IW41: automatic update of activity type when changing the work center?

Hello colleagues,
when doing a time confirmation with IW41, we have following problem:
In the PM order the operations are assigned to a neutral executing work center, as it not known which individual technician is completing the operation later on.
Now when the individual technician is entering the time confirmation with IW41, system is proposing the work center indicated in the operation from the PM order, then technician is overwriting the work center proposal with his own individual work center ID (and pressing Enter), but the activity type is not getting updated automatically. So the technician must jump to field "activity type" and choose the correct activity type.
Is there any solution (hopefully with user exits!) to have the field "activity type" automatically updated with the one indicated in the work center, which was entered manually?
Thanks for your ideas!
Regards,
Patrick

Hi Maheswaran,
yes, as usual all PM work centers have only 1 activity type assigned in the costing tab.
We also checked the settings of the activity type (KL03), but we just found one difference: the price indicator was set on 3 "Determined manually" - we've changed to 1 "Plan price, automatically based on activity" (..same setting as for the act. type of the work center with working update of act.type).
We tested already all possible constellations and scenarios, but we have not found any good reason for the behaviour.
Thanks for your efforts so far!
Patrick

Similar Messages

  • All default routing value has to be changed, while changed the work center in production order

    Dear friends,
    our client they want to change the work center in production order.according to production version work center also they are changed.so while change the WC,all the default value has be changed as per routing what we maintained in routing.At present we have to enter the manually change the W.C as well as set up time and operation time enter manually.Any other option to do the automatically capture value from routing while change in Work center in production order.pl help me on this.
    Thanks&Regards
    Sabhapathy R

    Hi Rahul,
    Thanks for reply. I am maintained in diff value  maintained routing , Ex :First routing i have  work center 'X' value maintained as a setup time in 15 Min's and operation time 10 Min's
    second work center 'Y' I have maintained as set up time 10 Min's and operation time 30 Min's,
    Now I want to change the work center in production order as a 'Y' so whatever value maintained in routing , it has to be changed automatically (10 min's and 30 Min's), but system will not change only old value only picked (15Min's AND 10 Min's).
    Now I think you get to know what the client requirement, kindly do the need full.
    Regards,
    Sabhapathy R

  • Update weight and volume when changing the quantity

    Hello ALL,
    For some configurable items, those whose weight and volume depends on configuration, when changing the quantity at set level, weights and volumes are not calculated again and order item is saved with wrong data about weights and volume.
    when ever changing the quantity we will get a message - " Changing date/quantity may result in different BOM Please configure"
    if we do explicitly by clicking "Item Details Configuration' then Weight and Volume will get update automatically.
    my requirement is Weight and volume should get update automatically when changing the quantity with clicking on "Item Details Configuration'.
    could you provide any OSS notes available for this or any help to achieve this functionality.

    Dear Prathap Naidu P,
    Did you solve this issue?
    Because I have the same problem, and I was looking for hints.
    Thank you so much for any help.
    Best regards,
    J.Flanders

  • Automatical update of PO quantity when changed in SO

    We have a following issue
    for our regular business we have a third party process for trading
    goods. So we are using on customer sales order stock. In our system
    following is possible: We create a sales order and after using of
    Purchase requisition we create a purchase order. So now when we change
    the quantity in SO and save the SO, this change is automatically done
    in the PO as well.
    So this really works without canceling the PO first,
    changing the SO and creating a PO again.
    So now we have implemented a new product in a different sales area with the same process and
    with same material type HAWA but this automatical update of quantity is
    not working.
    What needs to be done to enable this function for our new
    product as well?

    My colleague was here when the system was implemented. He is not aware of any development here that enables this function. I have been looking for user exits and none are active for this. I have been told that this works only for customer sales order stock but I was not given any reason why.
    It seems logical, that in some development a new sales area needs to be included as Bijay said. Anyway we still think this function works without additional development.
    @Raghavendra we are using the SAP standard scenario. SO - PR - PO. PO is manually created out of PR in both cases.

  • Automatic change of Work Center during Confirmation.

