Hi one simple way u can do it
In SE01 first u release all the TO that u have created for that table
Now u goto changemode for the table in SE11
then click on save, it will ask another req number
u create new one and save
and transport this TO number to production.
that will work
reward points if helpful
regs
Manas Ranjan Panda

Similar Messages

  • Function module to find table entries associated with transport request

    Hi all,
       I have requirement, like we have created a table and maintenance view for that table - and made entries in that table.
       now we want to know all the entries made in the table are associated with transport request or not.
      how to do it programmatically?? is there any function module which gives the result for transport object associated with the table entries ?????
    Thanks
    Sathish

    Hi,
    Use the table <b>E071K</b>
    in se16 give :
    request number in TRKORR
    Table name in OBJNAME
    in the filed TABKEY u will get the <b>values of the key fields</b> in the table
    by comparing the key fields u can find out the enrties related to the request number
    Please let me know if i am not clear
    ---Patil
    Message was edited by:
            Santhosh Patil
    null

  • How to deactivate tax code with transport request

    Hi expert
    We would like to deactivate tax code with transport request instead of manual on production.
    Do you know how to?
    Thanks in advance.
    Great

    Hi,
    You need to do below:-
    (1) Deactivate the tax line in test system
    (2) Then create a transport request via Export feature in FTXP
    (3) Open your target system and then import the transport request via import feature in FTXP.
    Then the tax code will get deactivated line in target system also.
    Regards,
    SDNFICO

  • Issues while transporting requests to an upgraded system

    Hi all,
    There is a development system which is upgraded.
    prior to upgradation of this development system , we copied all the abap developments to a temporary system, where developments were done until development system is upgraded.
    As of now , we are manually copying the changes done in temporary system to the upgraded development system,
         i.e  for ex;  Manually copying the code of a program in temporary system to upgraded development system
    Instead of manual copying of the developements/changes from Temporary system to development system, can we move the requests directly from
    temporary system to development system.
    Please let me know ,what are the issues raised while moving requests ( of programs,tables,scripts,smartforms..... e.t.c ) from temporary system to development system
    Thanks in advance.

    There's a new 'check' that can be done when transporting CRs throughout your landscape. It is the unconditional mode "Ignore Invalid Component Version".
    This feature (check the component version) was included with SAP_BASIS 702, so the tp checks the component version of the system where the transport was released (this information is included in the transport) and the component version of the system where the transport is going to be imported.
    This component version check feature will check all the components version between source and target system. So before choosing the 'Ignore' option, please try to make sure that the software component version that the objects contained in the request belongs to, should be the same between the systems, to avoid any inconsistencies. It is recommended to transport request in systems which are on the same support level or use the same add-ons.
    The component check is a hint that you will import a transport which come from a system which is different from the target system. It only checks the installed add-ons and support packages. This means if you have in the source system installed a add-on which is not present in the target system of the transport you should aware that you import no objects which depends on the add-on which is not present in the target system, the same point belongs also to different support package
    releases. This option was implemented to reduce the risk of inconsistencies. If you import the transport please use transport option "ignore invalid component version".
    This import option means that transport requests can be imported even if  their component version does not match the current component version (including Support Package Level) of the system. This is the case if the component version of the system is either new (the Support Package Level
    is higher than that of the export system) or too old (you first have to have imported the Support Packages before you can import the request). You should only use this option if you are sure that the content of the transport request is independent from the component version.
    If it is required to avoid this check you could set transport parameter SP_TRANS_SYNC with value OFF and this check will be not performed from tp, but I would recommend to use import option "ignore invalid component version" before you would import the transport.
    transport parameter SP_TRANS_SYNC = OFF.
    Parameter SP_TRANS_SYNC is delivered ON by default.
    This option will avoid the check of the component version.
    Some notes regarding this feature:
    1581638 - SAP component checks no longer working in TMS
    1577714 - Transport requests in Check requirements phase
    1650265 - TMS workflow: 'Ignore Invalid Component Version' missing
    1742547   Information about component version check in TMS
    1756116   TMS Component Check: Fix for excluded component logic

