Issuing Project Stock to Vendor

Hi,
  I have the following scenario-
  The organization's projects are being carried out by EPC/Turnkey contractors.But the management wants to keep a tab on the quantity of material issued to the vendor and then later consumed.But the Finance department does not want that to show as a valuated inventory in their accounts.
I think that the probable solution could be to have a non-valuated stock for my project.i would procure the materials with an account assignment category Q.In that case I can keep a track of the materials issued to the contractor without any values being shown against the stock in the inventory. Am i right?
But if the material is sent from one project to another under a different company code then in that case material values cant be taken into account for the different Comany codes.Please advise if its workable or not.
Thanks and Regards

Hi Abdul,
This is not an exact case of project sub contracting persay.
the scenario is that the organization is into construction business and it procures materials for the project but does not valuate it at the inventory level.
the materials are needed to be tracked at 2 levels-
1. giving the materials to the vendor for construction activity(for that we have made a separate storage location for the vendor and on receiving the material we transfer the material to that specific storage location).
2. tracking the materials actually used by the vendor(material is issued(GI) against the particular project element).
this is the reason we plan to procure materials with a Q account assignment using non-valuated stock option.
would request to let me know if the solution discussed above is right or not?
Secondly.the procured materials against a project may be transferred to another project which comes under a different company code.Here the point is that the stock being non-valuated would not result in value updations reflection in the companies' accounts.any input is appreciable
Thanks and Regards

Similar Messages

  • Movement type for issuing materials from project stock to vendor

    Hello  gurus,
    after making GRN, the stock is updated in Project stock. now from the project stock, i want to issue the materials to vendor. which MvT i have to use and where it displays the Vendor. i need to track the materilas provided to vendor.
    tnx in advance
    Purushotham

    Hi,
    Here you are talking about Subcontracting Scenario.
    If you need to transfere the project stock to vendor, then you will need to do 2 steps:
    1. Transfer the Project stock to own (unrestricted use) stock. (411 Q)
    2. Transfer the Own stock to vendor. (541)
    Regards
    Vishal

  • Project stock to Vendor

    Dear All,
    Is it possible to create a material with requisition as a project stock and issue the same material to the vendor for execution of works and reconcile the same when doing GR.
    If yes please let me know the process and also if possible the movement tyoes

