Lead time Report

Hi,
Would like to have a report on Lead time between PO Date & GR date.
Ideally the report should show the PO Number, Date,Material, Mat. Doc Number & GR Date.
Though ME80FN shows by clicking the PO history, But our user would like to have in a single line item.
Is there any other Standard Report  to get the above data?
Regards,
Vengat

Hi,
There is a standard report that shows the actual average LT compared to the master data definitions. You can also see the details, and even update master data automatically if you want; WPDTC.
Regards,
Mario

Similar Messages

  • PO lead time report

    Hi Gurus
    What report can be run to provide the average time taken from PO creation to Goods reciept? IE how do we measure actual delivery lead time
    Thanks in advance
    BR

    Hello
    Thanks for reply.
    IF this is not , could you pl let me know the correct procedure and any standard report for measuring the Delivery time for Purcsase Order based on materials.
    As per your exnample , why a person should enter the delivery date manually , it should should come by system based on PDLT maintained ..
    for tht reason only we are looking to review our materials to update correct PDLT.
    thanks..

  • Production lead time report

    Hi,
    Given below mateiral with their lead time activity
    Material A- Finish (in house prodn)
    100 qty = 10 days
    Low level in BOM
    X- Halb (2 days)
    Y-Roh (10 days)
    Z-Traded goods (2 days)
    Is there any report available which provide the information, if i want to plan mateiral (finish) with what period it is possible to fulfill the customer requirement. Considering all procurement and production activity.
    Regards,
    Rajesh

    Hi Rajesh,
    There is no standard report available for the leading time of FG with BOM multi levels. You can go for a Z report.
    thanks and regards
    Murugesan

  • MM Report for Reorder and lead time

    Hi,
    Can anyone suggest me a report that can show information by materail such as min./max. quantity, re-order or safety stock, and replensihment lead time.
    Thanks
    Atif

    you can create the query using MARC or just go se16 adn enter the MARC table and pull the data.\
    Displayed Fields:   8 of   8  Fixed Columns:                2  List Width 0900                                                                               
    Material             Plant  Reorder Point     Safety stock      Min. lot size     Max. lot size     Total RL time Min SafetyStock                                                                               
    MATERIAL            Z001               0.000             0.000         5,000.000       350,000.000   0                       0.000

  • Lead time values are not appearing in the report for current year.

    Hi friends,
    Iam checking a report in production.  where lead time values are displayed as 0 for 1 key figure lead time3 (w/0 dim) . i found there is a formula for this it shows like NODIM ( 'Lead Time 3' ).and there is a value for cal.lead time
    how can i get values in the report.
    Thanks ,
    VRV.

    Hi,
    Although your question is not clear, I understood that the formula built on that KF is NODIM. Basically it means, units of measurement is not considered when calculating.
    Eg: 5 Minutes + 5 Kilograms = 10
    You please try to analyze your KF by the above logic. Then you would be able to figure out why the data is not appearing in the report..
    Assign if helps...
    Regards,
    Suman

  • Lead Time Demand on REORDER POINT REPORT ??

    Hi ALL,
    Hope you all doing greate , I am very new in Re order point Inventory Planning Method. I have done all the configuration as;
    i - Creates an Item and assign it to the specific IO where I am selection the Planning method as Reorder point and enter the other paramters under the lead time tab I am seleting the total lead time as 5.
    I have define safty stock as 100  quantity.
    I have configure the Forecast Set and forcast under it which contain an Item with Current Quantity is 1000 now I have call the Report to run so I am getting the rest of the thing except value Lead Time Demand ??
    kindly help me in this regards, I would be so kind of you.
    Thanks
    Mohammad Younus

    Hi,
    There is a standard report that shows the actual average LT compared to the master data definitions. You can also see the details, and even update master data automatically if you want; WPDTC.
    Regards,
    Mario

  • Report Supplier Lead Time - Days

    Hi All,
    Can anybody give me the characters, key figures, CKF's, RKF's and other fields that are usually used in Supplier Lead Time - Days Report in general irrespective of the requirement.....come up what ever you remember from your side.
    Thanks All,

    Nevermind

  • PO Lead Time Standard report

    Hi Experts,
    Do we have Standard report to monitor PO Lead time. (Time taken by Vendor to fulfill the Order)
    Regards,
    Jackie

    Hi,
    You can use the report MC$K to check the delivery date vairance for the vendor with respect to material delivery.
    The delivery date variance is calculated with respect to PO Delivery Date and GR Posting Date.
    To execute the report, the delivery date variance  needs to be defined in transaction code MCFC at Purchasing Org. level.
    Regards,
    Bijoy Kumar

  • Material report showing lead time & min order quantity?

    Hi,
    Is there a report which I can download which shows by material, the lead time and minimum order quantity?
    Thanks
    Keeley

    We don't have access to any query writing so if it's not possible to get both fields on one table, can I run two reports?
    OR...
    is it possible to change the ME1M report to display/export horizontally in a table type format rather than wrapped?
    Edited by: Keeley B on Sep 23, 2009 7:58 AM

  • Re: report for lead time of material

    Dear Gurus,
    I just want to know is there report to see the lead time of material. Kindly suggest me which is the t-code available
    Regards,
    Rajashekar

    Hi,
    You can see the lead time in Report- MCE7 (T Code) for material analysis, here yo will get lead time delivery time of material as per Material group, Vendor,purchase Org. If you want to get material number ,after results displayed choose from menu settings > characteristic display > key & description (or just key) , then
    choose from menu settings > column width and extend the length to e.g. 59 (18 material number + space + 40 description)An alternative way is building query  taking into consideration Table MARC. Thanking you.

