Link b/w cost center and activity of a WBS

Hi,,
Can anyone let me know how work center and activities of a WBS are linked?
Please let me know ASAP...
Regards,
Balu

I got to know...
Take object id from AFVC for the activities and give it to CRHD to get the cost center

Similar Messages

  • PM Order Confirmation using Personnel's Cost Center and Activity Type

    Hi All,
    Is it possible to have PM Order confirmation (IW41) using Cost Center and Activity type from Personnel instead of default from Work Center?  If it is, can it be done with some configuration or user exit?  Please advise.  Thank you.
    Dai

    Hi friend,
    Order confirmation will be done for order operations.While doing confirmation we post the actual work done by the repective work center and respective activity type assigned to the same workcenter.
    But these activity types are assigned to cost center for cost calculation.confirming the respective operation in maintenance order through workcenters gives the report of planned work and actual work done by the respective workcenter.
    We cannot confirm the operation using costcenter and activity type directly through transaction IW41.
    If you want to develop new confirmation screen and making confirmation of the respective order operation with only costcenter and activity type fields, you can do it .
    Regards,
    Pardhreddyc
    Edited by: Pardhreddyc on May 17, 2011 12:45 PM

  • What is Cost Center and Activity type

    Can any one make me understand Conseptually, what is Cost Center and Activity Type

    <b>Cost Center:</b>A cost centers is an organizational unit within a controlling area that represents a clearly delimited area of responsibility where costs are monitored against a budget.
    Cost centers represent areas of responsibility (management areas) that generate and influence costs.
    Cost centers are the locations at which the costs are incurred
    <b>Activity types</b> describe activities produced by a cost center. They are measured in units of time or quantity. Activity quantities are valuated using a price.
    For example: the maintenance department provides maintenance service at a labor hourly rate of SAR 2000 or USD 1000.
    When the activities produced by a cost center are used by other cost centers, orders or projects, this means that the resources of the sending cost center are being used by the receiver objects.
    By recording the planned and actual quantities consumed, you reallocate cost incurred on the sender into the receivers.
    Activity Types can be grouped to facilitate reporting and cost allocation.
    Hope it clears your basic doubt on Cost center and Activity type
    Assign points if helpful.
    Regards,
    NareN.

  • Cost center and activity type

    Hi,
    how can I link a cost center to an activity type ?
    Regards

    Hi..
      You can defined a activity type to a cost centre category not a particular cost centre.
      Suppose you have one activity 99xxxx you can defined it to cost centres cat "P" for prod
      you can defined it in KL01 activity master creation.
      If you want to assign one specific activity to be used for a particular cost centre then creat the cost centre under spl cat and creat master data for activity type for that cat.
    kkumar
    Edited by: kkbdsp on Mar 29, 2011 10:03 AM

  • Link for Cost Center And Work Center.

    Dear Experts,
    Can you Provide me the Link for Cost Center And Work Center.
    Regads,
    Jyoshna

    Dear Experts,
    I got the answer for the Link Between Cost Center And Work Center.
    By using CR03   T Code we can see the Display Work Center : Cost Center Assignment Screen will appear.
    we need to select the costing tab, We can find Cost Center .
    Thanks & Regards
    Jyoshna

  • Cost center and profit center linked to GL account

    Hi All
    I am obtaining the carry forward balance for the fiscal year from the table
    GLT0 but I also need the cost center and profit center details for the GL account,
    which I am unable to get from either GLT0 or GLTPC or GLT1 tables.
    Is there any other way out. Please suggest!
    Regards
    Ankit

    Hi,
    Hope OKB9-Account Assignment will resolve this issue.
    There you have the assignments.
    Regards
    A
    Assign points if useful

  • COST CENTER AND PC BALANCES

    Hi all
    In which table balances(total) of the cost center and profit center's stored?
    Regards
    Hari

    Eli,
    Thanks for reply,
    If i have activated NEW GL, any other tables get update in CC or PC balances?
    Like we have GLT0 and FAGLFLEXT in FI.
    Regards
    Hari P
    Edited by: Hari Peddi on Jun 24, 2009 3:10 PM

  • Cost center and Cost element.

    Hi all,
    I am in an urgent need to understand the relation between cost center and cost element. Please provide me with their individual information as well as the link they share. An existing relationship table between the two, if any, ...then plz mention.
    Thanks & Regards,
    Naresh

    Cost Element: cost element is an individual which carry cost like salaries, wages, power expenses, etc.. These Cost Elements are Two types
    1. Primary Cost Element
    2. Secondary Cost Elements
    Primary Cost Element will carry cost form FI to CO (Cost Centers, Internal Orders, Cost Objects, etc…)
    Seconday Cost Elements carry cost with in CO to different Cost Centers, Internal Orders, Cost Objects, etc…
    Cost Center: Cost Center is an individual which contain collection of costs. For example “Admin is a cost center, it contain costs like Salaries, Power, Rent, Stationary etc,
    With this following report you can retrieve  cost elements given a cost center “controlling – cost center accounting – information systems – reports for cost center accounting – plan/actual comparisons  ”
    Thank you