    Hi
    MB1b is for transfer posting
    301          Transfer posting plant to plant (one-step)     301
    301     E     Transfer posting plant to plant (one-step)     301E
    301     O     Transfer posting plant to plant (one-step)     301O
    301     Q     Transfer posting plant to plant (one-step)     301Q
    301     V     Transfer posting plant to plant (one-step)     301V
    301     W     Transfer posting plant to plant (one-step)     301W
    302          Transfer posting plant to plant (one-step) - reversal     302
    302     E     Transfer posting plant to plant (one-step) - reversal     302E
    302     O     Transfer posting plant to plant (one-step) - reversal     302O
    302     Q     Transfer posting plant to plant (one-step) - reversal     302Q
    302     V     Transfer posting plant to plant (one-step) - reversal     302V
    302     W     Transfer posting plant to plant (one-step) - reversal     302W
    303          Transfer posting plant to plant - remove from storage     303
    304          Trfr posting plant to plant - remove fm storage - reversal     304
    305          Transfer posting plant to plant - place in storage     305
    306          Trfr posting plant to plant - place in storage - reversal     306
    309          Transfer posting material to material     309
    309     E     Transfer posting sales order - material to material     309E
    309     O     Transfer posting SC stock material to material     309O
    309     Q     Transfer posting project material to material     309Q
    309     V     Transfer posting cust. return. packaging mat. to mat.     309V
    309     W     Transfer posting cust. consgmt material to material     309W
    310          Transfer posting material to material - reversal     310
    310     E     Transfer order sales order material to material - reversal     310E
    310     O     Transfer posting SC stock material to material - reversal     310O
    310     Q     Transfer posting project material to material - reversal     310Q
    310     V     Transfer posting cust. consgmt mat. to mat. - reversal     310V
    310     W     Transfer posting cust. consgmt mat. to mat. - reversal     310W
    311          Transfer posting storage location (one-step)     311
    311     E     Transfer posting storage location (one-step) - sales order     311E
    311     K     Transfer posting storage location (one-step) - consignment     311K
    311     M     Transfer posting storage location (one-step) - RTP     311M
    311     Q     Transfer posting storage location (one-step) - project     311Q
    312          Transfer posting storage location (one-step) - reversal     312
    312     E     Transf. posting stor.loc.(one-step) - sales order - reversal     312E
    312     K     Transf. posting stor.loc.(one-step) - consignment - reversal     312K
    312     M     Transfer posting storage loc. (one-step) - RTP - reversal     312M
    312     Q     Transfer posting stor. loc. (one-step) - project - reversal     312Q
    313          Transfer posting SLoc to SLoc - remove from storage     313
    314          Trfr posting SLoc to SLoc - remove from storage - reversal     314
    315          Transfer posting SLoc. to SLoc. - place in storage     315
    316          Transfer posting SLoc to SLoc - place in storage - reversal     316
    317          Creation of a structured material     317
    318          Creation of a structured material - reversal     318
    319          Split structured material into components     319
    320          Split structured mat. into components - reversal     320
    321          Transfer posting quality inspection to unrestricted     321
    321     E     Transfer posting QI sales order to unrestricted sales order     321E
    321     K     Transfer posting QI consignment to unrestr. consignment     321K
    321     O     Transfer posting QI SC stock to unrestricted SC stock     321O
    321     Q     Transfer posting QI project to unrestr. project stock     321Q
    321     W     Transfer posting QI customer consignment to unrestr. stock     321W
    322          Trfr posting qual. inspection to unrestricted - reversal     322
    322     E     Transfer posting QI sales ord. to unr. sales ord. - reversal     322E
    322     K     Transfer posting QI consgmt to unrestr. consgmt - reversal     322K
    322     O     Transfer posting QI SC stock to unrestr. SC stock - revers.     322O
    322     Q     Transfer posting QI project to unrestr. project - reversal     322Q
    322     W     Transfer posting QI cust. consgmt to unrestr. stck - revers.     322W
    323          Transfer posting quality to quality within plant     323
    323     E     Trfr posting QI sales order to QI sales order within plant     323E
    323     K     Transfer posting QI consgmt to QI consgmt within plant     323K
    323     Q     Transfer posting QI project to QI project within plant     323Q
    324          Transfer posting quality to quality within plant - reversal     324
    324     E     Trfr pstng QI sales ord. to QI sales ord. in plnt - reversal     324E
    324     K     Trfr pstng QI consgmt to QI consgmt within plant - reversal     324K
    324     Q     Transfer posting QI project to QI project in plant - revers.     324Q
    325          Transfer posting blocked stock to blocked stock within plant     325
    325     E     Transfer posting blkd sales ord. to blkd sales ord. in plant     325E
    325     K     Transfer posting blkd consgmt to blkd consgmt within plant     325K
    325     Q     Transfer posting blocked project to blocked project in plant     325Q
    326          Trfr posting blkd stock to blkd stock in plant - reversal     326
    326     E     Trfr pstng blkd sales ord. to blkd sales ord. in plnt - rev.     326E
    326     K     Trfr pstng blkd consgmt to blkd consgmt in plant - reversal     326K
    326     Q     Transfer posting blkd project to blkd proj. in plant - rev.     326Q
    343          Transfer posting blocked stock to unrestricted-use stock     343
    343     E     Transfer posting blkd sales order to unrestr. sales order     343E
    343     K     Transfer posting blkd consigment to unrestr. consigment     343K
