J1IH - Material Non-Prod

Hi All,
In J1IH  material used in non Production.
In the Intial screen It ask for Material Doc. ,Which Material should I give here ??
Against which Mvt type ??
Biswajit

Hi,
Materials used for Production are with Movement Type 261 and for 201 i.e. Cost Center, 231 - Sales Order, 331 - For Quality Samples, etc... are for Non-Production.
Then follow the below process for the JV;
Making Adjustment Postings for Materials Not Used in Production
Use: - You follow this procedure if you have not used a material in the production process and want to reverse the excise duty debited to your CENVAT account.
Procedure: -
1. J1IH > Excise JV > Create ? Matl non-prod.
2. Enter data as required, including:
u2022 Document number
Enter the number of the material document that the adjustment posting is to refer to.
u2022 CENVAT account selection group box
Specify which account is affected by the adjustment posting is for. If the posting does not have to be remitted immediately, select Fortnightly payment.
3. Click on u201CEnteru201D button.
The system displays the information from the material document.
4. Adjust the posting date as necessary.
5. Adjust the excise duty for each line item either:
u2022 Manually
u2022 By assigning the line item to an excise invoice
6. Specify which G/L accounts are to be posted to.
Here you can change Debit A/c as per your requirement.
7. Save the adjustment posting.
Excise JV Document, Accounting Document with Part2 Serial No has been successfully created.

Similar Messages

  • Purchase order Field LIke Material , Non editable by using Trax code Me22n

    Guru
    How to make Purchase order Field LIke Material , Non editable by using Trax code Me22n
    Thanks

    Hi
    Check this in SPRO- SAP IMG- Material Management - Purchasing- Purchase order- Define screen lay out at document level
    In this select the particular field selection key and change the material field to display.
    Hope it will do
    Regards,
    Raman

  • Grid Control : Change Management Across Non-Prod and Prod

    All,
    I had some questions with regards to Grid Control Implementation Architechture on Prod and Non-Prod Env's
    The best practice is to configure a production Grid Control (GC) environment to monitor only production targets. This prevents nonproduction targets from adversely impacting a production environment.Another issue could be the compliance policy where in the production systems are to be isolated from Non-Production Environments.
    If this is the case then we have to have 2 GC environments , 1 for Prod and 1 for Non-Prod. In such a scenario how well can we do change management (Version control ) across the Non-Prod and Prod Environments ?
    To be more specific
    How is version control managed for Oracle builds if we have separate GC for Prod and Non-PROD? (Change Management pack / Configuration Management Packs are there but what is the real depth of these? )
    Change management for the Oracle Environments from DEV -> Test -> Pre-Production-> Production? We aim to have consist build across the environments can we achieve this if the GC is managed by Different OMS/OMR and if we have 2 separate environments how do we sync the GC environments managing PROD/NON-PROD after a change?

    This is feature is not there in 10.2
    This situation can be avoid by chagning the 9i port to 1522
    or install the GC on diffrent box

  • Workflow Notification Mailer in Non-Prod

    Hi,
    Does anyone have any suggestions on the best way to setup notifications in Non-Prod environments so there is not confusion with Production EBS notifications?
    Thanks in advance!

    Change the Message Generation configuration of Workflow notification mailer
    Navigate :
    System Administrator --> Workflow --> Notification Mailer --> "Stop the services" --> click "Edit" --> Click "Advanced" --> Click "Next" and go to "Message Generation"
    --> change "From" (eg.) PROD Workflow Mailer to "TEST Workflow Mailer" --> Click "Finish" --> Start the Services again.
    Thanks,
    Narasimha Rao

  • Material non cenvatable

    Dear All,
    I am having a scenario,
    PO- 100 inr
    Excise- 10 inr
    Vat- 5.5, I don't know while making PO where i will avail cenvat or not.
    Now at the time of GR i know that i am not availing the cenvat credit. So i manually make the material non cenvatable and the excise duty is loaded on the stock, which i want also.
    Stock- 110 db
    Gr/Ir Clearing- 110 cr. That is OK.
    Now at the time of invoice verification, system suggest me 100 inr for bill passing in line item. When i calculate tax, accounting is
    Vendor- 115.5 cr
    GR/IR Cleaing- 110 db
    stock- 10 cr
    Cenvat cleaing- 10 db
    Vat payable- 5.5 db.
    So the ultimate impact 10 inr for excise not getting loaded on the material. I want stock valuation by 110 inr and Vendor posting by 115.5 inr.
    Please suggest

    Hi,
    Are you using TAXINN procedure if it is yes then maintain Excise condition as JMIP in T code FV11 with key combination of tax code/ Plant or Plant / material/ vendor as per your reqyurement then check in GR the GR/IR will be same as per your requirement as this excise duty will be loaded to material cost which is Non cenevatable which results in loading to material cost.. Hope this helps you.
    Regards

  • Change Material non-valuated to material valuated

    Hi experts,
    I have created a material before doing settings in transaction OMS2, so this material was created as non-valuated.
    After that, I have changed the settings in transaction OMS2 (I have marked qty updating and value updating).
    I'd like to change the material master - accounting 1 from material non-valuated to material valuated.
    Is it possible to do it?
    Thanks.

