Item 050 Order 600491 budget exceeded

Budget maintained for particular asset 1,000,000.00  and assigned 833,903.21
I have created PR with that PR i am creating capitalPO, at the time of saving its showing an error
Item 050 Order 600491 budget exceeded
Message no. BP604
In document item 050 Order 600491, budget  for fiscal year 2011 was exceeded by 240.00 INR

the value of the P.O may be more than that of the PR . the value of the P.O is checked again with the budget maintained in KO22
it may be possible to change this message to warning in availability control , internal orders

Similar Messages

  • Item 001 Order 6111456 budget exceeded

    Dear Friends,
    When the user is trying to post Miro, He is getting the following error,
    Item 001 Order 6111456  budget exceeded
    Message no. BP603
    Diagnosis
    Budget was exceeded by 6,688.33 INR in document item 001 Order 6111456 .
    All the purchase orders are in the year 2009.
    Q1. What is the T.code to know, how much budget is avilable for that particuar internal order?
    Q2. What is the T.code to know, How much amount has been used in that internal order?
    I want to send the user the reply in the following manner.
    Total budget for internal order = xxx, buget used = xxx, exceeded =  6,688.33 .
    Please suggest.
    Regards
    Sridhar

    Dear Friends,
    As per ur suggestions, I have executed T.code KO23, year-2009, The systems displays the data like this.
    Budget, Current budget, Assigned, Planned totals,
    Q1. Which should be taken for calculation?
    For Report report S_ALR_87013019 -2009, The data is displayed as
    Actual, Commitment, assigned ,avilable.
    Q1. Which should be taken for calculation?
    When the user is posting the miro, Should i take the internal order values only and should i consider the taxes also to arrive at the final conclusion?
    Please suggest to reslove the issue?
    Regards
    Sridhar

  • Item 010 Order EST5CRQP128A budget exceeded

    Dear all,
    I am trying to short closed the PO. However, I encountered the following message :
    ===========================================================================
    Item 010 Order EST5CRQP128A budget exceeded
    Message no. BP604
    Diagnosis
    In document item 010 Order EST5CRQP128A, budget  for fiscal year 2008 was exceeded by 1.20 USD.
    ===========================================================================
    Please advise.
    Thank you in advance.

    Hi
    Check it in SPRO- SAP IMG- Controlling - Internal orders - Budget and availability control - Define tolerance limit for availability control
    In thic check for the controlling area and usage %.
    Regards,
    Raman.

  • Item 001 Order 99999999 budget exceeded SRM 5.0 Classic Extended

    There are two issue that seem to be going on with budget being exceeded.
    One is that when looking at the Budget Overview the Credit Limit Used seem to be twice that of what is noted in our backend system. 
    The second one is the Assigned value is not the same as that in the backend system. 
    In both cases the sysem of record ECC is correct. Is there a way to refresh the information from the ECC side or how do I find out why the Credit Limit Used is way over the assigned limit.
    The ECC (backeend) allows a 10% overage to occur. How do I get SRM to allow for the 10% over so that we do not exceed the limits and cause an error.

    Is this thread still valid? If not, please close the thread.
    If so, as no response has been submitted, please rephrase your question and/or provide further information to describe your requirement.
    Thanks
    Jason
    SDN SRM Moderator Team

  • Error: Order 300401 Budget Exceeded while doing PO w.r.t PR

    Hi Experts,
    We are getting error, Order 300401 budget exceeded  while doing service PO
    In budget shows exceeded in making the P.O of approx amount Rs 411,500. While in the below PO Value, it is clear that the indent still has the amount of RS 1,760,737.
    Indent No. 1000031924 Total Value = 3,230,000
    Sr No.     P.O     Value     
    1     3900006041                       456,774     
    2     3900006146    Line item 1       101,467     
                            Line item 2      266,414     
    3     3900006184                       326,158     
    4     3900006188                       318,450     
         Total P.O's Value               1,469,263     
    Total value of Indent                  3,230,000
    Total P.O value in the Indent     1,469,263
    Balance Amount in the Indent     1,760,737
    Regards,
    Manjunath