    Happy New Year to all!
    Just want to ask if anyone of you encountered the scenario during confirmation in which the backflushed work center was changed. The user claims that they did not do any changes during confirmation nor did they change manually the order itself. The confirmation happened last December and they only noticed it this month when they were checking the reports.
    I did not configure their system so that they can change the Work Center during confirmation. By default, the work center is grayed out during confirmation.
    Hope to hear from some of you soon!
    Thanks and regards,
    jLmendoza
    Edited by: John Luis Mendoza on Jan 4, 2011 3:15 AM

    Dear
    If your production order operations are re-scheuled and dispatched after Capacity Avalaiblity check in cm21/cm22/cm31 etc  , then during the dispatch of operation ,  you have option to change Work Cnetre , time , date based on the selection option in Startgy profile (CM31/CM21-Enter the WORK CENTRE /Order )  and check wether work centre is changed.
    One more option may be in Order Change in CO02-Operation Overview -Operation -Work centre -Here user may change the Work Centre .
    If you have Order Change management active then you can trace the same .
    Refer : Production order change history
    Otherwise , there is not such confirguration in SPRO where work centre can be changed automatrically during confirmaiton because it will grade out based on the ste of confirmaiton default screen in OP00.
    Hope it clarifies
    Regards
    JH

  • Change in Work center

    Hi SAP Friends,
    I want to do some tick marks in capacity field of work center in one work center as well similar tick mark at other work center also.
    Please Tell how to do in one time?
    Plaese Reply.
    Chandra.

    Hi,
    First in T. Code : OP36, you need to define the Default Capacity.
    Enter your plant and Capacity catgort for e.g : "001".
    Define the default values carefully.
    Then Secondly, in T. Code : OP42, you need to define the Default Work center.
    With thses two settings every time you will get the work center with filled in fields and you can modify at any point in time.
    But, to change the Work center Capcity details, I guess there is no Mass Maintenance Transaction..
    Regards,
    Siva

  • Activity Type Changes in Work Center

    Hi Experts,
    We now want to change the activity type in a work center, and hope all the routings that have the work center being changed automatically. Currently, the existing routings can not be changed automatically. Is there a way to have all the routings changed as well? 
    Best Regards,
    Helen

    Hi,
    In Costing tab next to the activity you should find a check box for Reference Indicator. If this is ticked, then the changes done in work center will be automatically read into routings.
    If it is not, then you will have to manually change in routings. For individual, you can use CA02, for mass work with CEWB, working area as SAP_OPERATION
    Regards,
    Vivek

  • I got a new apple iD so when i try to update my apps it wont change the last one that i had so i cant update my apps. How do i fix this?

    I got a new apple iD so when i try to update my apps it wont change the last one that i had so i cant update my apps. How do i fix this?

    - Go to Settings>Store and sign out and sign into your account.
    - Apps are locked to the account that purchased them.
    - To update apps you have to sign into the account that purchased the apps. If you have apps that need updating purchased from more than one account you have to update them one at a time until the remaining apps were purchased from one account.

  • No redetermination of organizational data when change the activity partner

    In the Business Activity we have the determination Rule for Org.Data Model "14000161 - Org. Data Re. Master Data".
    When we create a Business activity and enter the activity partner, the organizational data is determinated correctly.
    The problem is that, when the activity partner is changed, the organizational data not is redetermined.
    Anybody Knows how to do it?
    Thanks.
    Best regards,
    Dani Sevilla.

    Hi Daniel,
    Did you try "propose alternative"?
    you can read at http://help.sap.com/saphelp_crm40sr1/helpdata/en/82/adc9531f1bc5419d0785617d6a59c2/frameset.htm
    also the BAdI mentioned can help you.
    Eyal.

  • How does system automatically picks up document type when you enter INV?

    1.How does system automatically picks up document type when you enter Invoice?
    2.What is Algorithms? Where is it used?
    3.What is the use of Customer Ledger Inquiry?