    Hi Osmar,
    You may change your non-valuated into valuated material, by doing following steps:
    1. create new material type for valuated material
    2. change your material with the new valuated material type using MMAM
    But ensure that new material type should be extended into particular Plant that has been assigned for respective material master.
    Cheers,
    Girang

  • Hiding non Prod IBASE -ChaRM

    Fellow Members,
    Is there a possibility to hide non prod IBASE component from scope selection screen  in charm.
    I need only Prod system with prod client to be displayed, when user/change manager tries to define scope. Currently search for component displays all the systems and client.
    This is avoid user selecting wrong ibase.
    -SS

    Hi,
    This can be done by restricting authorization object SM_SDK_IBA for the users. This will restrict the configuration item to show only the ones which links the systems you have maintained in Identification tab of Business partner with CRM001 entry. This auth object has a field "IBase Components that the BP itself is assigned to" which restricts the visibility.
    Regards,
    Vivek

  • Issues with clone of database from PROD to non-prod

    Hi All,
    I am trying to clone the production database to a non-prod database.This used to work fine with out any issues before.Only change made on the backup side is we change the compress option to nocompress.Below are the steps followed for the clone process.
    Create a new init parameter file.
    Started the database in nomoutn state
    Connected to prod database through rman
    connected to auxiliary database(non-prod)
    connected to catalog
    Set the new file destinations in ASM for the non-prod database.
    Set the recovery time until the last SCN on the full backup.
    Here is the error encountered during the process of restore.
    ORA-19870: error reading backup piece /exp/prod_backup/emrepdb_0_PROD_20101114_ublt0vq6_1_1
    ORA-19502: write error on file "+STG_DATA/stage/datafile/undotbs3.dbf", blockno 2641537 (blocksize=8192)
    ORA-27061: waiting for async I/Os failed
    Outer dbms_backup_restore.restoreCancel() failed
    ORA-19870: error reading backup piece /exp/prod_backup/emrepdb_0_PROD_20101114_ualt0vq5_1_1
    ORA-19502: write error on file "+STG_DATA/stage/datafile/undotbs4.dbf", blockno 1044817 (blocksize=8192)
    ORA-27061: waiting for async I/Os failed
    Outer dbms_backup_restore.restoreCancel() failed
    Any one faced the same kind of issues before?

    Hi,
    ORA-19870: error reading backup piece /exp/prod_backup/emrepdb_0_PROD_20101114_ublt0vq6_1_1here is problem with execute permissions on the backup location, give full permission to open those backup sets and read...
    post
    ls -ltr /exp/prod_backup/emrepdb_0_PROD_20101114_ublt0vq6_1_1give full permissions like *777*
    #chmod 777 -R /exp/prod_backup/*
    Thanks

  • Repair flow (material non valuated) must be transferred to storage location

    Hi,
    We create an Repair Sales Order.
    Then we receive the material (Mvt 451) in non val. stock.
    Then we like to transfer to the shipping storloc. but should not be valuated. From the shipping stor.loc. we would like to create a delivery and send the repaired material back.
    How can we transfer the received material (mvt 451) to a storage location without adding value. Which movement type can we use?
    Thank you,
    Eric.

    Hi,
    We receive the material with mvt 451 in return stock.
    So it is initial not available for transfer. But if I transfer it then it gets valuated. This is what we do not want. Which movement type do I need to use (or more steps) to move it from 451 return stock to an other storagelocation without value creation.
    Thank you,
    Eric.

  • Check stock availability in non-PROD loc

    Hello,
    I have set my production st/location(PROD) in material master, When I creates the prod order it always check the stock availability in PROD location and pops up missing parts as stock is in raw materials loc.
    Can we set something, so that while prod order creation, it should check stock availability in all raw material locations (but not in PROD).
    added laterly----
    I think it can be done via OPJJ, no sto loc inspection, but what could be the pro/cons for setting this indicator.
    Please suggest.
    Regards,
    JPS
    Edited by: Bhatti JPS on Apr 7, 2010 5:35 PM