  • Cost Center and Profit Center Planning

    Hi,
    I have one  Co issue.  Pls Suggest me the wiseful solution.
    Cost Center and Profit Center Planning.
    For F-2008 Planning  data they have updated in the month of Aug, 07 for Profit and Loss Items and they have revised the plan data of some cost elements in the month of oct, 2007 (say 5% Increas).  when comparing the cost center report to profit center report, both are not matching.  the reason when i see and reconcile the document nos and values in between cost center and profit center reports  i found out that there are some documents are missing in the profit center report. 
    wherever plan data had revised e.g for cost element Salaries they have updated 100000 Planning cost in the month of Aug, 07.  In the month of Oct, 07 increased 5% i.e.5000. In cost center line items details i found 2 documents for Rs.100000/- and Rs.5000/-  But in Profit Center Line Items i am getting only Rs.5000/- Value Document.
    Note.  As and when KP06 Plan data has been updated Profit Center line items are generating.  It is not necessary to run any programme inorder to transfer Plan Data from cost center to profit center.
    Observations From My Side:-
    I tried to run the transaction code 1ke0. i have selected the cost object is Cost Center, version and had given Cost Center Parameter in development and quality clients and executed the same.By this time already existing data either deleting/ riversing and creating new documents fully except manually changed data in profit center through 7ke1.
    My Question is
    1.Upto what extent it will work.
    2.will it be possible to transfer data from cost center to profit center only missing documents which are available in cost center, without disturbing of existing data in profit center.
    3.suppose if i done this activity, there are some data which was already transferred from other cost objects like internatl orders & wbs elements to Profit Center. will the data get disturbed (deleted/riversed).
    Pls suggest me the wiseful way to solve the

    Hi
    Try This
    BAPI_COSTCENTER_CREATEMULTIPLE
    BAPI_COSTCENTERGROUP_CREATE
    BAPI_PROFITCENTER_CREATE
    BAPI_PROFITCENTERGRP_CREATE.
    Regards,
    V.balaji
    Reward if usefull

  • Blocking of Cost centre and activity type

    Dear all,
    Please tell me how to block cost centres and activity types which will no longer be used
    best rgds,
    Manoj

    Hi,
    There are two ways .
    If you wish to use the cost center number for any other cost center , then you need to delete the cost center by KS04 & you need to mention the future period for which the same should deleted, normally, starting would be 1st day of next year to 31.12.9999
    Keep in mind, cost center can only be deleted , if no data (Actual/Plan/reversal) is posted in it. You may do it , before starting next year's budget processing.
    If you wish to just block the same , lock Actual primary/Secondary & Plan primary/Secondary in the control tab.
    Regards,
    Deepak Kolwankar

  • Link between Material, Cost center to Work Center.

    Hi Experts,
    Can you provide me the following.
    Link between the material and work center.
    Link between Cost center and Work Center.
    Thanks in advance.
    Jyoshna.

    Extend the cost center validity from 01.01.2008, there won't be any harm. It may take from the beginning of the calendar year.

  • IW41 using HR data (cost centre and activity type)

    Hi all,
    Does anyone know the steps required to make IW41 determine the Cost Centre and Activity Type from the HR master?
    We can change the Activity Type by user-exit CONFPM04, but not the Cost Centre.
    Also posted [here|http://www.sapfans.com/forums/viewtopic.php?f=7&t=329923].
    PeteA

    Hi Pete,
    Which cost center field are you using? SKOSTL (sender cost center) should be changeable in export structure AFRUD_EXP. It is this field that is written to the AFRU table (not KOSTL). I did a quick check through debug and it looks possible to set a value in the exit that gets written to AFRU-SKOSTL.
    -Paul

  • CO, which table decribes "cost center" and "cost center group"?

    Hello experts,
    now I have the transaction KP06. Maybe through customizing the user has built a "cost center group" for some "cost center".
    In which table can I find out the relationship between the "cost center" and "cost center group" ?
    Thanks.
    RD
    Edited by: Marching Dai on Jun 16, 2008 2:05 PM

    Hi Arun,
    Please check this link
    http://www.erpgenie.com/abap/tables_fi.htm
    Please check CKPE --->CO-PC Cost Object Hierarchy: Individual Objects
    CSKA Cost Elements (Data Dependent on Chart of Accounts)
    CSKB Cost Elements (Data Dependent on Controlling Area)
    CSKR Resource master record
    CSKS Cost Center Master Data
    Best regards,

  • Creat Cost center assig  activity type, cost center need to be tras to COPA

    Dear All
    I have created a Cost Center, and Assigned  Activity Type by KP26
    Now this Cost Center need to be transported to COPA
    Plz let me know the procedure what are the steps need to be followed.
    With Regards,
    kamal

    if you want to run an assessment of cost centers to CO-PA, you should create and run a cycle in KEU5.
    Dude
    I have gone to this particular transaction code, I have given period from
    1 to 12 and fil year 2007
    and given test run,
    and given Detal list
    its asking me the cycle , and date
    where i  there is no cycle being defined and date given as 22.02.2008
    Its throughing the error msg  cycle has not been created.
    With Regards,
    kamal

  • Find department from cost center and position

    Hello Experts,
    I have a reqmnt for client, I am producing a report in which i need to find out the department using cost center or position, now i am confused wat department is, does deparment mean org unit or its differnt, where wud be the relation stored between cost center and the department?
    Please advise,
    Thanks

    Hi,
    Yes. department means Org unit. You can create the relationship between the cost center and Org unit in the Activity Allocation infortype IT1008.
    I hope you got the solution same like this. If something different, would you mind to share.
    Good Luck
    Om