  • Issue when transport request of Text Control

    Dear Gurus,
    I have some problem when modified Text controls.
    Requirement
    My customer want to copy item text from Quotation which is use access sequence 9000 to item text in Sale Order
    What I do.
    1. I go to SPRO -> Sale and Distubution -> Basic Function -> Text Control -> Define Access Sequences For Deermining Texts -> Sales Document -> Item -> Textproceture -> Text ID's in procedure of Sale order Item
    2. I input Access squence 9000 to sepecific Text ID and ticked "Refer/Duplicate"
    3. I save and I get the Transport Request
    4. I create sale order reference Quotation and the result is system copy text.
    5. Then, I transport request to Simulation Server.
    6. I create sale order reference Quotation but this time system does not copy text
    I want to know why problem is occurs. if you have reference document about this issue please tell me.

    Hi,
    Run the program 'RSTXTRAN' using transaction SE38 and attach the Text object to your TR.
    Last time I faced the same problem.
    Everything gets transported except Text object.
    Hope it will be useful to u.
    Revert if not resolved.
    Regards
    Amit
    Edited by: Amit Gupta on May 14, 2009 7:31 AM

  • Issue with Delta Request

    Hi Friends,
    I have an issue with loading.
    1. From source 2lis_13_VDITM, data loads to 2 targets.
    ZIC_SEG, 0SD_C03.and from 0sd_C03 it again loads to ZSD_C03W and ZSD_C03M through DTP.
    I have done a repair full load on 08.08.2011 to PSA and loaded this request manually to cube ZIC_seg.
    I forgoted to delete this request in PSA as i dont want to load this to other targets.
    Before i notice ,already delta requests got loaded and has pulled my repair full request also to other targets.
    As i have not done any selective deltions on other cubes there may be double entries.
    I am planning to do the below steps inorder to rectify the issue.
    1. Do a selective deletion of the delta request in all 3 targets which got loaded on 8th along with repair full.
    2. Delete the repair full request from PSA.
    So now delta request which got loaded after repair full request, is left in PSA.
    My question is if my PC runs today will this delta request in PSA also pulls again to cube through DTP?
    Kindly share any other ideas please urgent...
    Regards,
    Banu

    Hi Banu,
    If the data in the CUBE's is not compressed, then follow the below steps
    1)Delete the latest request in CUBE ZIC_SEG
    2)Delete the latest request from cubes  ZSD_C03W and ZSD_C03M and then from 0SD_C03.
    3)load the delta request manually using DTP from your cubes(in DTP you can load by giving request number). to cubes ZIC_SEG and 0SD_C03.
    3)now run the delta DTP to load the delta request from 0SD_C03 to ZSD_C03W and ZSD_C03M.
    Next when your PC runs it will load only that particular day delta request.
    It will work
    Regards,
    Venkatesh

  • Mandatory assignment of Project with Transport Request

    Hi All,
    I have to create project PRJ1 in Solman and configure it with DEV system client 400. So all the requests created in DEV 400 must be assigned to PRJ1 also the condition is users must be able to create request only in 400.
    There is also one client 410 in DEV where the consultant should do only testing (not customization) with sample data and all request shloud move from 400 to 410 by SCC1. And all the requests in 400 must get create only if assigned to project PRJ1.
    In this task, I created project in Solman and also maintained the DEV 400 in system landscape and IMG of DEV project in third tab of system landscape.
    But still my users are able to create request in 400 without project assignment. I also locked client 410 in SCC4, but some smart persons are opening client 410 and sometime creating request in it.
    Please suggest me how to make it mandatory in DEV 400 to make mandatory of project assignment while creating request, and how to block 410 to produce request apart from SCC4 control.
    Regards,
    Ramesh.

