for transport then probably the system is open for changes. If you want to modify process chains in Q and P systems, make appropriate Object Changeability settings in Transport connection in Q and P systems and make sure the system is closed for changes (SCC4).
3. Use Transport connection to collect the objects required for Process chain. After transport, check the transport log and make sure all the objects are imported successfully.
Regards,
Sree

Similar Messages

  • DTP failure which was in process chain after transport

    Hi,
    I created a DTP in Development Server and it get transported to QA successfully.
    I also created a Prcocess Chain that execute that DTP. When I tried to transport this Process Chain to QA, transport was sucess but when i check in QA process chain was not in active mode. its showing the error that DTP is not in active A version.
    Error:Process variant DTP_LOAD DTP_4AEIYC0UV528F7W1JL587E7HR does not exist in version A
    I checked the DTP in QA and I noticed that the DTP has been converted to a different technical name which is not the same as the one I transported from Development.
    Example: DTP DTP_LOAD DTP_4AEIYC0UV528F7W1JL587E7HR in Dev is converted to DTP_4AN4TVDRYNSMT95UGI48JVC6J in QA.
    Please advise how I can  transport the Process Chain that call this DTP from dev to QA

    Hi Sri,
       You need to collect your  DTP along with the Process chain in the same request. When you migrate DTPs from DEV to QA , a new DTP ID are generated in QA system and your DTP in the Process chain points to DEV's DTP and that is why you get this error. You can also find more information when you turn on the " Detail View On" from the menu. This will display technical name of all the objects in your process chain.
    so recollect your DTPs and the process chains objects in the same transport request and migrated to QA ,this will Fix you issue.
    Hope it helps,
    Cheers,
    Balaji

  • Issue in process chain with DTP after imported to production

    Hi,
    we have a issue with process chain.
    after transportation DTP technical name is differ in prod and dev. process chain is went inactive.
    i have read some related threads, i'm not find any suitable solution for this.
    we don't have access to change process chain(they are not willing to open prod system)
    could you please provide solution on this issue .
    Thanks,
    EDK....
    Edited by: EdK666 on Oct 21, 2011 2:54 PM

    Hi,
    I have observed the behavior of changing technical name for DTP but still I think your process chain should not become inactive due to this.  I think process chain somehow adjust the new technical name but anyways you should be able to change the DTP in process chain directly in production system.
    If that is not possible you can just try re-transporting it.
    Regards,
    Durgesh.

  • Transport process chain by transport connection step by step

    Hello expert:
              how to transport process chain by transport connection step by step?
    Many thanks,

    Go to RSA1 -> Transport Connection.
    Make sure Only Necessary objects is selected under Grouping.
    Expand Process Chain -> Click on Select Objects -> Search for the process chain you want to transport.
    Select it and click transfer.
    When finished collecting - Click on the Red Truck. Create a transport request when prompted to create a request.
    Then go to SE10 or SE09 -> Find your request and right click and select release on your transport request as well as the task under it.
    After it is released you can check the log by clicking on the log button and see if your transport moved successfully to target system.
    Good Luck.
    MP.

  • Process Chain after EVENT - More than once

    Hi all, I would like to run a process chain after an event; everything works fine with the following model...
    PC1 >>
         >> some processes
         >> EVENT TRIGGER
    PC2 >>
         (after EVENT) runs ok after event ONLY if I SCHEDULE it
    After succesfully run, I've tried to run again immediatly PC1 again and it runs ok, even triggers mentioned EVENT, but PC2 never runs again until I manually SCHEDULE it.
    The answer is: how should I SCHEDULE the process chain PC2 so I'll "never" need again to SCHEDULE it when I want it to run after event triggered on PC1?
    Hope you can help me.
    Thanks a lot!
    Bernardo

    Hello,
    Both process chains are separated. At the model I described, at the end of PC1 event is succesfully triggered. After event is triggered at PC1, PC2 triggers correctly due it is scheduled as "after event".
    Everything works fine, then, if I trigger PC1 again it runs correctly; event is triggered succesfully but PC2 (that is scheduled as "after event") doesn't runs; this is because I haven't SCHEDULED it again (after the first succesfully run).
    What I want is not schedule PC2 after a succesfully run. Is there any way to reach that purpose?
    Thanks again!
    Bernardo