    343     Q     Transfer posting blkd project to unrestr. project stock     343Q
    344          Transfer posting blocked stock to unr.-use stock - reversal     344
    344     E     Trfr pstng blkd sales ord. to unrestr. sales ord. - reversal     344E
    344     K     Transfer posting blkd consgmt to unrestr. consgmt - reversal     344K
    344     Q     Transfer posting blocked project to unrestr. proj. - revers.     344Q
    349          Transfer posting blocked stock to quality inspection stock     349
    349     E     Transfer posting blocked sales order to QI sales order     349E
    349     K     Transfer posting blocked consignment to QI consignment     349K
    349     Q     Transfer psoting blocked project to QI project     349Q
    350          Transfer posting blocked stock to QI stock - reversal     350
    350     E     Transfer posting blkd sales ord. to QI sales ord. - reversal     350E
    350     K     Transfer posting blkd consgmt to QI consgmt - reversal     350K
    350     Q     Transfer posting blocked project to QI project - reversal     350Q
    351          Transfer posting to stock in transit from unrestricted-use     351
    352          Trfr pstng to stock in transit from unrestr.-use - reversal     352
    411          Transfer posting storage location (one-step)     411
    411     E     Transfer posting sales order to own     411E
    411     K     Transfer posting consignment to own     411K
    411     Q     Transfer posting project to own     411Q
    412          Transfer posting storage location (one-step) - reversal     412
    412     E     Transfer posting sales order to own - reversal     412E
    412     K     Transfer posting consignment to own - reversal     412K
    412     Q     Transfer posting project to own - reversal     412Q
    413          Transfer posting sales order in one step     413
    413     E     Transfer posting sales order to sales order     413E
    413     K     Transfer posting consignment to sales order     413K
    413     Q     Transfer posting project to sales order     413Q
    414          Transfer posting sales order in one step - reversal     414
    414     E     Transfer posting sales order to sales order - reversal     414E
    414     K     Transfer posting consignment to sales order - reversal     414K
    414     Q     Transfer posting project to sales order - reversal     414Q
    415          Transfer posting project in one step     415
    415     E     Transfer posting sales order to project     415E
    415     K     Transfer posting consignment to project     415K
    415     Q     Transfer posting project to project     415Q
    416          Transfer posting project in one step - reversal     416
    416     E     Transfer posting sales order to project - reversal     416E
    416     K     Transfer posting consignment to project - reversal     416K
    416     Q     Transfer posting project to project - reversal     416Q
    441          Transfer posting unrestricted-use to tied empties     441
    442          Transfer posting tied empties to unrestricted-use     442
    453          Transfer posting to own stock from returns from customer     453
    454          Trfr pstng to own stck from returns from customer - reversal     454
    455          Stock transfer returns to returns     455
    456          Stock transfer returns to returns - reversal     456
    457          Stock transfer returns to QI     457
    458          Stock transfer returns to QI - reversal     458
    459          Stock transfer returns to blocked     459
    460          Stock transfer returns to blocked - reversal     460
    541          Trfr pstng to stock with subcontractor from unrestr.-use st.     541
    542          Trfr pstg to stock w. subcontr. from unrestr.-use - reversal     542
    Mb1c for goods receipt
    305          Transfer posting plant to plant - place in storage     305
    306          Trfr posting plant to plant - place in storage - reversal     306
    315          Transfer posting SLoc. to SLoc. - place in storage     315
    316          Transfer posting SLoc to SLoc - place in storage - reversal     316
    451          Returns from customer     451
    452          Returns from customer - reversal     452
    501          Receipt w/o purchase order into warehouse     501
    501     E     Receipt w/o purchase order into unrestr. sales order stock     501E
    501     K     Receipt w/o purchase order into consignment     501K
    501     M     Receipt w/o purchase order into unrestricted RTP     501M
    501     Q     Receipt w/o purchase order into unrestricted project     501Q
    502          Receipt w/o purchase order into warehouse - reversal     502
    502     E     Receipt w/o purch. order into unrestr. sales ord. - reversal     502E
    502     K     Receipt w/o purchase order into consignment - reversal     502K
    502     M     Receipt w/o purchase order into unrestricted RTP - reversal     502M
    502     Q     Receipt w/o purchase order into unrestr. project - reversal     502Q
    503          Receipt w/o purchase order into quality inspection stock     503
    503     E     Receipt w/o purchase order into QI sales order stock     503E
    503     K     Receipt w/o purchase order into QI consignment     503K
    503     Q     Receipt w/o purchase order into QI project     503Q
    504          Receipt w/o purchase order into QI stock - reversal     504
    504     E     Receipt w/o purchase order into QI sales order - reversal     504E
    504     K     Receipt w/o purchase order into QI consignment - reversal     504K
    504     Q     Receipt w/o purchase order into QI project - reversal     504Q
    505          Receipt w/o purchase order into blocked stock     505
    505     E     Receipt w/o purchase order into blocked sales order stock     505E
    505     K     Receipt w/o purchase order into blocked consignment     505K
    505     Q     Receipt w/o purchase order into blocked project stock     505Q
    506          Receipt w/o purchase order into blocked stock - reversal     506
    506     E     Receipt w/o purchase order into blkd sales order - reversal     506E
