Hi
Created one invoice amounting Rs.12500. but the customer paid only Rs.12000.To settle the customer account can i create a credit memo of Rs.500.
OR what are the other possible doc type i can use to make the debit and credit entry same.
regards
Debasish

Hi Gupta,
As per the standard Credit memo request(reference to the Invice)-->Creditmemo.
But as per the client requirement we can do the copy control settings between the document types that is not a problem.
In your case the copy control done as per your client requirement from Invoice -->Creditmemo.
I hope it will help you,
Regards,
Murali.

Similar Messages

  • Line item Settlement and KOB5 for automatically created AUCs to PM orders

    Hello Experts,
    I am trying to set up line item settlement for automatically created AUCs. We would like to use line item settlement because we want to see the costs split up by either percentage or amount when settled to the AUC.  If I can't settle by percentage or amount to the AUC then i'd like to be able to temporarily block some of the costs from settling.  This is for billing not capitalization purposes since all costs will eventually settle to one final asset. The settlement is done using transaction KO88 or KO8G and automatic processing type.  I’ve configured a PM Order type as an investment order and set up the related investment profile and investment asset class.  Some of the things I've determined from my testing:
    Using transaction KOB5, costs can be split up by creating other distribution rules, but only to another object (i.e. another
    asset, order, cost center etc. by using the Preliminary) not to the automatically created AUC linked to the order
    The default settlement rule is account assignment category FXA, percentage rate 100%, settlement type AUC to the AUC
    and therefore cannot be updated/altered when using KOB5 or any other transaction.
    Once the costs are settled to another object other than the AUC, those costs cannot be settled to the final asset. Creating Preliminary
    settlement rules to a receiver IO and changing the period or fiscal year will not “block” costs from settling whether the processing type is automatic, by period, partial capitalization or full settlement.
    I’ve been testing this out in our development client and need verification that this is the way that transaction KOB5 works with line item settlement or did I do something incorrect . 
    Your feedback is greatly appreciated.  Thank you in advance.

    Hi Zaid,
    Thank you for your response.  Assets are not my area so I’m not sure if I missed a transaction or step in the process.   I tested this out by doing the following steps:
    Created AUC Asset class with line item checked
    Assigned PM Order type as non-investment with no investment profile and created order number
    Created a main asset number 
    Created an AUC sub asset number to step 3
    Created settlement rule to sub asset number on order
    Posted costs to order
    Settled from order to AUC with transaction KO88
    Created distribution rules for asset with transaction AIAB
    Settled from sub asset to main asset number with transaction AIBU
    When I settled from the sub to the main asset number in step 9, I found I lost the line item detail.  Is there another configuration setting I need to make to allow me to see the line item detail when I use AIBU?
    Thank you,

  • Line Item settlement of Internal Order through Investment Measure

    Dear friends
    Can we do the line item settlement of Internal order. The Internal order is created through IO as Investment Measure.
    Thank You

    Hi,
    Yes. It is possible to have line item settlement for Investment Internal Order.
    Trust this helps much!
    Cheers!

  • Tcode for line item settlement other than tcode CJIC

    Dear SAP Guru,
    Please let me know the tcode for line item settlement other than tcode CJIC.
    Required urgently.
    Thanks & regards,
    Pradip Shelke

    Thanks for your reply.
    Actually we are trying to create the BDC program for line item settlement. Through both the tcode CJIC & CJ70 this BDC program is not getting created.
    So please suggest some other tcode.
    Thanks & Regards,
    Pradip Shelke

  • Auc line item settlement to main assets

    Dear all ,
    We settled AUC assets Building  no.91000002 in main assets Building No. 40000005 from using T-Code aibu and aiab. , we select line item to settle in main assets. After settling we got document no. eg. 4000002 ,, but i want see all line item settled to main document no 400002 ,  i have check SE16 table ANEKPV not showing my settled line item ,, pls give any tcode which  line item selected to settled to eg.document no 400002. but we not using order no , wbs , project , i have check tocde KO88, AB03,CJID, kO02, AR01 Not find ,  how to know my selected line item, more details find the attachment ..pls help me
    Regads
    Ajay

    Dear Sir,
    Thank for reply  ,  i have checked e.g doc no - 1234561. then go environment and click original document, when i select it show two line item (list of assets document ) when i select main assets docs then go to overview assets docs , not go to CJ88 , so i am not able to resolve this issue , Pls help me ,,,
    if anybody know pls give me ans asap,,,,
    thanks
    Regards
    Ajay