  • Execute Process chain after infopackage run for a PC file

    Hello all.
    The scenario I need to solve is the following.
    I have several files to be load to ODS from P users PC. I will do this with an info package. But after this load there are some more process that have to be run whoch are created in a process chain.
    I would like to automate the execution of the precess chain right after the load from PC file is done.
    Any sugestions?
    Thanks and regards,

    Hello Javier Alvarado,
    If you use process chains, the automatically integrated processes are ignored and have to
    be implemented using the process chain. If you schedule a specific process in a chain,
    you support the automatic insertion of additional, relevant standard processes with the
    consideration of such automatic actions.
    For example, if you have selected the processing types Only PSA and Subsequently in
    Data Targets in the InfoPackage from the tabstrip Processing, and you are using this
    InfoPackage in a process chain, then the further processing into the data target does not
    automatically happen. Instead, it only happens if the process Update PSA is scheduled in
    the respective process chain after the loading process. Thus, the process chain
    maintenance supports the automation in this case. In this way, you generate a process
    variant for updating from the PSA in the chain when inserting the loading process with the
    process types Only PSA and Subsequently in Data Targets automatically into a chain.
    Well i am talking about 30B Version
    Regards,
    Mohan.

  • Transport Release Issue For Process Chain

    Hi Gurus,
    While trying to relase my request, which has Process Chain to be imported to testing environment i am getting a message like below:
    Check Objects before release and msg as
    key :R3TR TABU RSCOMPTLOGOT             ERSPC*(Application Component Of Process Chain)
    If i click release anyway the information i get is "You have to be an approver to bypass this check" and it is not released.
    I have checked the request and it is consistent and "ok".
    Not able to understand why i am not able to release this request.
    Please guide me on this.
    Thanks

    Hi Vijay,
    Can you check your process chain or any part of proce chain (diff process type) are not locked in two different transport request ?
    If so then delete the object from one request and add same object in another request and release.
    Regards,
    Kiran

  • DTp issue in process chain

    HI guys,
    I have an issue with DTP in process chain.
    Actually we have a process cahin in quality as well as in development and production,the structure of chain in production and development is same but the structure in quality is not matching.we are getting 1 additional DTP in the chain in quality system .when we run the chain it get fail at the additional DTP,and the process cahin get stopped.
    now iam not able to find out wher from this additional DTP came and how to find out wher exactly it is from and how to restart the chain.
    can anybody help me out?Its very urgent for me.
    Regards
    sk

    Hi,
    I have asked u to deschedule the process chain and then Check the Process chain using the Check View..
    I think that this is a dummy process which has got added when u have done the transport.
    Check if u can see the error DTP when u check.. then u can delete this DTP as this is a Dummy one.. and then link the processes if the link breaks bcz of this... and then check the PC again, and activate the same..
    Finally u can use PC after this..
    Thanks
    Assign points if this helps

  • Inactive chain after transport.

    Hello experts,
    I´ve transport a process chain into the quality system.
    The process chain chart does not appear on the right display screen and
    the chain is in grey in the menu so probably it is inactive.
    If I push the button Schedule I get next message:
    "Chain has no starter. Add a starter.
    Message no. RSPC020
    Diagnosis
    The process chain has no start-process. A process chain always requires
    exactly one general starter.
    System Response
    The system is unable to activate the process chain.
    Procedure
    Add a general starter to the chain, and schedule it as the first processin the chain."
    Furthermore if I push the modify button it let me see the chain flow
    chart but if I try to schedule it or activate it the system ask for a
    transport request.
    As the system says there is no starter, if i enter in maintain start
    process i can see the variant so the variant has been tranported correctly.
    How can we do to get the process chain be active in the quality system?
    Why the system does not recognise the initial variant in the quality system?