    506     K     Receipt w/o purchase order into blocked consgmt - reversal     506K
    506     Q     Receipt w/o purchase order into blocked project st. - rev.     506Q
    511          Receipt of delivery without charge     511
    511     M     Receipt of delivery w/o charge RTP (ret. transp. packaging)     511M
    512          Receipt of delivery without charge - reversal     512
    512     M     Receipt of delivery w/o charge RTP - reversal     512M
    521          Receipt w/o production order into unrestr.-use stock     521
    521     E     Receipt w/o production order into unrestricted sales order     521E
    521     Q     Receipt w/o production order into unrestr. project stock     521Q
    522          Receipt w/o prod. order into unrestr.-use st. - reversal     522
    522     E     Receipt w/o prod. order into unrestr. sales order - reversal     522E
    522     Q     Receipt w/o production order into unrestr. project - revers.     522Q
    523          Receipt w/o production order into quality inspection stock     523
    523     E     Receipt w/o production order into QI sales order stock     523E
    523     Q     Receipt w/o production order into QI project stock     523Q
    524          Receipt w/o prod. order into qual. inspec. stock - reversal     524
    524     E     Receipt w/o prod. order into QI sales order stock - reversal     524E
    524     Q     Receipt w/o production order into QI project st. - reversal     524Q
    525          Receipt w/o production order into blocked stock     525
    525     E     Receipt w/o production order into blocked sales order stock     525E
    525     Q     Receipt w/o production order into blocked project stock     525Q
    526          Receipt w/o production order into blocked stock - reversal     526
    526     E     Receipt w/o prod. order into blkd sales order st. - reversal     526E
    526     Q     Reveipt w/o production order into blocked project st. - rev.     526Q
    531          Receipt of by-product into unrestricted-use stock     531
    531     E     Receipt of by-product into unrestr. sales order stock     531E
    531     Q     Receipt of by-product into unrestricted project stock     531Q
    532          Receipt of by-product into unrestricted-use stock - reversal     532
    532     E     Receipt of by-product into unrestr. sales order - reversal     532E
    532     Q     Receipt of by-product into unrestr. project stck - reversal     532Q
    561          Receipt per initial entry of stock balances into unr.-use     561
    561     E     Receipt per init. entry of stck balances to unr. sales ord.     561E
    561     K     Rcpt per init. entry of stock balances to unrestric. consgmt     561K
    561     M     Receipt per initial entry of stock balances to unrestr. RTP     561M
    561     O     Rcpt per init. entry of stck balances to unr. stck w. subc.     561O
    561     Q     Receipt per initial entry of stock balances to unrestr.proj.     561Q
    561     V     Rcpt per init. entry of st. bal. to unr. ret. pack. at cust.     561V
    561     W     Rcpt per init. entry of st. bal. to unr. consgmt at customer     561W
    562          Receipt per init. entry of st. bal. to unrestr. - reversal     562
    562     E     Rcpt per init. entry of st. bal. to unr. sales ord. - rev.     562E
    562     K     Receipt per init. entry of st. bal. to unr. consgmt - rev.     562K
    562     M     Receipt per init. entry of st. bal. to unr. consgmt - rev.     562M
    562     O     Rcpt per init. entry of st. bal. to unr. st. w. subc. -rev.     562O
    562     Q     Receipt per init. entry of st. bal. to unrestr. proj. - rev.     562Q
    562     V     Rcpt per init. entry of st.bal.to unr.re.pck.at cust. - rev.     562V
    562     W     Rcpt per init. entry of st. bal. to unr.cons.at cust. - rev.     562W
    563          Receipt per init. entry of stock balances into qual. inspec.     563
    563     E     Receipt per init. entry of stock balances to QI sales order     563E
    563     K     Receipt per init. entry of stock balances to QI consignment     563K
    563     O     Receipt per init. entry of st. bal. to QI st. w. subcontrac.     563O
    563     Q     Receipt per initial entry of stock balances to QI project     563Q
    563     V     Receipt per init. entry of st. bal. to QI ret. pck. at cust.     563V
    563     W     Receipt per init. entry of st. bal. to QI consgmt at custom.     563W
    564          Receipt per init. entry of stock balances to QI - reversal     564
    564     E     Receipt per init. entry of st. bal. to QI sales order - rev.     564E
    564     K     Receipt per init. entry of st. bal. to QI consgmt - reversal     564K
    564     O     Rcpt per init. entry of st. bal. to QI st. w. subc. - rev.     564O
    564     Q     Receipt per initial entry of stock bal. to QI project - rev.     564Q
    564     V     Rcpt per init.entry of st.bal. to QI re.pck. at cust. - rev.     564V
    564     W     Rcpt per init.entry of st. bal. to QI cons.at cust. - rev.     564W
    565          Receipt per init. entry of st. balances into blocked stock     565
    565     E     Receipt per init. entry of st. balances to blkd sales order     565E
    565     K     Receipt per init. entry of st. bal. to blocked consignment     565K
    565     Q     Receipt per initial entry of stock bal. to blocked project     565Q
    566          Receipt per init. entry of stock balances to blocked - rev.     566
    566     E     Receipt per init. entry of st. bal. to blkd sales or. - rev.     566E
    566     K     Receipt per init. entry of st. bal. to blkd consgmt - rev.     566K
    566     Q     Receipt per initial entry of stock bal. to blkd proj. - rev.     566Q
    581          Receipt by-product from network     581
    581     E     Receipt by-product to unrestricted sales order from network     581E
    581     Q     Receipt by-product to unrestricted project from network     581Q
    582          Receipt by-product from network - reversal     582
    582     E     Receipt by-product to unrestr. sales order from netw. - rev.     582E
    582     Q     Receipt by-product to unrestr. project from network - rev.     582Q