  • Line item settlement(Invest prof)

    Dear Experts...........
    I have one doubt on Settlement (INVESTMENT PROFILE)
    I have seen like
    Summary setlement.
    Line item settlement and list of origin.
    I have read in SAP HELP ,evn though im not clear can any one plaz expalin in simple words about this different types of Setllements.
    Lineitem,Summary settlement.....wht is the function,how it works.
    Regards
    Chandra

    Hi
    In the summary settlement you can not break down the values of line item (e.g an invoice) and distribute it amongst the receivers.
    While in line item settlement you can distribute the amount of one invoice to different receivers. Take the example given in the link below. There are tow invoices from constuction (of value X) and electrical (value Y). Now if you are using the summery settlement then all the debit (X+Y) can be settled to one or more recevires but you can not break in between X and Y
    While if you go for line item settlement then you can use distribution rule like 20% of X and 80% of Y to one receiver and balance to another.
    http://help.sap.com/saphelp_47x200/helpdata/en/2a/f9f7de493111d182b70000e829fbfe/content.htm
    Regards

  • Work Order to cost center settlement with line item detail

    Iu2019m having difficulty finding a method to settle from a work order to a cost center with line item detail.  When an order is settled with KO88 or KO8G the total value for that work order/cost element combination is combined and posted to the cost center as a lump sum with the description of CTR\######.  Users would like to see the individual values that posted to the work order in a cost center report such as  KSB1.
    I donu2019t see anything in the settlement rule, settlement profile or allocation structure that will allow line item settlement from work order to cost center.     Is line item settlement possible when settling to a cost center?   Is there an alternate way to see these expenses as line items in KSB1?
    Thanks,
    Jeff

    Thanks Christian,
    We've defined an allocation structure that we use for Project System and Work Order settlement and have Receiver Categories established as FXA, CTR and WBS with "by Cost Element"  checked.  Work order costs do settle to the cost center entered in the settlement rule, the problem is it combines all items values as a single amount when posting to the cost center.
    For example:  
    expenses post to the work order under cost element 500000 for $500, $200, $300 and cost element 600000 for $250 and $250.  The settlement rule says to settle to cost center 170000.  When the settlement takes place cost center 170000 is debited $1000 to cost element 500000 and $500 to cost element 600000.  We would prefer to see individual posting of $500, $200, $300 to 500000  and $250, $250 to 600000.
    Thanks,
    Jeff

  • Open AUC Line Items

    Hi
    My requirement is to upload the legacy open AUC line items into the new system. For this we are writing a ABAP program. I could find all the AUC line items in the Table ANEP. But my requirement is to extract only the open AUC line items and not all.
    Can any suggest the Table in which I could find the open AUC line items ?
    Requirement is critical and thank you in advance.
    Gemini

    My requirement is not to find whether the given AUC is deactivated or not. I would like to extract the line items which are open in all the AUCs for uploading this as cut over data into the new system.
    As I have mentioned in my question I could find all the line items (settled + not settled) of AUC in ANEP table, but I want to know  if there is any Table which stores only the unsettled AUC line items.
    Thank you
    Gemini

  • LIne Item Reports CJIF & CJID - not showing output

    Hello Friends,
    Can anybody help me to find out why CJIF - Result analysis and CJID - Line item settlement not giving any out put though we are regularly doing RA & settlement for RA as well as Incoming order.
    Thanks and beste regards
    Bharat

    sorry - i should have clarified
    CJID can only be used for line items for settlements to assets
    this report is used when project is for investment
    the line item / summary settlement is part of investment profile, not settlement profile (i should have clarified that earlier)
    if your project is not for investment then use CJI3 from the line items for the project and fileter for the settlement cost element

  • Function to make line itens settlement in a Project

    Hi,
    We are having an issue in a development for the automatic line item settlement in a program since we can´t use CALL TRANSACTION because the standard way (CJIC - program RKPEP012) is an ALV report.
    Does anyone know another way of creating a settlment to a line item besides the standard transaction and that could be used in a program?
    Thanks for your help.
    Best Regards,
    Sandra

    I don't know such a feature. On the other hand it does not make sense to do so if you have a large project with 100+ files.
    Can you give a use case?
    Timo

  • Configure line item

    error is line item settlement not possible for asset
    my question is how to configure line item

    Hi,
    Check the asset class of the asset you are trying to settle. IN T code OAOA, w.r.t the asset class , check whether it is defined for "line item settlement" if not then maintain it.
    Regards
    Hemant

  • Assets with active line item management

    where I should get  assets with active line item management so I can do line item settlement is active.