    I´ve found the next messagge warning in the transport request:
    "Start of the after-import method RS_RSPC_AFTER_IMPORT for object type(s) RSPC
    Version 'M' of chain ZBCS_DAT_AUX was saved without checking
    No destination maintained in target client 400 -> Not activated"
    The messagge detail:
    "Message no. RSPC085
    Diagnosis
    When activating a process chain, this is checked and scheduled. Both the checking of a process chain and its scheduling require that
    1. the function is executed in the target client of the import and
    2. the user executing the function has the appropriate authorizations.
    This is usually the case for the BI background user
    The function can be executed in the target client if an RFC logon occurs in the target client. An RFC destination must be predefined for this purpose. This destination is used for logon to the target client from client 000 during import postprocessing.
    This destination does not exist in this system.
    System Response
    The process chain will not be activated, which means that it will not be checked, scheduled, or saved in an active version. The process chain will only be adjusted to the local situation (for example, key changes with objects that are dependent on the source system), and will not be saved in a modified version.
    Procedure
    Create a destination for the import postprocessing."
    Do I have to contact with the data basis department to solve this issue?
    Regards.

  • Changes are not getting reflected in Process Chain after changes.

    Hello,
    I have modified a Process Chain in Development environment. I have created one new infopackage and included it in the process chain. I have also added two new change run variants in the process chain. I have collected the process chain and infopackage in a transport request and transported it to integration environment.
    Transport request has reached successfully in integration but the changes in process chain are not getting reflected. The infopackage has reached to integration after transport.
    I need some suggestion on this.
    Regards,
    Sanjay

    Hi Sanjay.......
    R u in Display mode..........click on Change mode...........
    If you can see the chain in Change mode............then ur process chain is imported in in-active version..........
    U can try activating it manually or re-transport the active version..........
    Regards,
    Debjani......

  • Invalid DataStore object name error when running process chain after EHP1

    Hello,
    We recently upgraded our BW Dev platform to NW7.01 EHP1 SP6. I noticed that the layout for "Delete PSA Request" process in the Process Chain has changed after the upgrade. We can no longer specify the actual PSA table to delete eg, /BIC/B0001645. Instead we need to specify the Datasource name and the Source System.
    Now after the upgrade when I run one of my process chains, it fails at "Delete PSA Request" step with error message "Invalid DataStore object name /BIC/B0001645: Reason: No  valid entry in table RSTS". This datasource is based on the flat file source system and the PSA table for this Datasource is /BIC/B0001653.
    Unfortunately the process chain is picking up an older PSA table for this datasource and there is no way for me to specify the current PSA table name after this change in layout with EHP1 upgrade. Any suggestions on how to resolve this issue.
    Many Thanks,
    Al

    Hi,
    Please implement OSS 1345331.
    If this does not help try the below steps:
    1.  Run the report 'RSAR_PSA_CLEANUP_DIRECTORY/_MS' in check mode for a 
           particular PSA table for finding the inconsistencies.
    2.   After that please analyze the logs and if there is any problems related to partition, you need to correct them using the report u2013
    3.  'SAP_PSA_PARTNO_CORRECT' in repair mode for the
          PSA tables.  Run the report again after this
    4.  'RSR_PSA_CLEANUP_DIRECTORY/_MS' in check mode to 
         double check that the invalid partitions are 
         corrected.
         Once this is done you can execute the report     
         'RSR_PSA_CLEANUP_DIRECTORY/_MS' in repair mode.
    -Vikram

  • Process chain - After error ABAP - trigger a metachain start does not work.

    Hi,
    I have a process chain, where after an ABAP runs into red (ERROR MESSAGE triggered), another process type, like start a new meta-chain, or start an infopackage starts.... But is does not work. After i go to logs, it asks me whether i want to trigger the following jobs, if i choose yes, it works. But i need to start it automatically, when the ABAP Routine has an error message (RED) in the chain.
    Any idea, because I tried to solve it all the day, but i did not manage to get itwork...
    Many Thanks,
    L.