  • Project stock issue?

    dear ps experts,
    kindly let me know what is the right process in dealing with Project stock items issue for customer project.
    1. Is it thru MIGO-Goods Issues to Project against Reservation number
    2. Delivery thru Sales order - Delivery thru VL01N - PGI from project stock
    We are successful thru sales order - delivery thru vl01n - pgi and unable to settle the Reservation number in Project, which is still showing as "Reserved" through MMBE against the same material after delivery thru
    Pl help in clarifying us the right process.
    Regards
    Srihari

    Hi
    I meet the same problem before. and i can share the experience.
    generally speaking, we use CNS0 to deliver the finished or semi-finished products from the project.
    then we use VL01N to create the delivery note.
    if you only use VL01N, the project will generate reservation again (planned order or PR ) when MRP runs. one way to avoid this is to tick "final issue" in the Proc Para. tab of the material (in the project builder) as soon as you create the deliver note using VL01N. then the no extra reservation will be generated.
    if you use CNS0 to deliver, the final issue will be ticked automatically.
    it will help you to understand.
    Judy

  • Required reference document to issue the material from project stock

    Hi All,
    we have procure the project stock material with Acct. assignment Grp as "Q", now the material is laying in project stock.
    the things is we can issue the warehouse material with reference to Project Reservation similarly my client wanted to use some SAP document for records purpose to issue the material from project stock.
    i have checked this functionality in SAP which is not available except straight way issuing the material from project stock using MB1A( 221 Q).
    please help me out to resolve this requirent.
    manoj singh
    we can

    Hi,
    Did you implement PS module in your system?  How were your project stocks reserved?
    Cheers,
    HT

  • Inter company STO issuing from Project Stock

    Hello Experts,
    In my Scenario, I have two plants A & B which are in two different company codes
    Plant A raises an STO to receive materials from Plant B.
    Plant A will receive the materials into unrestricted use stock, but Plant B should issue from valuated project stock (via outbound delivery).
    This is necessary to keep accurate cost tracking.  If Plant B moved the project stock to unrestricted stock first, then the moving average price could be affected before transferring to plant A.
    Can anyone tell me if this is possible?  I don't see stock type Q available for movement 643.
    Does anyone have any other options to for intercompany transfer of project stock?
    Regards,
    Thomas

