Linking of vendor payments to Purchase order

Hi
My requirement is that  i want to link payments ( vendor ) to PO i.e how much payment has been made to particular vendor for a particular vendor .
I have placed several orders to a single vendor for the supply of different material.
In my sceneraio i am paying the advances to vendor  against thes PO.
I wanna to link these vendor payment to PO so that i will bw in postion to know what is my payment done against PO.
Waiting for prompt resonse
Thanks and regards

Hi,
Linking payment to PO is not available in SAP standard reports .If down payment is released in F-48 where in the user put the PO No in the purch doc field it will reflect in the status tab of the PO header.For viewing other payments against the PO one has to drill down the PO history tab and clickthe invoice document .Than click the accounting document no. and see the document overview.Than select the vendor code click the details .Here look in the field Clearing .If there is a clearing document number and date it implies payment is made to the vendor.This is a clumsy way however.Otherwise a custom report need to be developed for this.
Dhruba

Similar Messages

  • Link between vendor number in purchase order and supplying plant (Sales O.)

    Hi All
    Please could you advise, what settings control the following:
    1. Purchase order created for vendor A. (vendor- is internal supplier within same company in SAP, but different company code).
    2. Sales order automatically created on vendors side, plant B.
    Question is where is the link between vendor number (A) and supplying plant name (B):
    How SAP identifies, what plant sales order (for created purchase order) should be generated at?
    Thanks!
    Regards, Andrey

    Hi,
    Click the below link for more infromation about SD & MM integration.
    http://sap-img.com/sap-sd/link-between-sap-sd-mm-and-fi.htm
    regards,
    Venkatesan Anandan

  • Vendor outstanding against Purchase order

    Hi Gurus,
                      Is there any standard report in SAP where we can get vendor outstanding against purchase order . (Purchase order made,miro also made , but payment is still due ). How can we find or track the pending payment of vendor against which purchase order.

    Hi
    No standard report displays your requirement.
    Prepare a Functional Specification(FS) as per your requirement and tell your ABAP Guy to prepare a Customized Report.
    Regards
    Venkat

  • Post vendor Invoice without Purchase order.

    Hi all
    good afternoon
    how can i post vendor Invoice without Purchase order.
    And any option
    Regards
    Manju

    Hi,
    Use following transactions to do so;
    1. MIGO - Goods Receipt > Others
    Here use movement type as "501" and enter material, vendor, quantity, Plant, storage location, etc... manually and post the material document.
    Here following A/c entry will appear;
    (BSX) Stock Account - Dr
    (GBB-ZOB) Expense A/c - Cr
    2. FB60 - Post Vendor Invoice
    Here following A/c entry will appear;
    Vendor Account - Cr
    Expense A/c - Dr
    3. F-53 - Post Payment w.r.t. the Invoice posted in step2.
    Here following A/c entry will appear;
    Vendor Account - Dr
    Bank Account - Cr
    Note: - If you don't want to carry out inventory transactions then follow only steps 2 & 3.

  • Down payment against Purchase order

    Hi SAP GURU
    i have one queries regarding down payment made against asset puchase order
    I created one asset code, create the PO with accoun assignment categories A, made a advance payment against reference to this PO no .
    when i enter the po number in purchase document field, immediatly asset number coming and showing error message
    You cannot use this transaction type to post to this asset
    Message no. AA834
    Diagnosis
    The transaction type entered belongs to transaction type group 15. According to the specifications for this transaction type group, posting with transactions types belonging to this group are only allowed in specific asset classes (for example, asset classes for assets under construction).
    The asset to which you are posting belongs to class 9000 (chart of depreciation SHV). You cannot post to this class using the transaction type you have entered.
    Procedure
    Check the asset number entered. You may want to allow posting with this transaction type group for the asset class of the asset.
    Can any body suggest what is the right way for the whole scenarion , or i am making some mistake .
    points will be awarded for useful answers
    with regards
    sai krishna

    last week i also faced this problem.
    Please refer sap note number 310368 valuated goods receipt paragraph and they have clearly mentioned about making down payments against asset purchase order without getting debited to asset account.
    You have to make F5 378 message number to be a warning message instead of error message and you have to suppress asset related settings in OB41 posting keys 29 and 39. Posting key 39 is useful when you have down payment request.
    If you have done this, then it will show only warning message during down payment that "purchase order is related to asset" and it will not be debited to asset account. Also after following the above steps, it is not necessary for you to give Acquisition: down payments G/L and Down payment clearing G/L in AO90 transaction code.