    Hi,
    Budget is exceeded w.r.t to maintained Internal Order in PR /PO ,Use below options.
    1 ) Re-construct Budget-KO31 or
    2 )Either de-activate budget-KO32 or
    3) Maintain budget for IO-KO22 .
    This will resolve your issue.
    Thanks & Regards,
    Sandesh Sawant

  • Item 10 WBS element Budget exceeded

    Hello All,
    I am facing an issue while creating a PO with the newly created WBS element. I have followed the below steps in creation and release of the WBS Elements:
    1. The user has created a WBS element for the Financial year 2015, but the user allocated the budget in FY 2014.
    2. We have made the release value to '0' for the year 2014 and maintained the budget for 2015
    3. Released the budget via Tcode:IMCBR3
    But, I am still facing an issue while creating a PO that WBS element budget exceeded.  Please let me know if there is any other process to follow for this scenario. Kindly help.
    Thanks,
    Mercy

    hi,
    Increase budget for the WBS in CJ30 and then release in CJ32
    Regards,
    Rakesh

  • Err: Budget Exceeded(when int.order changed in asset) while creating invoic

    Hi All,
    Hope you are all doing wonderfull !
    We have created a statistical order type and wanted to assign them to assets as we don't wanna settle thoze expenses,but needed only for statistical purpose.
    It was okay, when we have changed them in asset master. However, we could not change them in already existing PO's, so when we are trying to create Invoices for the PO's having old internal order number, it is shooting us an error " item xxx order xxxxxx budget exceeded?
    Please let me know how to proceed further to clear this problem.
    Thanks
    Sri

    Hi Sri,
    Can you please elaborate a bit on your scenario. Have you assigned an internal order in asset master record.
    The internal order in asset master record has different purpose. It is used when you want to post depreciation of that asset to internal order.
    Regards
    Chetan.

  • Internal Order Budget Exceeded when creating a PO

    Dear all,
    When we create a PO against an Internal Order, the system displays the message "Item 001 - order X budget exceeded". But checking that order we can see budget available.
    Do you guys have idea the reason of it?
    Many thanks,
    Amanda

    Hi Sreenivas,
    As we are planning to send budget exceed message to responsible person in the internal order, however, from the configuration, it is find that the warning message of budget exceed will send to the budget manager only, and the definition of budget manager is by internal order type and not by individual internal order.
    Please advise how can I send the warning message to the person responsible for the internal order instead of send to the budget manager for the internal order type.
    Thanks,
    Nina

  • Order budget exceeded when creating a PO

    Dear all,
    When we create a PO against an Internal Order, the system displays the message "Item 001 - order X budget exceeded". But checking that order we can see budget available.
    Do you guys have idea the reason of it?
    Many thanks,
    Amanda

    hI,
    You have to check tolerance limit for Order buget.
    Go to SPRO - Controlling - Internal Order -Budgeting & avalibily contrl & ammend the Tolerance limit.
    I hope it will work
    Regards,
    Manish
    Don’t forget to give point if useful ans.

  • Err: Budget exceeded (while creatin invoice) as int.ord got changed in asse

    Hi All,
    Hope you are all doing wonderfull !
    We have created a statistical order type and wanted to assign them to assets as we don't wanna settle thoze expenses,but needed only for statistical purpose.
    It was okay, when we have changed them in asset master. However, we could not change them in already existing PO's, so when we are trying to create Invoices for the PO's having old internal order number, it is shooting us an error " item xxx order xxxxxx budget exceeded?
    Please let me know how to proceed further to clear this problem.
    Thanks
    Sri

    My question is,
    If we have changed an internal order in asset master, how do you make it reflect in already existing PO's(which were using that asset).
    Thanks and awaiting the reply.