    Hi Ramesh,
    to make the project assignment mandatory, make the following customizing in DEV - 400:
    1. transaction SE03 --> Display/Change Request Attributes
    2.Modify SAP_CTS_PROJECT attribute uing client specific checkbox (very important otherwise you will be blocked... to prevent transport request creation in other clients use SCC4 settings)
    Kind regards,
    Stéphane.

  • Want to crate a bc set with transport request,which has deleted records

    Hi
    I need a help in BC sets regarding records deletion.
    I want to create a BC sets with the transport, which has one deleted records from the table
    I have 30 records in table. I have deleted one record and created transport for the same.
    When I try to create BC sets with the above transport. It is not showing records, which is in Transport request.
    Could you please help me on this How can we create BC sets with deleted records.
    Thanks and Regards,
    Venkat

    Hai,
    Please check the following link.....
    http://help.sap.com/saphelp_nw70/helpdata/en/a6/c3a768465411d395c600a0c930dcc1/frameset.htm
    Regards,
    Yoganand.V

  • Issue in transport requests

    i am facing problem in transport request in Production Server, changes are not reflecting whereas changes are perfectly reflecting in QA Server.
    Regards,
    Majid

    This is a very generic question, without information we just can guess...
    Whats been transported?, Did you check that the changes are been reflected in the objects transported?.... Any logs?...
    Not enough information, read the "Rules of Engagement"
    Regards
    Juan

  • Issue in Transport Request of ChaRM

    I have created a Transport Request made import'd to Q-Sys, Now i need to Make some changes I've set the status to IN-dev & made changes & saved ,also released the transport request, still no changes found, Plz suggest me a remedy?

    hello Savithru,
    the normal process to import in QSystem your change via charm is to run the action "test transport" when you are "in development" for normal change document (SDMJ). You need to release your task prior to this action.
    This action will create a copy of your intial transport and will release it to the import buffer of your Q system. (the initial transport is NOT released). You can see the transport number in your log in your change document.
    The actual import in Q needs to be scheduled manually or automatically
    Do you see your transport of copy in the import buffer of your Q-System ?
    I hope it helps
    br Xavier

  • To find program name with transport request number

    Hi friends,
    I have a senario
    i have a transport request number, by using that how can i find the program name ie : to which object that transport request number corresponds to.
    Example :
        AD1K970456
    i know this request number now how can i find out to which object it coresponds to .
    Can any one tell how should i approach for it.
    Regards
    Priyanka.

    Hi,
    If this transport request is created by you or u know the respective user then go to the tcode SE09 and enter the user name and click on display you will get the list.then go on expanding u will get the program name.
    Thanks,
    Jayshree

  • Percentage Overhead Rates are not capture with Transport request

    Hi,
    I have defined Percentage Overheads rate in KZZ2 and assigned the same  into Costing Sheet.But while saving the transport reqest in to QAS client,It is throwing the below error.Kindly help me in solving this issue.
    Individual entries cannot be put into the change request
    Individual entries cannot be put into the change request
    Message no. SV141
    Diagnosis
    For technical reasons, the entries cannot be fully specified in the change request. There are two possible reasons for this:
    1. The key of an entry is longer than 120 characters. All entries whose keys match up to character 119, are then copied into the change request, rather than an individual entry.
    2. The key of an entry contains fields of special data types, for example, packed numbers. The key can only be specified in the change request up to the first such field from the left.
    all entries whose keys match up to character 238 are copied into the change request, rather than a single entry.
    System response
    The selected entry is copied into the change request correctly, but other entries may be copied as well.
    Please advice me.
    Thanks
    Sunitha

    Hi Sunita,
    I am also facing the same problem while transporting the overhead rates in quality and production.
    Can you give the elaborative steps of how you resolved your issue.
    The steps mention as under i tried but it is not working
    1) Go to SA38 or SE38
    2) Run the program RKAZUTR1
    3) You need to specify the number of your request with the costing sheet changes
    Thanks in advance
    Sayed