    I opened a message with OSS and below is the response.  Basically it cannot be done with the standard system.  There is a note on how to modify your system, but it is only for a certain releases and would be considered a core mod.
    "Dear customer,
    Thank you very much for contacting SAP Global Support Center.
    unfortunately the functionality you expect does not exist within the
    standard SAP design.
    note 92231 deal with a modification suggestion how to create such
    movement types in some releases. As this is a modification note
    originally proposed for special customers, there is no general
    modification for all releases. As the tables has changed
    in 46B, the modifications to create 643Q proposed by SAP via the
    corresponding notes are not made for your release. We do as well not
    plan to provide a new modification note at the moment.
    The creation of the movement type is therefore possible but is
    considered a modification to the system design."
    I am sorry that I could not provide you with a more positive answer
    this time but nevertheless can provide an accurate information. For
    more information, please refer to note 11 and 83020.
    Please notice that the reason for your request does not indicate any
    possible errors in the SAP Software. Nevertheless we have at our
    discretion decided to process your request within the framework of our
    support. Please note that you are not entitled to free consultation in
    similar future cases. In this case check the "The SAP Eco-System
    in a nutshell" that explains how to find help to overcome this issue.
    The document can be found at:
    http://service.sap.com/~sapdownload/011000358700006245642006E/
    Note 1054121.
    I am sorry but this is the standard system design. Please confirm your
    message at your earliest convenience.
    In the end, my client has decided to transfer the project stock to unrestricted stock before doing the STO.  Please be aware that this could affect moving average price before doing the transfer.

  • Return to vendor from Blocked Project stock - Line rejection

    hi
    I have a problem in doing line rejection for return delivery from a blocked project stock.
    we had modified F5 notification for Project related senario to FQ and using the same for doing line rejection return delivery directly from project stock with the help of action box.
    While the include is accessing MSPR table for picking up the project stock.
    the steps involved are as below.
    1. create FQ notification (Similar to F5) by giving inputs as Material to be rejected,Plant, Defect code from existing code group and assign the purchase order.
    2. Tranfer the project stock to blocked projection stock ie.rejection stores using 344 movement type. while doing this 344 we give input of WBS element, storage location and Batch.Stocks against this WBS are picked from MSPR table and trasnferd to rejection stores.
    3.After this while doing return to vendor we give the reason code and post 122 document.
    the problem is if the material is having two WBS elements it and both have stock in rejection stores this follow up action is unable to pick the Exact stock for which the WBS element is assigned to notification while 344 movement.
    please suggest me as how the WBS element can be retrived from a notification which was used for earlier actions in action BOX.
    regards
    NVB

    Hi
    If u want to return the material to the vendor. In MIGO itself select return delivery against the material document with movement type 122 u can send it.
    This is irrespective of material lying in quality or blocked. From quality or from blocked status u can send the material back to vendor.
    No need for quality to Un restricted or Blocked to Un restricted.
    Regards,
    Raman

  • How to issue parts from our Unrestricted stock to Vendor QI stock (Subcont)

    Hi ,
    In subcontrating process , I wanted to transfer material from my unrestricted stock to Vendor QI stock where subcontrator will test the quality of the material and only if it gets approved it will be used for process otherwise will be returned back to us.
    For this I wanted to transfer my stock in QI stock of Subcontrator, how can I do that ?
    Similary is there any way to Transfer material back from Subcontrator Blocked stock to my unrestricted / Blocked Stock.
    Thx in Advance
    Regards
    Sandeep Marwha

    Blocked stock at a subcontractor is not possible. The table containing the stock at a vendor is MSLB, and this table just does not have a field for blocked stock.
    if you use batch management, then you can have restricted stock.
    Edited by: Jürgen L. on May 6, 2008 4:04 PM

  • Issues on Copying the Project without Project Stock Checked

    Hi,
    When I copy the operative project (with project stock unchecked and components assigned to the activity in this project) to create a new project, I checked the project stock in the master data of the new project. Although the new component assigned after the creation of the new porject is project stock, the component copied from the operative project is still not project stock.
    Is there any walkaround or solution to make the copied component to become a project stock?
    Thanks,
    Ting

    What was the item category of materials of the old project which you used to copy?

