Link between schedule Line Number and Delivery

Is there a link between Schedule line Number and Delivery number ?
Eg. Line item 10 with quantity 100. 
has 5 schedule lines..with 5 different delivery dates.
1 .  quanity 40
2.   quantity 30
3.   quantity 20
4.   quanity  6
5    quantity  4
For schedule line 1, 2 deliveries were created,
one      with quantity 20
another with quantity 15
quantity 5 is still not delivered.
also schedule lines 2,3,4 and 5 are fully delivered.
Is there any table, FM etc in SAP which will give me the link between the schedule line and delivery number ?
Total deliveries created : 6. - But which delivery corresponds to which schedule line ?
Please dont tell me to look VGBEL and VGPOS.. that will just give line item number 10.. I need to get the schedule line number.
Also, RV_SCHEDULE_CHECK_DELIVERIES --> will give me the delivered quantity against each schedule line.
My purpose is to create an ontime delivery report .
a report which list each schedule lines, and tell, how many shipments were late/ontime/early etc..
and for Late ones, how many days late has to be found.
this is where i need the delivery.
No. Of days Late = Actual GI Date - Planned GI Date.
Actual GI date is in the delivery.
Any suggestions ?
Thank you in advance.

Hi,
Check in the below link.
relation between VBEP-ETENR and LIKP-VBELN
Thanks,
Sree.

Similar Messages

  • What is the direct link between Schedule Line item and Delivery line item?

    Hi SAP SD Gurus,
    The question is simple.  I would like to calculate the Open order quantity for a particular month based on the Schedule Line Date.
    I am taking all the Schedule lines falling below the running date of the month and sum up that and look for the deliveries happened for that Schedule lines.
    I am unable to link that Schedule line with that Delivery line item.
    The only link is Schedule Line Number in VBEP table which is not available in LIPS.  I would like sum up the Schdule line Quantities and Subtract the sum of the Delivery quantities which will give me the Open orders for the particular day of the month.
    Can anyone help me to link this VBEP table to LIPS table to connect the Schedule line number with the Delivery line item?
    Thanks in advance for your help..
    Augustine

    Anuj,
    I am aware of the Functional Modules. 
    I wanted to know for this Schedule Line, this is Delivery document created.
    Where in SAP through Tables it is linked?  Because, I need to source the Tables to calulate the open orders by way of external report through Business Object.
    The table link from VBEP to LIPS is not directly linked.  It is linked from Sales order line item level.  Because we are capturing all the Sales order Line tiems through the Delivery Status which is not equalled to C. But if there are partial deliveries against the Scheuld Line item level, we need to identify.  The only common joint should be Scheldule line number which is not available in LIPS.
    If we are developing report inside SAP, we can use the said Functional Modules to capture through Structures VBEPD.  Since it is a external reporting , we need to give correct tables and the joints.  Hence I am looking for any other way to solve this.
    Thanks
    Augustine Ponraj

  • Link between Schedule lines and delivery quantity

    Hi all,
    At the item level in a sales order, can anyone tell me the link between schedule line data and delivered quantity.
    Schedule line data can be found in VBEP and delivery qty can be found in LIPS. But I want the link between the two. For which partcular date in the schedule line item the delivery qty is displayed.
    Thanks in advance.

    Hi Amol and Rahul,
    Actually I dont want the link between sale order and delivery, I want the link between schedule line dates and delivery qty.
    Hope I am clear.
    Thanks in advance.
    Edited by: Rajini R M on Sep 11, 2008 6:12 AM

  • Link between Invoice verifycation number and Accounting Document number

    Dear All
                   I want the Link between invoice verifycation number (MIRO) an accounting document number the same MIRO. in which table the both two numbers avilable.
    How can identify. can any one tell me the table name for this
    Regards
    Kumar.

    Hi..
    What is the link or join condition for these two tables
    BKPF and RBKP. and RSEG and BSEG.
    In this i want to Accounting document number and invoice verifycation number in a single report.
    Regards
    Kumar

  • What is the link between schedule lines and delivery document item level

    Can any one please explain me what is the link between the schedule lines of the order/scheduling agreement and the item level of the delivery.
    Is there any link between VBEP and LIPS ?

    Hi
    Most of the item level data in delivery doc is copied from Schedlue lines in Sales order for eg delivery date
    So u may say that schedule line in sales order becomes the line item in Subsequent doc that is in Delivery doc .
    The table u are talking about i.e VBEP is related to sales doc and it contain data for Schedule line in sales order and the other table i.e LIPS give the delivry doc related data at item level.
    Hope this help

  • Schedule line category and item category

    Hi all,
    Can some body explain what is the use and differences between Schedule line category and item category?
    Where exactly they come into picture when a sales cycle is done? it would be very helpful.
    Thanks in advance.
    Manu