    Dear Gajanan,
    When ever u execute AB08, system brings all the documents passed on that asset. In the list of these asstes the transaction which is at the bottom is the latest one. So the transactionlist goes as "Latest - Oldest" from bottom to top.
    Also, system by default selects the first transaton which is the oldest transaction.
    so u have to select the transaction that u want to reverse & click on reverse button. In the next screen put the revesal reason & click save. system will reverse only the transaction that u have selected.
    Hope this will solve ur issue.
    Regards,
    Ajay

  • How to create new line item in credit memo request in rebate settlement

    HI friends,
                 I need aimmediate help on following.
    Requirenment is for given agreement all invoices for that needs to be retrieved. In those invoices we need to check the tax code or tax city for all invoices. If all are same then do nothing.
               But if any of these 2 fields are different in all retrieved invoices, then we need to sum up the qty for all invoices having same tax code/city & like wise ned to create a credit memo request which will have one line item for each tax code/city.
    Example:
    Agreement 9999 with the relevant sales volume:
    Invoice 1: Material A, tax key X, quantity 1 kg
    Invoice 2: Material B, tax key X, quantity 2 kg
    Invioce 3: Material C, tax key Z, quantity 4 kg
    The credit memo request for agreement 9999 should look as such:
    Thanks & regards,
    Abhijeet.
    Item line 1: SETTLEMENT MATERIAL, tax key X, 3 kg
    Item line 2: SETTLEMENT MATERIAL, tax key Z, 4 kg
    Please help me . I am not getting the user exit / badi for this development.
    Please let me know if any one of you know from where to do this?

    Hi Vinod,
    The relationship with main item is stored with CRMD_ORDERADM_I- Parent.
    You need to pass the guid of main item to orderadm_i-parent. This will keep the relationship with main item.
    Thanks
    Ajay

  • Commitment Line Item report - BE and Settlement Unit issue

    Dear experts,
    Request your kind help.
    This is with respect to viewing the commitment line item report in ECC 6 for RE-FX master data objects. There are two scenarios.
    Scenario 1
    Purchase requisition (PR) is created with a business entity (BE) as an Account Assignment object. After the PR is released the same is used to create a Purchase Order (PO). After the PO has been successfully created, I am running the Commitment Line Item report (REISCOLIBD) giving the BE number as a search parameter. The report shows perfectly the PO and the amount of commitment.
    Scenario 2
    Purchase requisition (PR) is created with a BE as a Account Assignment object. Further to that under the Settlement section, inside the RE Obj box I am also specifying the Service Charge Key, the Settlement Unit and the Ref Date. After the PR is released the same is used to create a Purchase Order (PO). After the PO has been successfully created, I am running the Commitment Line Item report (REISCOLIBD), again by mentioning only the BE number as the input parameter. This time the report does not show the PO at all under commitment line items and instead gives the message "no line items were selected". But here is the catch. When I am running the transaction KSB2 and I am clickng on 'further selection criteria' and then 'Ref Doc num' and then typing the PO number and then running the report, it shows the result perfectly.
    Can someone please tell me why in the second scenario, the transaction REISCOLIBD is failing to capture the data related to commitment line items?
    Please refer to Note 1271310 to see how to adapt the transaction REISCOLIBD to suit the needs for Commitment Line Item report.
    Regards,
    Suvarghya Dutta

    Hello all,
    I have been able to find the answer. As of now Commitment Line Item report for any master data for service charge settlement does not exist and and as such wont be available.
    Kind regards,
    Suvarghya Dutta

  • Line item and summary settlement in AUC

    Hi
    What is the difference between line item and summary settlement with reagrds to AUC,In what cases they are going to be used ,can any one provide me some examples.
    Thanks
    Lily

    Hi,
    In WBS, there would be n number of line items in the Investment Projects.
    So while doing settlement for those, we can decide whether to do on WBS based or Line items based.
    These settings will be done by CO people.
    Regards,
    Maheswaran.