  • Project Stock Consumption

    Dear Experts,
    I am working on a scenario- details given below
    1. Purchase requisition from Network as Preq + WBS for raw material with stock type L
    2. PR Converted to PO and then GR is done ( Raw Material)
    3. PR raised through Network as N-                PR converted to PO and issued to contractor with a subcontractor material
    4. Material received through GR is transfered to subcontractor
    5. Material issued to contractor is consumed through a GR ( PO for service material and not raw material).
    What i have found out is Cost is not hitting project when GR is done to Raw material PR but it comes in project only when there is a Consumption from subcontracting GR.
    Please let me know what should happen as best practise at this stage
    Is it-       Cost should flow to Project when 101 Q happens
                                                    or
                 Cost should flow to Project only when 543 O is done
    Currently movement types are in this manner
    101 Q then 411 Q and 411 Gnst and then 541 to contractor and later consumed through 543.
    Please give you valuable comments.

    Hi
    Check in MRP-4 view for "individual/coll" field. It will be 2. that is collective requirement. If it is done then only you can issue material subcontractor when you use project system.Then only it uses 543- O to consume from vendor stock. If you don't keep "individual/coll" field as blank then soncumption will happen via 543Q.That is project stock. So you will not be able to do 541 to send material to vendor.
    Coming to Point. 
    Look at your step 2. PR to PO and GR.. It will go to normal plant stock because of 2 maintained in "individual/coll" field.Movement type 101 will be used. Not 101 Q. So cost will not flow to WBS at that point of time.
    But it comes in project only when there is a Consumption from subcontracting GR because header material MRP-4 view will not have "individual/coll" field 2.
    It is standard process in project system module subcontract
    Regards
    Antony

  • Subcontracting with project stock

    Hi All,
    When using project stock as we cannot issue components to the subcontractor in the subcontracting process we have created a new storage location for the subcontractor. So when the components will be sent to the subcontractor we will move the components from one storage location to the subcontractor's storage location using movement 311 Q.
    But how do I get the delivery document that should be sent with these components. Is there a SAP standard way of triggering the delivery documents in this case?
    Regards,
    V S

    Hi,
    In case of subcontracting PO with account assignment for Project, components are directly withdrawn from the project stock at the time of the goods receipt. But if you want to withdraw the components from the stock of material provided to vendor then you can set the collective requirement field in Material Master MRP4 view as Collective requirements only (2), then you can use ME2O.
    The collective requirement field has to be set for the components to be provided.
    If you work with this setting then you don't need any seperatestorage location the process will behve as normal subcontracting process.
    Regards
    Chandra Shekhar
    Edited by: Chandra Shekhar Singh on Jul 14, 2011 6:48 PM

  • Problem with project stock valuation class

    Dear All,
    We have an issue regarding the Revenue Inventory and Capital Inventory. There is a certain balance amount which should be in capital but system is showing in Revenue and vice versa.
    The reason for this is that when the material was created, in some materials the main valuation class was 3032(Project) and in some it was maintained as 3030(revenue). But project stock valuation class was not maintained.
    Now the problem persists in the G/L balances, the G/L of project stock (132006)displays some amount of revenue(132000) and vice versa.
    We tried to maintain the project stock valuation class (3032) for materials for which the main valuation class is 3030 (Revenue),but still the G/L for revenue (132000) is getting hit.
    At the end, the requirement is that G/L for revenue (132000) should hit when revenue procurement is there and G/L for capital (132006) should hit when capital procurement is there.
    Kindly suggest the way forward.
    Regards,
    Harsh

    Thanks Venkat, we have thought of the same as a last stop but there are hundreds of materials which has this problem and there would be many open documents for them.
    If anything could be suggested other then this, and I wanted clarification on one more point that the materials for which main valuation class was 3030 and later we added 3032 in project stk Val class but after maintaining it. When we procure(Capital procurement), it is still showing the balance in G/L 132000(Revenue).
    Regards,
    Harsh