  • Budget exceeded problem in PR

    Hello Friends
    I created the project and allocated the budget in 2009,
    I created  PR in Feb 2010, but the problem is while i am changing the quantities in ME52N.
    I am getting the error message :item XXX WBS element budget exceeded
    Even i carry forwarded the budget from 2009(CJC0) to 2010.still the same problem exists.
    Regards
    Kiran

    Hi,
    Check the delivery date in the PR. If the delivery date is for next year
    2011 system displays the error message.
    If problem still persists then reply the thread with error message number.
    Regards,

  • Budget exceeded

    Hi:
       I  am  posting  in FI with wbs,the system gives me the following  error  message:
    Item 001 WBS element ******** budget exceeded
    Message no. BP604
    Diagnosis
    In document item 001 WBS element ***, budget for WBS element *******for fiscal year 2008 was exceeded by 320.00 CNY.
    but  there is stilll enought available budget in wbs(48,200.00 CNY), i confirm in report S_ALR_87013558   the budget is 48200 cny,the actual cost and commitment is zero ; the system should not issue error message, I am so  confused!
    Regards in advance.
    thanks.
    Edited by: junzhi wang on Aug 26, 2008 8:11 AM

    Availability control against overall value
    Indicator which controls whether availability checks are conducted against the overall value or against annual ones.
    Use
    In the project budget profile, the "Overall" indicator, used in conjunction with the "Releases" indicator, has the following effect:
    Ind. 'Overall' Ind. 'Releases' Avail. control against ...
    X - Overall budget
    - - Annual budget
    X X Overall budget released
    - X Annual budget released
    X = Indicator is set, in other words, checkbox was checked.
    if  Ind. 'Overall' Ind. 'Releases'  are both not ticked,it's  Annual budget ;we have done the Annual budget and  Overall budget  already.and some WBS with the same budget profile  have no problem when posting.

  • Budget exceeded in CJ32

    HI
    getting Below Error
    Item WBS Element XXXXXX Budget exceeded
    Message BP604
    When  User wants to release the Budget in CJ32 he get the above error
    they do Bottom up budget, Period Wise they have assigned the Budget
    At first level after total up budget is 90laks, they have released only 16lak, this month they are trying to do release balance amount of 74lak
    thy could not able to do, system say budget exceeded
    in cj32 when its checked assigned value was 2 cr's which is more the release budget
    WBS 4 level XXXXXXX  Budget 1687000  Assigned  1005276
    WBS 4 level XXXXXXX  Budget 1900000  Assigned 18466080
    WBS 4 level XXXXXXX  Budget 4600000  Assigned     264621
    WBS 4 level XXXXXXX  Budget  NA         Assigned   1725420
    First thing how system allowed to do commitment/actual booking more then the released Budget when Availability control was active
    Kindly advice what are all the changes need to be done
    Thanks

    hi,
    Please check SAP note http://service.sap.com/sap/support/notes/1606591.
    Hope it helps!
    Thank you and Regards,
    Varshal Kachole

  • Budget Exceed Issue in work Order (P.O) in Production Server.

    Hi Friends,
    I am getting different type of budget exceed issue, that to only in Production server.
    Here the issue is when I am creating the work order P.O (Acc.As. Cat.P, Itm Cat. D) with different service line items with respective WBSe with in the budget limit, then I am doing SES for some quantity, now when I am changing (I am decreasing not increasing) the same P.O line item available quantity and creating the new version now system is calculating the old version line item quantity + new version quantity (nothing but double) then giving budget exceed error.
    One more strange thing is, if I change quantity for one line item then system is giving budget exceed error for another line item which is having the different WBSe which was saved with out giving any error at the time of P.O creation.
    This issue is happening only in Production server ....same scenario I have run with the same values in both Dev. and Qau. (Where the config. is same in all 3 clients) but in both the clients it is working fine...but in production why the system is behaving in such a way I am not getting. 
    In the below I have given the test scenario...
    Service P.O Creation
    Line Item
    P.O Quanity
    Value
    WBS
    Budget
    Commitment
    SES. Quatity
    Actual cost
    1
    10
    100
    WBS 1
    2000
    1000
    5
    500
    2
    20
    200
    Wbs 2
    4000
    2000
    10.00
    1000
    3
    30
    300
    WBS 3
    6000
    3000
    15
    1500
    4
    40
    400
    Wbs 4
    8000
    4000
    20.00
    2000
    Service P.O change with new version
    Line Item
    P.O Quanity
    Value
    WBS
    Budget
    Commitment
    SES. Quatity
    Actual cost
    1
    6
    100
    WBS 1
    1000
    1000
    5
    500
    2
    20
    200
    Wbs 2
    2000
    2000
    10.00
    1000
    Budget exceed with the double value
    3
    30
    300
    WBS 3
    3000
    3000
    15
    1500
    4
    40
    400
    Wbs 4
    4000
    4000
    20.00
    2000
    If any one has come across with this type of issue and solved ...please suggest me ..
    Regards,
    Srikanth