  • Advance payment against Purchase order/Work Order: F-47

    Hi SAP Gurus,
    Our Client's requirement is as follows u2013
    Advance payment against Purchase order/Work Order:
    1. Advance should be PO/WO wise & not item wise.
    2. Advance should not exceed total PO/WO value.
    3. Advance against PO should include taxes & conditions maintained in PO/WO
    When I put the purchase order number along with the item number, it is taking into account the basic price for that specific item. This amount is excluding Tax.
    Actually the advance is given against the Purchase Order. So whether it is possible to
    1. Remove the mandatory filed of  Item number against the PO?
    2. Whether the amount of the advance should be inclusive of the Tax?
    Regards,
    Amit

    Amit kulkarni,
    For this requirement you have to do validation of the amount field for advance payment againest PO.
    i thiought this is only way to get your requirement
    May be this information is useful to you
    Regards
    Surya

  • Linking document info record and purchase order

    Hi all,
    I hope that someone can help me because I'm having a problem with creating links between document info records and purchase orders.
    By default in SAP I can create links between document info record and purchase order ITEMS! When I create that link, I can see it in document info record under Object links tab, but when I double click on the number of purchase order nothing happens (I expected that this purchase order will open).
    Why is that so?
    Why can't I access purchase order from document info record even though the link exists?
    The other question is about creating object links to purchase orders, not purchase order items! Is it possible to link document info record with purchase order?
    I would appreciate quick answer because we're in the middle of a project and we're stuck with that problem.
    Thanks!

    Hi Karlo,
             As you mentioned, object links could be linked to Purchase order items. In customisation you maintain these entries under the node SPRO > Cross Application Components> Document Management--> Control Data --> Define Document Types --> Define Object Links.
    There are many links in the standard system (possible entries).
    The system automatically determines the screen number (dialog box) where the key data for the object is maintained for document maintenance.
    You can check the screens when the screen entry is missing or contains errors by doing the following:
    Start the Object Navigator and display the objects for the development class  CV.
    Expand the function group 130. The structure nodescreens lista all screens that can be used for object links.
    You can make an object link to SAP objects that are not shown in the possible entries list. To do this, proceed as follows:
    In the standard system, there are already two special screens for the module pools SAPLCV130 and SAPLCV140 for the linked SAP object.
    You must create two new screens with the same number for the module pools SAPLCV130 and SAPLCV140 .
    The processing logic must follow that of screen 1204 in program SAPLVC130.
    Create function module OBJECT_CHECK_XXXX (XXXX = object name)
    If the object can be classified, this function module already exists .
    Otherwise copy the function module for linking equipment DOCUMENT_CHECK_EQUI and change it as required for the new object.
    Hope the above instruction helps in solving your problem,
    Sojan
    Note : Award points if you find the information useful

  • MIRO Down Payment for PUrchase order ********* Exist

    Dear all,
    I have made PO with three line items in that third line item i have done the down payment.
    i have made GRN and done Invoice for all the three line items.
    My question user is again doing the miro for the same particular po. Now system throwing a error message saying that
    Down Payment for PUrchase order ********* Exist M8138.
    But my user id i was trying to do the same its not showing anything.
    What could be the reason and SPRO Invoice verification--sytem attribute message i was checking there. It was not maintained this error message How system will bring this message in MIRO.
    Could you pls clarify my doubt.

    Thanks Kunal.
    If duplicate entry exist also why its showing for only one User. Becos my user id its not showing that error message.
    Then above message i have told that i havnt maintained any message M8. But where its picking this error message

  • Vendor postings with purchase order

    hi,
    I am learning SAP Fi/co.I have one doubt .what are steps we have to maintain to post vendor transactions with purchase order.if u have any material about mm plz send to me.

    Commitment
    Definition
    Identifies costs that will be incurred in the future for materials and services that you have requested or ordered. Commitments reserve funds that will become costs at a future date.
    Use
    On the account assignment objects, Commitments Management portrays the cost side of the procurement process for MM Purchasing. The costs incurred are assigned to business objects, such as orders, cost centers, or projects.
    In Commitments Management, you can specify which object the costs are to be assigned to (for example, purchase order costs). In this case, this is known as an Initial Account Assignment.
    Commitments Management distinguishes between three types of commitments, depending on the account assignment object:
    Order Commitment:
    The commitment is initially assigned to an order.
    Cost Center Commitment:
    The commitment is initially assigned to a cost center.
    Project Commitment:
    The commitment is initially assigned to a project, or to a work breakdown structure element.
    For more information, see the SAP Library:
    For Internal Orders
    Financials ® Controlling ® Internal orders ®  Manual Actual Postings On Internal Orders.
    For Cost Center Accounting
    Financials ® Controlling ® Cost Center Accounting ®  Manual Actual Postings.
    For Project System
    Financials ® Controlling ®  Commitments/Actual Updates Of Transaction Data
    Integration
    Commitments occur
    In Purchasing, due to:
    Purchase requisitions (purchase requisition commitment) define the internal requirement for a material or a service. Purchase requisitions have a control function and you change them at any time.
    Purchase orders (purchase order commitment):
    Purchase orders are contractual requests to a vendor, to supply certain goods or services according to the agreed conditions. No short-term, unilateral changes can be made.
    due to funds commitments (commitment for funds commitments):
    - You can use Funds Commitments to reserve funds for costs you are fairly certain to incur, but you cannot yet assign to a specific business transaction (such as, a purchase order or a purchase requisition).
    Regards,
    SUbha

  • Down payment for Purchase order

    Dear Friends
    In my client place Down payment is made as per purchase order Item wise
    How to make down payment on the value of Purchase order not considering the PO item wise?
    The reason why i am asking is Some times if vendor does not do the service or deliver the goods returned, we normally change the PO.
    Your suggestions will be valuable to me
    Regards
    Shamulheq