  • Issue in Stock transfer

    Hi
    We have an issue in Stock Transfer. the Stock transfer happens between a manufacturing plant which is excise registered and a depot, which is not excise registered. We raise a Stock Transfer order from the depot on manufacturing plant with a freight component. The system creates a freight provision in the depot, when the goods issue is done by the manufacturing plant against the stock Transfer Order. After the goods issue the material is shown in Transit in report MB5T until the same is recieved by the depot. However, some goods are lost in transit and the same is recovered from the freight vendor. In such a case, we do a MIGO for the actual quantity recieved at depot and pass a debit note to vendor by loading the difference to material.
    The issue is:
    1. the quantity and the value of the physical inventory recieved have been rectified by a recovery from the vendor.
    2. However, how can we remove the goods, which we have short recieved from the report MB5T
    The certain work around  we have thought could be :
    1.  Receive the quantity in full at the recieveing Depot and then scrap the material to the extent it has been received short through M Type 551. However, the issue arises in case of transfer of goods from one manufacturing plant to another, where in both are excise registered. In such a case, goods receipt in full would not be correct as it would raise issues in excise registers.
    Please suggest
    Regards
    Sanil K Bhandari

    Hi,
    One suggestion is you can pass a document through MB1A for material loss in transit for the mateial lost.
    Followign accounting Entry would be hit :
    Transporter shrinkage Clearing Dr
    to Inventory Raw Mateial          Cr
    You can pass the same document through Mvt. Type 951 (GI Lost in Transit).
    Thanks & Regards,
    Taral Patel

  • Vendor Consignment stock or vendor managed stock

    Dear All,
    My client wants to manage vendor consignment stock.
    Vendor will be given a area and vendor will keep the stock in his area. Based on the plan he will supply the stock.
    the GR for rawmaterials will be made on the consumption report given by the production person. This activity will happen next day only. i will do the GR only to the quantity consumed.
    for example if i consumed 100 qty, i will do GR only for 100 and vendor will issue invoice for 100. But when the vendor issue the stock, he will raise a excise invoice based on which i have to take excise credit. I want to know how to do the same.
    secondly, i take credit for 100 qty, but actual consumption is 95 only, how do i reverse the 5 only excise invoice.
    regards
    ranga

    No, it is possible to sell from vendor consignment stock directly and I have done it in ECC 6.0 (not IS-retail).
    - Pls refer the note 607604.
    - Establish the 'stock determination rule' in MM -> Inventory Management -> Stock Determination.
    - You need to assign it to the material (MRP3 view) or assign it to item-ategory.
    - DONOT mark the special stock indicator in item-category used in SD (e.g. TAN) with 'K'..I did this mistake and wasted some time. If you do, it will ask you to populate the Vendor field in the Delivery which is not available and you may get stuck up because of that.
    This should make it work.
    Pls award points if you find this information useful.
    Regards,
    Shripad

  • Storage location wise project stock valuation

    Hi all,
       I am tying to generate a report for storage locationwise project stock valuation. MBBS is giving the data valuation type as well as WBS element wise valuation.That is fine. I want to show the data storage location wise. So, I have taken MSPR table where I am getting data storage location wise. For this stock, i am picking up unit price from QBEW table. My user says there will be cases that the material comes in with different prices in a same financial period.Here I am facing issue when there are two prices for the same material with same Val.area and same WBS element .Pls tell me how can I pick up the correct price.

    Hi,
    If stock with different price under 1 plant and 1 WBS Element put into different storage location based on the material price then in table MSPR we can have LGORT (storage location) as indicator there. Otherwise, since valuation type is not implemented, there is no other way you can differentiate stock based on price as you mentioned before.

Maybe you are looking for

  • IPod & Power Surges?

    Hey all, Curious problem with my iPod (5.5G w/Video) recently I have been conecting it to my computer and have been getting this error message: " A USB device has malfunctioned and exceeded the power limits of its hub port." The iPod is not recognise

  • Restarted Standard manager

    Hi all, User requests are not been processed, So i restarted Standard manager. After restarting it, standard manager is missing form Concurrent: Manager: Administer window. I checked with Concurrent: Manager: Define window. I am able to view definati

  • Premiere Elements 9 - Help files don't activate

    In Adobe Premiere Elements 9.0, when I click on the "Help" tab, I get a very short system busy icon, then nothing.  None of the Help functions activate.  Similarly, when I click on the various "Click here" messages that show up on the bottom bar on t

  • What has happened to the latest episode of house of cards

    Why isn't episode 25 available today?

  • DVD format problem

    I had a movie shot in ntsc format that I edited in FCP and wanted to burn to a DVD to send to a friend in the US. I am in the UK. When I inserted a DVD-R blank disk into iDVD and started preparing the project, it warned that I was about to burn an nt