JIT  delivery schedule tab in Scheduling agreement is greyed out.

Hi all !
The "TAB JIT delivery schedule" is not accessible when creating a new Schedule line agreement. Where do i change the settings so that this TAB is available to me.
Thanks and regards,
vijay

Hi,
First please check whether schedule line due for delivery or not and other thing that prevent further processing of doc . If envrything is fine .
Please check tcode SHD0 Put Transaction code as VA31
                                              Transaction Varinat as BUS_2035 ( OR press F4 and select the one)
Trnsaction varinat will appear in lower half of screen -> click on first one -> change -> go inside u will find all the field, radio button etc please check the ur one and check whether the checkbox saying Output only in front of that field is checked or not .
If checkbox is checked please uncheck the same save it and try again .
If it is not checked or field is not availble . Please check other reason as there is no problem with screen varinats
Hope this help

Similar Messages

  • General Settings..BP Tab Activate approval procedure is greyed out

    Hi
    I see the General Settings..BP Tab Activate approval procedure is greyed out - how do i activate this
    regards
    Manian

    Hi,
    If the user you use to log into the system is one of the originator in any Approval template, then the tick box will be greyed out.
    To edit this tick box, check all approval templates you defined in the system to see if there is any users are not the originator for any templates. Log in as this user then you can active this box.
    hope this help,
    regards,
    maggie an
    Edited by: Maggie An on Jun 16, 2008 10:52 AM

  • Tools/Opts/Gen'l/start---Show windows/tabs from last time is greyed out.Unable to use.

    Unable to click on option noted. Also; using ff6.0.2 -- all tabs take a very long time to complete loading (sometimes several minutes). The rotating arrow (CCW) is fairly quick BUT the CW arrow rotates for inordinately long time. It seems to be all ALL tabs but w/varying timeframes.

    Yes, that can happen if you run Firefox in [[Private Browsing]] mode.
    * You enter Private Browsing mode if you select: Tools > Options > Privacy > History: Firefox will: "Never Remember History"
    * To see all History and Cookie settings, choose: Tools > Options > Privacy, choose the setting <b>Firefox will: Use custom settings for history</b>
    * Uncheck: [ ] "Automatically start Firefox in a private browsing session"

  • When firefox starts show my windows and tabs from last time is greyed out

    firefox 4.0 startup. when I go to general under options when firefox starts show my windows and tabs from last time it is grayed out and I can't select it.

    Yes, that can happen if you run Firefox in [[Private Browsing]] mode.
    * You enter Private Browsing mode if you select: Tools > Options > Privacy > History: Firefox will: "Never Remember History"
    * To see all History and Cookie settings, choose: Tools > Options > Privacy, choose the setting <b>Firefox will: Use custom settings for history</b>
    * Uncheck: [ ] "Automatically start Firefox in a private browsing session"

  • Business area tab in Sales order is greyed out

    Dear Experts,
    My requirement is that i need to give business area in the sales order.But even when we are creating the sales order the business area field in the account assignment is greyed out even when the recon account the field is set to optional entry.
    Help rerequired urgently.
    Thanks in advance,
    Ramesh Babu.

    Dear Ramesh babu,
    Please check in which table the business area is assigned to plant /sales area.
    It is T134G.
    Using the exits mentioned under the heading 'User-Exits for product allocation' in the below link,
    http://help.sap.com/saphelp_46c/helpdata/en/1c/f62c7dd435d1118b3f0060b03ca329/content.htm
    check whether you can pick the plant and division from the order and input the business area  (based on the entry maintained in T134G against the Plant and Division ) using ABAP help.
    Thanks & Regards,
    Hegal K Charles
    Edited by: Hegal . K . Charles on Sep 16, 2011 10:54 AM

  • Partition Tab in Disk Utility is Greyed Out

    Basically I wanted to try out Mac OS X Yosemite, so I created a partition on my hard drive. Now, I am trying to remove this partition, because it is no longer needed, but Disk Utility is simply not allowing me to.
    I heard there may be a way to solve this using Terminal. Is that possible?
    Any answers and/or helpful comments is appreciated in advance. Thank you.

    And, this was from the Internet Recovery utilities window, right? OK, this next suggestion depends on which MBA model you have. Check the link below. If your model came with Lion pre-installed then it is capable of using Internet Recovery. If it came with a late version of Snow Leopard it can be upgraded via a firmware update. You will find this in the link below.
    Computers that can be upgraded to use OS X Internet Recovery
    Be sure you backup your files to an external drive or second internal drive because the following procedure will remove everything from the hard drive.
    Boot to the Internet Recovery HD:
    Restart the computer and after the chime press and hold down the COMMAND-OPTION- R keys until a globe appears on the screen. Wait patiently - 15-20 minutes - until the Recovery main menu appears.
    Note: You will need an active Internet connection. I suggest using Ethernet
                if possible because it is three times faster than wireless.
    Once the Utility Menu appears select Disk Utility and click on the Continue button. Now try removing the partition again. If you have the same error, then do the following:
    From the screen's menubar select Terminal from the Utilities menu. Enter the following at the prompt:
         diskutil list
    Press RETURN. You should see a display of your devices. Next enter:
         diskutil unmountDisk force /dev/disk0
    Press RETURN. Now, if this works your internal drive should be unmounted. Return to Disk Utility and try the process of removing the partition.