    Hi,
    the problem is not the ABAP Program.
    I have the following situation:
    A Metachain contains as second step a call of local chain. After the local chain, according to the status of it (green o red), we have other different steps. So we have two different link (red and green) starting from the local process chain step.
    Inside the local process chain there is the ABAP program that check several parameters and if something is not as expected fails with status red. if this situation happens, the local process chain becomes red and in SM37 inside the job i see the error that i forced, but the status is not triggered to the first metachain , so the corresponding following steps are not triggered.
    This issue happens only if fails the ABAP program because, for example, a Infopackages loading fails every thing works and the corresponding steps in the metachain are executed.
    In the ABAP program in order to force the status red we have the following code:
    MESSAGE e162(00) WITH 'Status' 'Red'.
    Any idea?
    Thanks,
    Veronica

  • Small issue in Process Chain

    Hi Dudes,
    I have small problem in Process chain.
      1)Start
      2)Load  :
      3)activate : Always
    when i ran my PC ,due to some problem my Load Process type got fail.
      But after that i have actiavte Process type(PT) which should run whether Load PT is in success or fails .
    But it got stuck due to message "Status Change of Process LOADING ZPAK_EFAJ6WFZPJPA7MWVSZXETN4PE.
    Save Status and Trigger Events if Appropriate"
    with two option yes and no.
    when i click on yes then only it goes .
    But if i would run and nobody around then i would gets stuck at that point only .
    Is there any solution for that !!
    Hope i m clear toexplain u my problem
    every person will get the point
    Gain Points

    I do understand what u r saying.
    But I have given an example. Why that message box comes.
    Can’t we suppress automatically?
    Suppose had I been have a process type which send a mails after load status whether it fails or success at that point this could be an issue ??.
    So if it would be stuck like this then it could not send a mail.
    Hope u have understood my problem .
    or if u want in detail give me ur id i send u screen shot
    Gain Points

  • Issue with Process chains in BI (NW2004s)

    Hi,
    Recently we have done the system refresh (From Production to Quality Environment) for our BI Environment.
    After the refresh, our basis team has performed all the post activities like Source system conversion (BDLS), etc.
    But now, we are not able to open any process chains.The system is given the information message "<b>Variant &0000000XXXXXX does not exist</b>"
    "Message no. DB612
    Diagnosis
    You selected variant &0000000XXXXXX for program RSPROCESS.
    This variant does not exist.
    Procedure
    Correct the entry."
    Is this because of some post-processing steps got missed out?
    Do we have to create the Variants (Or can we copy the variants from the old Quality env? as we have the copy of Quality env. database).
    If we can create the variants, please let us know the procedure for the same.
    Please advise. Points will be awarded for your solution.
    Thanks,
    John.

    I have checked for the variants in the production system for the program RSPROCESS(in transaction SE38). But nothing exists.
    When I checked with the Basis team, they mentioned that the tables VARI, VARIT and VARID are copied from the (old)QA system and now they have imported these tables into the QA system after the refresh.
    I have never created any variants. Please let me know the procedure to create the variants in SE38.
    The process chains are working fine in our Dev and Prod environments. Will copying the tables(VARI, VARID and VARIT) from  production will help us?
    Is this due to some transports need to be moved from Dev to QA again? How can I find the requests?
    Please let me know your suggetion.
    -John.

  • Unable to find DTP from Process chain after SPS14

    Hi BI-experts,
    After applying SPS14 to our development and our test systems we are experiencing problems with our process chains. The latest problem is that after transporting one process chain (with dtp's) from dev to test the process chain states that the dtp does not exist in active version on test system. In the test system the process chain points to the wrong dtp technical name. The technical name it points to in test system is the techincal name of the DTP in development system. The dtp gets assigned a different name when transported to test, hence the reference to dtp is wrong in test.
    I have tried the following:
    - Reactivate the dtp on test- No success
    - Deleting the dtp from test and transporting it and PC again - No
    success
    - Reactivating the PC and DTP on dev and transporting it again - No
    sucess
    Please help.

    If anyone else experience this problem I can inform you that implementing note 1147587 solved it.

Maybe you are looking for