    Hi,
    I have face similar issue in deleting PO line items.
    Even though I delete items, system check budget for deleted qty with the currency conversion + value & gives budget exceed error.
    In some cases we have asked user to deactivated AVAC asked to do the transaction, which is not recommended.
    You can try running CJBN & CJBV in sequence for affected WBS.
    Thanks & reg,
    Sam

  • Budget Exceed Error during creating of Purchase order in reference to PR

    Hi,
    I am getting the subject error (Budget Exceed Error) every time when I want to create a purchase order related to purchase requisition of my project.
    Issue is that after release the project when the purchase requisition has created for non stock item under activity I found in transaction CJ31 the assign value has already updated.
    Let say my budget is 400 US$, and the purchase requisition has created for 380 US$. Now when I check with CJ31I found the assigned value is 380. Now If I create a purchase order it throws an error that budget exceed.
    The tolerance limits are following:
    SA     ZSA01     Budget Profile Overall AVAC     ++     1     90,00
    SA     ZSA01     Budget Profile Overall AVAC     ++     3     100,00
    SA     ZSA01     Budget Profile Overall AVAC     01     1     90,00
    SA     ZSA01     Budget Profile Overall AVAC     01     3     100,00
    Please advice what will be the proposed solution for the above issue.
    Thanks in advance.
    With Regards,

    Your budget is 400$ and PR value is 380$ but you have not mentiond what is the tax value ?
    when u r creating PO at that time system will check the budget against PO value considering taxes also.
    eg. 380$+tax value.
    after considering taxes your total PO value imay be getting updated more that 400$.
    Explre you error by clicking on error information you get the exact diffrence in budget and PO value.
    Hope this will sove your problem, reply after doing this.

Maybe you are looking for

  • No data fields are available in the OLAP cube

    i was able to access data in Excel yesterday, but now all the cubes that i have created cannot be accessed by Excel any more and after authenticating and selecting the cell for the pivot table i get this error: No data fields are available in the OLA

  • Access MySQL Database on Server with PHP Services

    Hi there There are lots of tutorials on how to connect to a MySQL database on your local machine but I'd like to access a database on my server. When creating a new Flex Project the wizard asks me to define a Web root and a Root URL. I used '/home/ec

  • Incorrect PO pdf document attached.

    I am working on the workflow issue This is on 11.5.10. The issue here is in the notification which is send to the requester has incorrect PO pdf document attached. For ex : PO 100 ,has the pdf attachment of 130.(attached are the PDF files for both PO

  • Adding new system in transport route

    Hi, I want to add new system in transport domain. Please advice me . I have done through SE06--PERFORM POST INSTALLATION ACTIVITYS but in STMS iam getting message as TMS configuration is not for this system. Regards, Asif Edited by: Asif Ahamed on No

  • Firewall gives ShowModelessDialog error. How to solve?

    I made a wesite with iWeb '08 (www.thehouse.be). A visitor (from a bank) contacted me as he was unable to get authorisation in his company to put my site on the white-list. Apparently the site was blocked by the firewall "for security reasons". Yhe s