    JPS,
    If you make the OPJJ setting, it will check all storage locations in that plant, including PROD.  Depending on what this StLocn is used for, this is probably OK.
    Some companies 'stage' their materials, which means they move stock from RM stockroom to a production floor staging area location.  Then, they run their ATP.  'Missing parts' means they have to go to the RM Stockroom, get the missing stuff, and move it into the production staging area.  For these companies, they want PROD checked exclusively.
    Other companies (sounds like your company) don't stage their components.  They run their prod order ATP checks, and any missing parts list they hand to the expeditors, who may go to the department that makes the subassembly (manufactured component), or may go to Purchasing department to expedite the RM (Purchased component).  
    It really depends on the business requirements.
    Rgds,
    DB49

  • Ideas on how to restrict non-prod servers from connecting to prod sql servers

    We ran into an issue this week and I’m looking for some ideas on approaches we might be able to use. While troubleshooting a P1 issue, we noticed Non-Production application servers connecting to the Production backend SQL Server using a Production account.
    The matter of how they obtained the PROD password is a security issue and we are already working that endeavor separately but my question is what (if anything) are other people using to identify and more importantly restrict connections on their Production
    SQL Servers from non-production servers?
    A colleague has already mentioned the possibility of creating a Classifier Function and using Resource Governor to identify hostname and if they begin with “DEV…” or “TEST…” they are not allowed in. Anyone have any other ideas???
    Thanks in advance
    Andre Porter

    If hostname is your criteria then I don't see any reason why a logon trigger wouldn't work...
    Beware that the hostname can be set in the connection string, so this is not safe.
    Despite what Javier said, it is possible to use the IP address, as it is available in sys.dm_exec_connections and cannot be spoofed. But there are a couple of things to keep in mind. The trigger needs extra permissions as plain users does not have access
    to sys.dm_exec_connections. You also need to consider local connections and possibly also connections over named pipes or VIA.
    The best and robust solution is to put test and production servers in different network segments, and then prevent access between the segments.
    Erland Sommarskog, SQL Server MVP, [email protected]

  • Different number of Business service endpoint for prod/non prod env in OSB

    Hi,
    I have a scenario in my project. We have 2 managed servers in all non production environment and 4 servers in production environment.
    In non production environments, have added 2 end point uri in the business service. If we create customization file from this, it will have only 2 endpoint uri details.
    Now problem is how to get all 4 enpoint uri added for production environment. Dont know how if we try to add 2 uris in customization file will work fine or not. Also it will be very cumbersome as there are more than 100 business services.
    Tried with comma seperated urls, but load balancing is not happening. Same thing when cluster address is used.
    Any pointers on this will be helpful.
    Regards,
    Pravin
    Edited by: pravinkapile on Sep 29, 2009 9:39 PM

    Hi..
    There's several ways to do it.. What I prefer to do is to generate the customization files and have a seperate set for each environment. As you say hand modifying the customization files is a pain (and error prone), so I wrote a program to generate the customization files.. basically it runs against my local dev environment, creates an edit session, modifies the env values (these are held in a properties file (easier to maintain)), exports the customization files and sbconfig jars, then discards the edit session.
    I then use a wlst/jmx script to perform the imports and running the customization files, then after the customization is ran, then I have a section that modifies the business service with multiple endpoints to set them up to load balance/failover..
    this is the function in my utils script to set the load balancing/failover....
    #=======================================================================================
    # Routine to modify all Business Endpoints with multiple URI's to set the Loadbalancing
    # algorithm to Round-Robin -
    #   Input must be an editable instance of an ALSBConfigurationMBean.
    #=======================================================================================
    def configureMultipleBSEndpoints(domainService, alsbSession):
      try:
        # get the Service config MBean
        servConfMBean = getServiceConfigurationMBean(domainService, alsbSession.getSession())
        bsQuery = BusinessServiceQuery()
        bsRefs = alsbSession.getRefs(bsQuery)
        changesToCommit = cju.parseBoolString("false")
        for bsRef in bsRefs:
          modificationsMade = cju.parseBoolString("false")
          serviceDefinition = servConfMBean.getServiceDefinition(bsRef)
          endPointConfig = servConfMBean.getEndPointConfiguration(bsRef)
          if endPointConfig.getURIArray().__len__() > 1:       
            outBoundProps = endPointConfig.getOutboundProperties()
            if outBoundProps.getLoadBalancingAlgorithm() == LoadBalancingAlgorithmEnum.NONE:
              outBoundProps.setLoadBalancingAlgorithm(LoadBalancingAlgorithmEnum.ROUND_ROBIN)
              modificationsMade = cju.parseBoolString("true")
            if outBoundProps.getRetryApplicationErrors():
              outBoundProps.setRetryApplicationErrors(cju.parseBoolString("false"))
              modificationsMade = cju.parseBoolString("true")
            retryCount = endPointConfig.getURIArray().__len__() - 1
            if outBoundProps.getRetryCount() != retryCount:
              outBoundProps.setRetryCount(retryCount)
              modificationsMade = cju.parseBoolString("true")
            if outBoundProps.getRetryInterval() != 2:
              outBoundProps.setRetryInterval(2)
              modificationsMade = cju.parseBoolString("true")
            serviceOpsEntry = servConfMBean.getServiceOperations(bsRef)
            if cju.booleanToString(serviceOpsEntry.isTakingURIOfflineEnabled()) == "false":
              serviceOpsEntry.setTakingURIOfflineEnabled(cju.parseBoolString("true"))
              serviceOpsEntry.setDelayInterval(15);
              modificationsMade = cju.parseBoolString("true")
            if modificationsMade:
              print 'endpoint configuration modifications made to - ' + bsRef.getFullName()
              hmServiceOpEntries = HashMap()
              hmServiceOpEntries.put(bsRef, serviceOpsEntry)
              endPointConfig.setOutboundProperties(outBoundProps)
              serviceDefinition.setEndpointConfig(endPointConfig)
              servConfMBean.updateService(bsRef, serviceDefinition)
              servConfMBean.updateServiceOperations(hmServiceOpEntries)
              changesToCommit = cju.parseBoolString("true")
        return changesToCommit
      except:
        print "Unexpected error:", sys.exc_info()
        print 'Failed to Configure Business Service Multiple Endpoints LoadBalancing Algorithm '
        raise..Mark.