  • RSS "Open all in tabs" greyed out.

    On RSS feeds "Open all in tabs" seems to ALWAYS be greyed out.
    It works fine on other bookmarks, so it is NOT this bug:
    https://support.mozilla.org/en-US/questions/950762
    I have lived with this bug for a loooong time since an update, I think it was around FF13.
    It is greyed out on ALL machines I know of... I have seen the bug on several machines with completely independent bookmarks, seen on multiple windows versions
    Tried all tricks and NONE worked. Just tried to start in safe mode (did not help) tried to start in safe mode and reset EVERYTHING - but the bug persists.
    Googling the bug gives thousands and thousands of hits, so this is still an existing bug NOT related to add-ons.
    The reset saves the bookmarks, so I guess the bug MIGHT be found inside the bookmark-database corrupted at some upgrade.
    If this is not a bug, but an intentional removal of a function, then it should be hidden not greyed.

    Thanks for the quick response. :)
    I added the not too fantastic
    OPEN ALL IN TABS 1.0.rev698
    that adds the function back in a slightly awkward way.
    ....But why not keep it as an About:config option?
    But even better would be to replace it with "Open all UNREAD in tabs"
    :-)

  • Importance of Forecast Delivery Schedules in SD scheduling agreements

    Hi ALL,
    I would just like to consult you a scenario that I'm facing.
    When I create a JIT scheduling agreement, even though that schedule lines are maintained for the JIT delivery schedule tab, if the Forecast delivery schedule tab has no schedule lines, the NET value of the document will be zero.
    Can you explain the Logic behind this?
    Also, why am I not allowed to create an outbound delivery and invoice if the Forecast Delivery schedule tab has no schedule lines?
    I know that the document will be incomplete without the net value, but why is it even though schedule lines are created in the JIT tab?
    Please help me with this.
    Thanks in advance guys!

    This is what I found out in an SAP “Knowledge Base Article" (1472965), indicating that there has to be requirements in the forecast delivery schedule in order for the schedujle agreement line item to not be considered incomplete for price.
    https://websmp230.sap-ag.de/sap/support/notes/convert2pdf/002007204200000153012010?sap-language=EN
    Resolution
    l You have to enter schedule lines for the forecast delivery schedule
    l The VBAP-NETWR is calculated based on forecast delivery schedule and not according to the JIT delivery schedule
    Regards,
    Jeff

  • Forecast delivery schdule and JIT delivery schedule difference

    Hi All,
    What isthe difference between Forecast delivery schdule and JIT delivery schedule in JIT scheduling agreement (LZJ)?? 
    I am doing JIT Inbound process now. Is it necesary to update both the schedule lines(Forecast delivery schedule&JIT delivery schedule)??
    Thanks,
    Anbazhagan E

    Hello,
    Forecast Schedule updates your planning , i.e. in MD04 you could see system is planning for quantities updated in forecast schedule.
    regards,
    amol

  • Planning delivery schedule , forecast delivery schedule , JIT delivery sche

    Hi
    could any one tell me the difference  between Planning delivery schedule , forecast delivery schedule , JIT delivery schedule & their respective ways of processing delivery???????????????????????????????????????????????/

    Hello Friend,
    Planning Delivery Schedule:
    You want to plan requirements for a certain customer for the next 16 weeks. You create a planning delivery schedule on the basis of information that you have gathered in an internal planning system. A few days later, the customer sends you a forecast delivery schedule that covers only 12 weeks. You decide to generate a planning delivery schedule by copying the schedule lines from the forecast delivery schedule for those 12 weeks, splitting them into units and days that fit your production schedule. For the remaining four weeks that you require, you simply adopt schedule lines from the previous planning delivery schedule in the scheduling agreement.
    For another customer, you create a six-week planning delivery schedule on the basis of internal data. When the customer sends in a forecast delivery schedule for the same six weeks, you notice that the first four weeks of schedule lines in the customer delivery schedule are detailed enough for production, but the last two are inaccurate. You decide to copy the first four weeks of schedule lines unchanged into the new planning delivery schedule. You adopt the remaining two weeks of schedule lines from the previous planning delivery schedule, which already exists in the scheduling agreement.
    Forecast Delivery Schedule:
    For an SD scheduling agreement, a customer sends a forecast delivery schedule containing requests for individual schedule lines. On the SD side, a delivery can be created automatically from this.
    JIT Delivery Schedule:
    A release carried out at an exact point in time of quantities in a schedule line (of a delivery schedule).
    The JIT delivery schedule is way of fine tuning production for the customer and shipping for the vendor.
    The term is used predominantly in the automobile component supplier industry.
    Delivery in Forecast in done through VL10 & VL01N and Delivery through JIT is done from JITK.