  • Target and Actual Lead time in MCP1 report

    Dear Experts,
    In MCP1 report, what is Target Lead Time and Actual Lead Time. How it is calculated?
    Thanks in advance for your valuable replies.
    Regards,
    Jejesh

    Hi,
                                                                                    Target lead time                                                                               
    On the operation level, it is the time period between the scheduled      
        input date at the work center (target input) and the latest scheduled    
        finish of the operation.                                                                               
    The target input date is calculated through the scheduled execution      
        finish of the previous operation.                                                                               
    On the order level it is the time period between the scheduled start and 
        the scheduled finish.                                                    
    and
                                                                                    Actual lead time                                                                               
    At operation level, the time between the input date at the work center   
         and the completion confirmation date (the total from queue time,         
         execution time and move time).                                                                               
    When calculating, the input date is determined via the completion        
         confirmation date of the preceding operation.  The process-dependent     
         wait time of the preceeding operation is subtracted.                                                                               
    At order level, the time between the reported start date and the finish  
         date (the total from execution times and transit times of the operations 
         as well as the order floats before and after production).                
    Regards,
    Rajesh

  • PR to PO lead time

    Hi All
    Is there any standard report to find PR to PO lead time.
    Formula to find PR to PO lead time = PO creation date - PR release date
    Regards
    Satish Kumar

    >
    satish kumar wrote:
    > Hi Afshad
    >
    > How do I get PR release date from EBAN table because the field "release date" in table EBAN is not the actual release date.
    Check this answered link:
    Re: Table for PR Release date

  • PO Lead Time cannot capture the time taken for shipping!

    Dear All
    I understand that we have PO lead time = PO Processing Time (Working Day) + Planned Delivery Time (Calendar Day) + GR processing time (working day).
    And this PO lead time will be added on top of my PO Creation Date to defer the actual goods availability date.
    My question:
    1. Planned delivery time is the time taken from vendor place to send out the goods to my warehouse. What if it is overseas purchase where goods leaving vendor's Port will first arrive in my country custom, and it will take 3 days to do clearance. once it is cleared, forwarding agent will delivery goods from my country custom to my warehouse. In this case, how do I capture it in SAP system for the planned delivery time as it has 4 periods of time now
    a. Time taken from vendor's port to reach my country's port
    b. Time taken for my country custom to do clearing
    c. Time taken for forwarding agent to fetch goods from custom to my warehouse
    d. Time taken for unpack, take out , count, inspect and put for use (GR processing time)
    Do I need to use user Exit?
    Thanks
    Edited by: Daimos on Apr 27, 2009 6:52 PM

    Dear dogboy.
    I think we must use feature on the PO Confirmation Control (CC) Key at PO Item Level:
    ED - Estimated Time of Departure from Overseas Port.
    EA - Actual Time of Departure from Overseas Port.
    EA - Estimated Time of Arrival
    AA - Actual Time of Arrival
    And the purchaser will maintain the value of each of the CC Key each time they are notified by the vendor.
    And we need to come out with a Customised Report to capture those CC dates entered so that finance is able to prepare $ in advance if the moment the EA is maintained, meaning the estimated date of arrival at the Custom there.
    But the problem is that PO User Exit is only at the header of Confirmation Control Key but not capture the DATE field we entered for each CC.
    That was the problem I last encountered.

  • Lead Time recalculation/update

    Hi,
    The requirement in my project is the following:
    I have a lead time for one material of 10 days. After two months I have recieved 2 PO's, one with 14 days and other with 12 days. The new lead time should be 13 days.
    There is any way to calculate this and update the material master?
    Thanks in advance,
    Guiza

    Guilherme,
    WPDTC is the TCode that you run to calculate the planned delivery time.  This transaction is available as of version 4.7.  Currently we are upgrading from 4.7 to ECC 6.0 and it still exists in 6.0.  There is a good description at this link in the SAP Help Library.
    [http://help.sap.com/saphelp_47x200/helpdata/EN/f3/41b53c4d36265ce10000000a114084/frameset.htm|http://help.sap.com/saphelp_47x200/helpdata/EN/f3/41b53c4d36265ce10000000a114084/frameset.htm]
    This program gives you a report of what the planned delivery times are in the info record, material master, vendor, and the calculated PDT based on documents and actual deliveries in the system.  You select the items you wish to change and click the Change Planned Delivery Time button.  You get a pop-up to verify you want to change the values.  Basically, this is a mass change tool for planned delivery time similar to physical inventory transaction MIBC - Set Cycle-Counting Indicator that calculates and changes the material master indicators.
    Hope this helps,
    Paul

  • Lead time issue

    Dear Sap Gurus,
    Is there is any report or in table  to check all the transportation Lead time settings  setting for particular plant  for all customers ? Because i need to upload several new Lead Time  due to the updation in transportation
    I want  compare the differences in system and the new Lead time whih is going to be updated.
    Thanks
    Guna

    Hi,
    Try joining VBAK, VBAP, LIKP and LIPS tables.
    take sales order number, confirmed quantity and document date from VBAK and VBAP tables and populate accordingly Actual PGI date and planned PGI date from LIKP and LIPS table. You can also take BKPF and BSEG if required. From this you will be able to find the time required between punching the sales order for confimed quantity and delivery to the customer.
    Thanks
    Anil Hooda