    Hi,
    SCHEDULE LINE CATEGORY:-
    Schedule line Category determines the Schedule lines for the Line item, it will determine whether the Item is relevant for  Delivery or not
    Transfer of Requirements are also controlled
    Availability check at the Sales order is controlled with the Indicator set at SCHEDULE LINES
    For Third Party processing, the Purchase requisition is created based on the Setting at schedule lines
    Together with the ITEM CATEGORY , the schedule lines determine whether the Transaction is Relevant for MRP or not In the Transaction code VOV5
    ITEM CATEGORY:-
    Item category is a significant part in processing the sales document
    Item category determines whether particular item is relevant for Delivery ot not,
    Whether item is relevant for the  Billing
    In Determine the Availability and TOR Item category plays an important role, for example the Availability check at DELIVERY will be taken place based on  the DELIVERY ITEM CATEGORY
    Some Fnctionalities like OUTPUT, TEXT, PARTNER, INCOMPLETION are controlled
    DIP which in the ITEM CATEGORIES is the Main Integration Between SD and PS
    Thanks,
    santosh

  • Table Link for EQUNR (Eqpt Number) and GEWRK (Main Work Center)

    Hello,
    I need to fetch the main work center from equipment master. I need a direct table link between the equipment number and mainwork center. We are getting a link of equipment number (EQUNR) to work center (ARBPL) and a link of work center (ARBPL) to main work center (GEWRK). But the problem with this scenario is - main work center is not getting fetched from equipment master once work center is missing.
    We want a direct link through some table between EQUNR and GEWRK.
    Puneet

    Hi Puneet,
    Appreciate your problem !
    Many a times in such a situation (which I presume exists where no direct link is available between fields); we have 2 clear cut approaches -
    Approach 1:
    Develop a SAP Query, Functional Area/Infoset, and User Group ( using T code :SQ03,SQ02,SQ01 respectively )
    While developing Functional Area feed in these 2 tables (Table 1- equipment number (EQUNR) & work center (ARBPL) and Table 2 - work center (ARBPL) to main work center (GEWRK) with  work center (ARBPL) as the Primary Key- bridge to join these 2 tables.
    In SAP Query Development; you may take Plant as the Selection Field or any other field as per business requirement to make a search in the query.
    Now when you execute this query, you will get a complete Download of (EQUNR),work center (ARBPL)  and main work center (GEWRK) in one table.
    For SAP Query, you may also approach your ABAP Team Member. This is a cleaner approach than the other one.
    Approach 2:
    Take SE16 download of the Table 1 and Table 2 and join them in Excel (using vlookup if required).This approach is however limited to the data volume that you have to process.
    Please let me know, if you get stuck !
    Thanks,
    RAVI.

  • Difference between Scheduling lines and Delivery schedule

    Hi SD Experts
    can u say me the clear difference between Scheduling lines and Delivery schedule.
    where we will maintain deliver schedule. whether delivery schedule is automatically created along scheduling agreements..
    with regards
    James

    Hi James,
    Schedule Lines: Has basically information realted to delivery scheduling in Sales Order level.
    Delivery Scheduling: Is a process using which system will determine what are the different activities which need to be performed and time taken for each activitiy only after which the material can be delivered to the customer.
    Delievry scheduling will be started only from the material availability date i.e., system will first determine the material avail date and then do scheduling. By default Standard SAP system does Backward Scheduling in case material availability falls beyond the required delivery date system will do forward schedluing
    Delivery Scheduling consists of the following Basic activities:
    We give deatils while creating order:
    Order Creation Date
    Required Delivery Date
    Order date - Material availability date - Transportation Planning Date - Loading date - Goods Issue Date - Required Delivery Date
    Time Between GI Date and required Delivery Date is called Transit Time
    Time Between LoadingDate and GI Date is called Loading time
    Time Between Material Availability Date and Loading Date consists of 2 components - Pick / PackTime and Transportation Planning Time
    System has to calculate all this before it determines the confirmed delivery date.
    Give your mail Id I have some Presentation I will send you across.
    REWARD POINTS IF IT HELPS
    Regards
    Srini

  • Link between Contract line and the Billing Plan number

    Hi All,
    I have a requirement which needs a link between the Contract Line item and its Billing Plan Number. I basically have to find out the contracts which have a billing block. So a invoice would not have been created to that line item.
    Please let me know if such a link exists.
    Thanks in advance,
    jr.

    Hello
    In table <b>VBKD </b>(Sales Document: Business Data) you will find the link between the contract (VBELN) and the billing plan (FPLNR). If POSNR = '000000' then this is the billing plan of the contract header.
    The billing block can be found in VBAK-FAKSK.
    Finally, billing plan details can be found in table FPLA. If FPLA-RFPLN is filled then the item billing plan is linked to the header billing plan.
    Regards
      Uwe

  • Delivery schedule line number in make to order

    Hi all,
    i am doing make to order scenario with 20 strategy group. In sales order we r defining the different delivery schedule lines.when i run the MRP and getting the plan orders for all the FG material and semifinished material, the sale order number and sale order item number is getting updated in production order . Beside these two , delivery schedule line number is not populated and delivery date is not picking correctly in production order.
    please give your valuable suggestion .
    i would be highly thankful to u
    regards
    piyush

    Hi
    When you do the MRP Run at MD02, maintain the Delivery Schedules as 3 (schedule lines), so when ever you do the MRP Run, it will run along with the delievry date.
    reward if it helps
    Regards
    Prasanna R