    The document type is hard coded by the system. Look at UDC table 00/DT for the document types in your system. Notice that some of those are marked as hard coded/reserved by JDE. You may wish to dowload the Accounts Receivable manual and read that to learn more about the document types.
    Not sure what you mean by algorithm, unless you are looking for how the system determines what document type to assign on invoice entry.
    These comments apply to accounts receivable and to JDE World, since you posted in the JDE World forum and are talking about the customer ledger inquiry. If you are in Enterprise One and asking about Accounts Payable, then this reply can be ignored (though Enterprise One works pretty similar to World in this respect).
    What is the use of the Customer Ledger Inquiry. To view accounts receivable detail history for a given customer, viewing on line. Whomever works in the accounts receivable department will likely use the Customer Ledger Inquiry quite a bit.
    Hope this helps a bit.
    John Dickey

  • Iphone 4s world must active phone when change simcard

    iphone 4s world must active phone when change simcard

    I have this same problem, and I also have the issue that contacts are recognized only in SMS and not in receiving calls (I store my contacts in intl format - i.e. +94 xxxxxxxxx). If I store it as 0xxxxxxx then number recognition works when calling but not SMS. Of course it is an option to store both numbers, but that,s a silly workaround on a device that cost 649$ when my 40$ dumb phone can manage effortlessly.
    I think the problems are connected, and that it is to do with recognizing the local country code in Sri Lanka. I used the phone in India (Vodafone in Chennai) and the number recognition was not an issue - I.e. local numbers saved in intl format were recognized in calls and SMS. (didn't try to use siri for dialing so can't comment on that)

  • Update Routing data after change in Work Center

    Hello All,
    I have just modified the Costing Data for 100 Work Centers CR02, setting a new "Activity Type" and "Activity Unit".  But the Routing Data CA02 does not get updated correspondingly.  I would like to ask is there any standard program which can help me to do the mass processing as to update the data to the corresponding routing?
    Thanks.

    1) You can change as per Mr Anupam sharma Said
    or
    2) YOU can also Update the data IN CA85N
    In selection criteria enter the respective work center and Plant
    and In new Value Give
    Same work center, Plant,  activity value , Unit  and activity type
    execute
    select the all the work center  and then click mass change
    Edited by: Sundaresan . E. V on Nov 12, 2010 10:25 AM

  • SPL block when changing the Address manually at Sales order level

    Hello all,  I hope every one doing well
    I am facing one problem in SAP system, when I am chanigng the Partner address at sales order level , system giving the SPL block , without screening even though the customer is a good customer.
    I checked in Img: GTS -> SAP Compliance Management->"Sanctioned Party List Screening" Service->Control Settings for "Sanctioned Party List Screening" Service->Sanctioned Party List Screening Strategy for Customs Docs tested with  as " Status check of unchanged Addresses( Partner Address) and New check of changed Addresses.
    I didn't find any difference. Sales order getting block for the above cases when changing the Address at Sales/Create document level.
    Please let me know  how to resolve it.
    Is it related to configuration  if yes how  ? pr
    do we  have any OSS Notes to Rescreen the Sales orders with compliace even though changing the Address at sales order level ( ship to party address changes like Name, city, email id, of fax )?
    or
    do we need to do the Enhancement for Rescreening when changing the ship to party adress (changes like Name, city, email id, of fax )
    manually at sales order level ?
    Thanks in Advance
    NVR

    hello Sameer,
    1. Whether your Embargo service is activated for the Country of Plant from which your order is getting shipped. -- Yes I have activated the Country under Embargo list.
    2. Whether the partner function for which you changing the county detail has been added in into the Partner group which is assigned to Embargo services.( GTS)-- Assinged the Sold to Party ( AG) for PGEMB2- Partner group
    3. Whether the country which u putting as Embargo has been maintianed under Embargo country list,
    - yes
    What I am doing exactly is , I am creating sales order with US customer master , but I am chaning the Country Key as Embargo country ( Ex: CU, SY, IR) at VA01 , or VA02 level Sales order header Partner tab level for Sold to party address ( changing only country key as embargo country) , not to ship to party  ( ship to party still US country key only), at that time system not blocking the sales order as embargo.
    please let me know if any once come across this sistuation..
    Thanks in advance
    NVR

  • How to Create New Activity Type  for Assiged to work centre Costing in Acti

    Dear Sir,
    We have four activity type to assigned in workcentre Costing Activity. Details are as under
    AIRJET     2010     AIRJET
    DONIER     2010     DORNIER
    SULTEX     2010     SULTEX
    SULZER     2010     SULZER
    in addition one more loom is comming in our unit and require new activity type.
    How can i create new.
    Please guide.
    Thanks in advance
    Regards
    Ajit