  • PO - Item Data - Delivery Schedule Tab - Delivered qty, issued qty, GR qty

    Hi Frens,
    In a Purchase Order, under Item data < delivery schedule tab, we have delivered quantity, issued quantity and GR quantity fields.
    Is there any TABLE to find out these quantities against PO.
    Thanks and Regards,
    CK Vikas

    >
    CK Vikas wrote:
    > Hi Raj, You mean EKBE?
    Yes EKBE is the right table for your requirement.

  • Display only/Grey out Delivery Schedule tab in the PO

    We are not going to use Delivery Schedule tab at all. Business wants us to Grey out the delivery schedule tab. Is it possible to make all fields under Delivery Schedule as display only? If yes, how can I do that? But, I don't want PO line qty to be grayed out.
    Fields like, delivery date, scheld qty, stat.del date etc.
    Thanks everyone.

    you better convince your business to wait for a couple months and then rethink this requirement.
    You may not have the full understanding yet and have not made a lot experience.
    in this tab you can add further requisitions to your PO item, you can close requisitions in case you order less than a requisition, you have to change the statistical delivery date in some case when you are using vendor evaluation, you may have to split the order quantity into several delivery dates  if your vendor informs you that he cannot supply you at one time with all quantity.
    Just to save you money that you may spend into a development which has to be turned off a little later.

  • I faile to create outbound delivery with reference to scheduling agreement by using BAPI_OUTB_DELIVERY_CREATE_SLS.

    Dear Team,
    Can you please help me by providing the BAPI name for creating the outbound delivery for Scheduling Agreement in SAP SD .
    I faile to create outbound delivery with reference to scheduling agreement by using BAPI_OUTB_DELIVERY_CREATE_SLS.
    The system says "missing data in the BAPI interface: VBAK VBTYP E". It seems another FM should be used for scheduling agreement only.
    Thank you for your help in this regard .

    Hi Raghu.
    As much as I don't want to do this but just to resolve this error I created an enhancement implementation in include LV50R_CREACSV form routine dcs_check_so_vs_interface and modified VBTYP to blank to avoid that error message.
    Got the tip from this thread http://scn.sap.com/thread/1972059
    Unless... anybody has a brighter idea (without modifying the standards)?

  • Delivery schedules with outline purchase agreement

    Can somebody tell me how to automatically result delivery schedules with outline purchase agreement through MRP running?

    Priyanka.P thanks for your reply.
    The following is how I process:
    1.I use auto po indicator at VMR
    2. I tick Auto PO indicator and source list indicator at MMR
    3.I have made schedule agreement(type LP) and assign it in source list as fix vendor(1000) and with the MRP indicator 2(Record relevant to MRP Sched. lines generated automatically)with the proper validity periods in IDES.
    4. In MD03, I use the create schedule as 3
    5.There is Dependent reqmt.
      When I finish my MRP running I find a Purch.Req with Exception 30( Plan process according to schedule (08.11.07/08.11.06)) generated. however I hope a  vendor Delivery schedule.

  • Greyed out fields to be enabled in delivery schedule tab of ME21N & ME22N

    Hi Gurus,
    I need to make two fields in PO create and change tcode, to be made editable as they are greyed out for particular document type and item category combination. Please refer screenshots below:
    Standard Order:
    Framework Order:
    I tried settings in 'Define Screen Layout at Document Level' for that field selection as well as in Edit system settings at the item detail level...but still the fields are in disabled mode only. Any help in this regard??
    Thanks in advance...

    Hello Pramod,
    As AKPT has pointed out, FO type documents are used for a broad framework type scenario, where most of the details are unknown at the time of releasing the PO.
    The system by default allows standard, limit (B) and service (D) for such POs.
    If you are trying to change the item category during creation (and not after the PO has history) please look at this IMG -> MM -> Purchasing -> Define Doc types -> Framework order FO -> Allowed Item categories.
    I don't think delivery schedules are allowed for FO type orders.

Maybe you are looking for

  • Running multiple instances of program in parllel processing.

    Hi Experts... We have an issue where we need to update huge set of data (say more than 2000000), update is simple where some BI table needs to be updated for few fields. Now issue is that if at one go this update is done then there is memory issue, s

  • Acrobat Pro XI problem+Accept End User License Agreement when opening a PDF inside IE

    Hi folks, this issue has been challenging. Acrobat Pro CC install W7 X64 Deployment went ok after the code was worked out, but..... We use Desire to Learn content management system at the community college where I maintain the student computers at. W

  • Firefox 11 will not install air or start air application from the badge install

    Seems to work in Chrome, but I need this to work from within firefox...11 is the default for the windows platform we must use. Running window 7 64-bit for development, and the air app is html javascript (J Query) created in dreamweaver 5.5 any help..

  • Replacing a image in progressbar.....

    Hi all, Is there any way by which i can have a image moving in a Progressbar(instead of rectangle moving) in case of indeterminate progress bar??? please help... -Soni

  • Aperture and Red Eye Removal

    Is there a way to reduce the size of the white eye after removing red eye from one's photos?  Aperture does a good job of removing the red eye area but leaves a rather large white shining ring for the iris in my photos.  How do I reduce the size of t