  • Delivery schedule line number in sales order is not populated in production

    Hi all,
    i am doing make to order scenario with 20 strategy group. In sales order we r defining the different delivery schedule lines.when i run the MRP and getting the plan orders for all the FG material and semifinished material, the sale order number and sale order item number is getting updated in production order . Beside these two , delivery schedule line number is not populated in production order.
    please give your valuable suggestion .
    i would be highly thankful to u
    Will reward points.
    Regards
    Kumaraguru

    Hi Kumar,
    Some changes done in your PRD server.If yes then contact abap consultant regarding the same.
    Because these type of problem comes when you do transport or changes done in the system.
    Regards,
    Anil

  • Delivery schedule line number in sales order is not populated  in productio

    Hi all,
    i am doing make to order scenario with 20 strategy group. In sales order we r defining the different delivery schedule lines.when i run the MRP and getting the plan orders for all the FG material and semifinished material, the sale order number and sale order item number is getting updated in production order . Beside these two , delivery schedule line number is not populated in production order.
    please give your valuable suggestion .
    i would be highly thankful to u
    Regards
    Kumaraguru

    Hi Kumar,
    Some changes done in your PRD server.If yes then contact abap consultant regarding the same.
    Because these type of problem comes when you do transport or changes done in the system.
    Regards,
    Anil

  • Technical link between a PM order and its operations (routing number)

    Hi all,
    I would like to know how to make link between a PM order and its routing number for operations in the order (field AUFPL) ?
    Thank you.
    Regards.
    Laurent.

    Hi again,
    I just found function module CO_DB_HEADER_READ.
    With Order Number as import parameter you got in export parameter CAUFWA value AUFPL.
    Then with +AFV+* tables, you have operations data.
    Regards.
    Laurent.

  • How do i remove the link between my apple ID and my mobile number?

    i decided to move away from iPhone a couple of days ago as a result of renewing my contract. When I got my new phone, I factory re-set it and handed it in to my network provider as part of a recycling scheme. Since getting my new phone, when people send me texts they are still sending as iMessages. I have logged onto my iTunes and removed my iPhone from the account but still nothing. How do I completely remove the link between my mobile nuber and iMessenger?

    Contact Apple support to deactivated iMessage: https://www.apple.com/support/appleid/contact/

  • Schedule line number determination - Schedule line category CP(MRP)

    Hello All,
    I want to know on what basis schedule line numbers getting determined.
    Schedule line category: CP-MRP
    Sales order line items getting confirmed based on the Planned order--> production order created through MRP run.
    I have created sales order line item 1 with 100 quantities. for example I created today. RDD also today.
    3 production order created.
    Those production orders confirmation date as below.
    Production order 1 - 60 quantities - 14.04.2014
    Production order 2 - 30 quantities - 16.04.2014
    Production order 3: 10 quantities - 18.02.2014.
    There are four schedule lines for the line item 1.
    All the 4 lines showed as per the confirmation date order.
    But the schedule line numbers are not as per the above order.
    For example,
    Schedule line number   ----- delivery date ----- Confirmed qty
    1.                                         09.04.2014            0
    3.                                         14.04.2014            60
    2                                          16.04.2014           30
    4                                          18.04.2014            10
    On what basis this schedule numbers getting determined? Is there any standard procedure ?
    Why schedule line numbers not inline with the confirmed date?
    Let me know if you need more information.
    Thank you.
    Regards,
    Rakkimuthu C

    Hi,
    Schedule line number is the number that uniquely identifies the schedule line .
    Use When an item has more than one schedule line, the system automatically assigns a unique number to each line. The number is displayed in the details screens for schedule lines.
    Note The schedule line number serves internal purposes and does not, for example, determine the sequence of schedule lines in the overview screen. The schedule lines on the overview screen are sorted by date.
    The schedule line number will get created automatically by the system. I hope this will clarify your doubt. Thanking you.

Maybe you are looking for

  • Is it possible to set trackmarks on a mix without playback-interruption?

    I´ve mixed my favourite songs in waveburner and now have a mix of one hour with nice crossfades between the single tracks. Only problem: I cannot switch between the tracks on my Ipod, because the whole mix is just one mp3. That´s why I´m wondering, i

  • Substitution variable in Calculation manager

    Hi, In calc manager there are two types of variable 1. replacement 2. execution. I want to know that is there any connection between substitution variable in Essbase and these variable? In a document, I saw that "Planning and Essbase users only: If y

  • Where do I find Maverick update?

    I neglected to upgrade my iMac to Maverick and now I want to install some other updates and can't because I didn't install Maverick first. Where can I find it to install it?

  • Firefox will not open on my Mac - it always worked before

    Firefox will not open today at all. It is sure, it is afflicted with Norton Firewall, Antivirus, etc. and I have MANY bookmarks. OS X 10.9.5. This is on Safari.

  • Fan stop working

    I have a Toshiba L655-s5198. The fan has stop spinning and then have the pop up saying st and I have already clean the heatsink (though since it completely close, there is minimal dust). it will every now and then spin but like roughly less than once