  • Issue with Service Request email Notification

    Hi All,
    Whenever we change the status of SR an email should be triggered. But it is not happening. Is there any setups we have to look for. When ever an event is raised there is no notification sent.
    Please let me know your comments at the earliest as it is an priority issue.
    Thanks,
    Mahesh

    Hi Mohammed,
    Thanks for the reply. I will explain the issue in detail. The issue is with the iSupport.
    User creates an SR in iSupport. Now the status will be in Open. Again user updates the SR by adding some notes by which the status of the SR will be changed to Updated by Customer. At this point we are getting an error notification. This error is as follows
    Event Error Name: WFENG_EVENT_NOTFOUND
    Event Error Message: 3142: Process 'SERVEREQ/100794754-1997529-EVT' has no activities waiting to receive event 'oracle.apps.cs.sr.ServiceRequest.statuschanged'.
    Event Error Stack:
    Wf_Engine.Event(SERVEREQ, 100794754-1997529-EVT, CSEVTPROC, oracle.apps.cs.sr.ServiceRequest.statuschanged)
    Wf_Rule.Default_Rule(oracle.apps.cs.sr.ServiceRequest.statuschanged, CEEC6B02CCB86CD4E0340003BA4D7D08)
    But If we update the same SR from service request form in customer support everything is working fine. \
    Please let me know your feedback
    Thanks,
    Mahesh

  • Issue with Transporting Mapping

    Hi,
    There is a strange issue that we are facing while importing a mapping from one PI server to another.
    Source PI server : PI 7.1
    Target PI server : PI 7.1 EHP1
    For the first time the softwarecomponent was import successfully. However eventually there were certain changes in the mapping and the mapping was transported to the target system.
    While doing so we encountered an issue stating :-
    The source structure, target structure, or a function library has been changed or could not be
    found in the Enterprise Services Repository. The mapping definition contains elements or attributes
    that does not exist in the changed structure, or function that were changed in a function library.
    The relevant entries will be deleted
    calculate122222222222222 function not found
           Signature of field  'a'  has changed
           Signature of field  'b'  has changed
           Signature of field  'c'  has changed
    Howerever there is no such udf in the original software component. Also there is no Udf with name calculate.
    There is no common udf for all the 3 target fields as well.
    There is only an RFC lookup that is common among the 3 fields, but without any field 'calculate'
    Kindly advice in case anyone has encountered such an issue.
    Regards,
                Milan Thaker

    > calculate122222222222222 function not found
    This is a default name, when the function is not found. You don't find the real function name in the error message.
    If you use a standard function and this is no longer available after import -> OSS ticket.
    If it is a global UDF, import it before the mapping.

  • Issue in Transport Request

    Hi,
    I am trying to understand how does transport works. I have a issue while moving some SAP BW objects.
    Transport X - Containts - A process chain , Transformations, some newly created variants and routines. - Moved to Q.
    Now the problem is I dont need to move the Process chains to Production, that means I need to move only transformations, newly created variants and routines.
    How do I do that.
    If I create another transport Y- just containing the objects apart from process chain and take that TR to Q and then to P will it work. and stop the TR - X in quality. 

    Hi Abdul,
    Thanks, but I know the solution, what I am trying to understand here is the mechanism and any proof like SAP documentation to support it. Please see below post.
    Ok, got it, but what I am trying to get here is rather than a hypothesis, a theorem.
    Lets see it as a experiment- first creating an ideal conditions-
    1) No Human error as in nothing to forget,no wrong sequence or anything.
    2) As Mathew said , that seems logical as if I split the class and method it wont work, but what if I always capture the complete object. As in, in the new TR i capture the complete class and the methods again . then what?
    I am trying to get here the science behind the transports, everyone has diff experience with TR, I consulted some colleagues,  they say - yes if i move the Z TR it will work,
    But what exactly happens , when we release the TR. Does the co-files and the data files contains the complete object or just the version change.
    If the version change it definitely wont work, if it contains the complete object I don't see any reason of its not working.
    Am i clear in my question and concern."

Maybe you are looking for