  • Serial No. tobe assigned to issue material in prod order confirmation scree

    Hi,
    have one material to be issued against production order in CO11N, this issued material should get one serial number atomatically.
    regards.

    Dear,
    In an Production order CO01/CO02 allows the user on header level to assign serial numbers to the production order.
    For component you can not do this in confirmation screen For the work around refer this link,
    [Serial Number For Components |Re: Reg serial numbers for components]
    Regards,
    R.Brahmankar

  • FG material in Prod Ord once 101, goes to Quality Inspection Stocks

    Hello,
    I would like to ask, why does one of our Finished Goods in our production order once confirmation 101 was done to it, the stock went to the Quality Inspection Stocks? We have check its material master data Quality Management Tab and below are what we see on it:
    in the Procurement Data Section:
    QM proc. active was TICK
    QM Control Key = 0000 (No active functions, info message)
    in the General Data Section:
    Inspection Setup was not TICK (no inspection set-up was maintain for the finished goods)
    That is why we wonder why it still been cue to QI stock once 101 was done? how could we check this and where else does this things occuring? please guide and help us to resolve the problem of ours.
    Thanks

    Hi,
    Is this inhouse produced or the Extenally procured material.
    in case externally produced material check the Qinfo record for the same also.
    reg
    satheesh

  • Various errors on self-monitoring (non-Prod) evironment

    Hi all, i do have few issues that i see on the app srv log for PPM, any idea whats causing this errors:
    - Component Performance metric calculations may be inaccurate or incomplete (usually getting this)
    - Errors in AppServ log "Communication to Monitor Servlet failed" (always)
    - Component objects not fully cached (rarely)
    - No Component PeopleCode trace information (always)
    I do get data populated in current and history tbls for PPM.
    thanks

    thx for the reply Nicolas
    answers to your questions;
    Peopletools version, ;8.48
    database used (with version), Oracle 9i
    OS (with version) :GENERIC (All Platforms)
    what configuration setting has been done or not: its a self monitoring PPM setup
    proper extract from your appserver/webserver log would be useful: im working on getting that from the customer
    let me know your thoughts...

Maybe you are looking for

  • Calling SQL function in SQL query fails

    Hi There, I am trying to execute INSERT INTO XML_DATA (NAME, DATASIZE, DATA) VALUES (?,?,XMLType('?')) using ODBC C SQLBindParameter APIs. If I execute the INSERT INTO XML_DATA (NAME, DATASIZE, DATA) VALUES (?,?,XMLType('<name>milind</name>')) works

  • How to print an int in binary form ?

    Say I have an int storing 5, can I print it out as 00000101 ? Thank you very much

  • K7N2delta ILSR won't except video drivers?

    I bought a K7N2delta ILSR & can't get it to accept the drivers for an ATI 9600? Before I install the drivers windows XP pro sets some drivers & I can alter the pixel settings, but once I install the ATI drivers I get nothing but a black screen? I boo

  • Special characters in file ^@

    hi, i used method tostring to convert a double into string and have written in a file, while i try to open the file in shell(unix), it shows some special characters as follows, ^@0^@.^@0^@4^@3^@7^@4^@0^@7^@ ^@0^@.^@0^@3^@1^@3^@1^@9^@2^@ ^@0^@.^@0^@1^

  • Why we use tcode qa07 deadline monitoring batches

    Dear Sir, i m new in qm module,can u tell what is deadline monitoring baches,what exactly the use of this tcode-QA07 There is initial run days enter what the use of  that days.its for transfer there quality stock to unrestricted befor retest date or