    Dear ,
    To create new Activity Type  , you need to follow the below steps :
    KA01 - Create Primary Cost Element for the new activities type.
    KL01 - Create Activity Type tied to the primary cost element. 
    KP26 - Change Activity Type/Activity Price Planning - maintain the Variable price
    Assign the activity type to cost center using T code KP26.
    In the input screen of T code KP26 ,enter version as 0, from period 1 and to period as 12 and the Fiscal Year as 20xx.
    Click on Overview tab on top and key in costing details in this screen.
    After performing this ,while creating the work center ,this combination of activity type & cost center should be assigned.
    At work centre level , you should have
    1.Create Standrad Value Key -OP19 and Formula Key in OP49.
    2.Create Formula Parameters in OP7B or u can use existing one to assing in the Standard Value Key
    3.In CR02-Assing the Standard value key in Basic Data  and select the Formula Key in Costing tab with cost centre assingement .Save
    Try and check
    Regards
    JH

  • IMac freezes when changing the screen saver

    Hi all:
    I originally posted this in the "Using Mac OS X" forum (iMac freezes when changing the screen saver, but thought I'd post here as well since the issue arises on a freshly installed OS.
    We've got three 350MHz slot-loading G3 iMacs (with 512MB RAM) which we're planning to use for basic word processing. The install of Panther (10.3.5 from black retail cds with 10-seat volume license) went fine on the first two. Ran the updates to 10.3.9, installed MS Office 2004, everything working great (they're a little slow, but after all, they are only 350 MHz).
    On the third, the first problem we noticed was the computer would lock up whenever we changed the screen saver from the default (Flurry; Computer Name also works). It continues to do so even after: repair permissions; repair disk; Disk Warrior; reset pram; reset nvram; reset pmu; change RAM; change hard drive; erase hard drive; write zeros to hard drive; reinstall with different set of retail CDs; trash preferences, and delete cache files. (If there's anything I've left out, it's in the other thread).
    Now we've noticed that we can't create any new user accounts. We've thought about putting this one in production, just warning the user that they can't change the screen saver, but god only knows what will turn up next.
    I'm starting to think it's a logic board issue, but could it be that selective? And would you see the same problem with another hard drive and different install discs? Am I missing something?
    BTW, there's a crash log with the other thread.
    Andrew
    Dual 2.0 GHz G5   Mac OS X (10.3.9)  

    I'm going to mark this one as answered.
    I removed the hard drive from the iMac, and put it into another 350 MHz iMac, and everything works great. I can select any screen saver without having it freeze, create new accounts, whatever my little heart desires.
    In checking the history of the problem iMac, there was an assortment of problems with booting (both from the hard drive and from the CD-ROM drive) which were never satisfactorily resolved. The problems just seemed to go away after sitting unplugged for a few days, as much as for anything we actually did to it.
    Now we just have to decide whether it's worth fixing, or using it somewhere in a non-critical role with OS 9 installed.
    Cheers,
    Andrew

Maybe you are looking for

  • How to view RUN_REPORT_OBJECT buil-in package source code

    Ps help. I'm creating a batch report that will execute from PL/SQL not forms - so I can't use this built-in directly on my PL/SQL procedure. How do I view RUN_REPORT_OBJECT source code and that of the functions that it calls. Thanks Khombi

  • OIM 11g: Add process tasks as a result of a Request?

    Is it possible in OIM 11g to have the result of a Request be that 1 or more process tasks are added to an an account's process? The out-of-the-box Request framework seems to be very attribute driven (Modify Provisioned Resource, Self Modify Provision

  • Support for JDeveloper 10.1.3 on Windows Server 2008 64 bit OS

    Hello, We are using JDeveloper 10.1.3.3.0 (patch # 9879989) for R12. Would like to know support for Jdeveloper on windows server 2008 - 64 bit. Thanks, Swati.

  • Issue in Passport Country 2 and Passport Country3  in ESS Portal

    Hi, In SAP Portal  Personal Data -Passport  Country 1 All datas are getting saved in Overview Screen But in Passport Country 2 and Passport Country 3 datas are not getting  saved  in Overview Screen  and  not getting the data from the backend also. I

  • Creating a query for task list operations

    hello all I checked the forum for similar questions but could not find any. I am trying to create a task list for the following: 1) specific plant 2) generic task list 3) specific group counter 4) specific operations type (filtered by control keys) i