    Hi,
    You can make down payment through  T.code F-48, while processing the down payment you can enter purchase order line item wise also.
    You have to make it Purchase order field optional entry for Field status group Reconcilation through OBC4.
    Regards,
    Rama Mohan Bangaru

  • Down Payment in Purchase Order

    Hi,
    We can create Down payments with reference to Purchase Order, the same is getting updated in the PO History. Currently we are mentioning the Downpayment requirement to the Vendor as a Text in the Purchase Order.
    Is there any clear method of specifying the down payment to the vendor. I checked in Payment terms, but I failed to find the same. Now if client, wants to clearly specify the down payment in any method apart from specifying in text, then what possibilities exists.
    Thank you in advance.
    Regards,
    Ramakrishna Mangena

    Thank you Utsav,
    Please clarify one point, Once we activate the Installment payment in Payment terms in OBB8, then in OBB9 we need to maintain installment options.
    Now in OBB9, we have both Terms of Payment & Payment Terms. So, here nothing is coming in 'Terms of Payment' as input. Can you please clarify, where from this entry will be taken and also, once we add the installment details here, will the details be displayed in Purchase Order.
    Thank you,
    Best Regards,
    Ramakrishna Mangena

  • How to default Vendor Text into Purchase Order

    Good morning! I'd like to have the text I add for the Purchasing Memo on the Vendor show up as Header Text on the Purchase Order. I have setup text on a Vendor using Extras>Texts and then adding information in for the Purchasing Memo. I've heard about 'Copying Rules' but I can't seem to get it to work. Would anyone have notes or a link that would show me how to set this up? I appreciate it!

    Hello
    In case you are working already on ERP 6.0 you should have a look at BAdI ME_PROCESS_PO_CUST, interface methods CHECK or CLOSE depending on your requirements.
    Regards
    Uwe

  • Payment terms - Purchase order

    Hi,
    We have a business requirement, where we are maintaining different payment terms for different company code in vendor master.
    I understand that the payment terms in the purchase org view of the vendor master takes precedence over those at the company code level during the creation of Purchase order and the payment terms of the company code level is accessed when processing an invoice NOT associated with a Purchase order.
    However, business wants to derive the payment terms from company code data of vendor master and not from purchasing view.
    Please let me know the use exit, which can be used to achieve this requirement.
    Regards,
    AG

    Hi
    Not every vendor with purchasing org data needs company code data. Not every vendor with company code data needs purchasing data.
    The payment terms at company code level are used if you post non-PO related invoices with FI transactions.
    Vendor Master Data Management
    Copy function for "payment terms"
    Payment terms in vendor  Master
    thanks..

  • Error message when vendor select in Purchase Order

    Dear Frnds,
    I uploaded Supplier master data in the sap b 1 system, when i select vendor from purchase order it sh
    owing error message  "no maching record found (CRD1) (ODBC-2028) (message 131-138)"
    thanks
    srikanth

    From this link https://websmp202.sap-ag.de/notes  you will reach the Notes Search Page where you will enter the Number in the click >>
    Try this first, incase you don't get there I have pasted the note below for you immediate reference.
    Summary
    Symptom
    Import or create Business Partner addresses via DTW or DI API
    Other terms
    Business Partners, Addresses, Bill To, Ship To, default
    Reason and Prerequisites
    Need for information
    Solution
    The correct way to use the BP header and addresses file in DTW is
    as follows:
    The BP header file in DTW should not be used for importing addresses.
    The Default Ship to and Default Bill to columns in the header file are
    only used for setting which address is default and not for importing
    new addresses.
    In these columns you use the address name given in the BPAddresses
    import file.
    Always use the Addresses file for importing BP addresses.
    EG: Create a BP called TestBP and give it 3 addresses in the addresses
    file 1 bill to (Bill1) and 2 ship to (Ship1 and Ship2),
    then using the header to set Ship2 as default.
    See my import files attached to this note.
    Creating Addresses via DI API:
    The BillToDefault and oBusinessPartner.ShipToDefault properties of the
    Business Partners Object:  Again these are only to be used to set the Default.  To create BP addresses use the BPaddresses Object.
    eg: oBP.Addresses.AddressName = "TestBP"

  • Partial Payments on Purchase Orders - IDOC Scenario

    Hi all,
    I have been asked to look into an integration scenario where a purchase order is set up in ECC 6.0 and payments are called off against this over the financial year.
    Payment files are generated in another system and the idea is that we pick up these files with PI and create payment documents in SAP that are associated with this purchase order.
    I have previously used FIDDCP2 to create payment/invoice documents in SAP - but these had no link or association with purchase orders.
    Anyone had this scenario before? Can I use FIDDCP2 to call off payments against a purchase order like this?
    Or are there other, better (easier?) ways to achieve this?
    Advice and thoughts welcome...
    Regards
    Ian

    Hi Ian,
    I guess that if you post this question in an R3/ECC (ABAP) forum you could get more help, because they should know more about Idoc types for different purposes.