List display of planned orders
Hi
List display planned orders is not bringing any material description . Do we have any other standard report to pull the planned order with material description or is their any way to bring the material description in the MD16 screen layout , the chars allowed for the material description is 0 in the layout
Thanks for help
Nic
Hi,
COOIS tick planned order in selection screen and execute.
Even i saw in MD16 you are right the description length is 0 but that description is hidding you can place mouse where the material coloum is ending and drag the coloumn(As we do in excel to make any hidden column visible ) . You will see descrption now.
I hope you got what i mean.
Regards,
Vishal
Edited by: VS on Nov 2, 2009 9:53 AM
Similar Messages
-
Display of planned order after conversion
Hi All,
I have a planned order "XXXX" & I have converted to production order "YYYY". Now I want to display this planned order to view the details inside it's various tabs.
Which Transaction code OR table will give me this?
Regards,
MHPDear Manish,
Once plan order is converted into production order then you cannot get details for that plan order
Either t-code level or table level
All you can get is plan order number
Execute CO03 and go to assigment tabn in filed plan order you can get plan order number
If you have converted plan order to production order
Regards
Madhu -
List of Unfixed planned orders
Hi -
Is there a report in R/3 which lists all the existing unfixed planned orders in the system?
Appreciate your help.
Thanks
VarunVarun,
Please confirm what do you mean by "Unfixed" Planned Orders?? Do you mean "Unfirmed" or NOT FIRMED planned order? If yes, then below information might help you.
I am not aware of any standard R/3 report that can do that. But you can definitely create a SAP Query for PLAF table and use fields AUFFX (Firming indicator for planned order data) and STLFX (Fixing indicator for BOM explosion).
Try and revert back.
Regards,
Swapnil -
Reservation list based on planned order / order( kkf6n)
Hi
How to get the list of reservations based on the planned order / order ( kkf6n ) for 1 year period. i am working in rem process.Dear Raj,
Are you having the planned order for all the products for 1 year period?
In my understanding even if planned order exists this may not be a firmed one and so why do you need the reservation list
alone for all these planned order's?
Check and revert back.
Regards
Mangalraj.S -
List of dependent requirements of planned order for a component
Dear guru ,
I search a list of dependent requirements of planned order for a component
What do you suggest ?
Thanks.Hi Cristano,
Go to MD04 transaction, enter comopenet and plant. Then from the list select the Planned order and click on the Order Report from the bottom tool bar available below the list.
You can see the componets details for that planned order.
Thanks and regards
Murugesan -
Reg. Component list of planned order
Hi All,
My requirement is i need a simple components list of planned order similar to COOIS - Component list, but not with all information.
Only I need the list of components planned order wise with component number, quantity, Sloc, Header material number, Production line and Production start and end dates.
To achieve this I am going for Z report development, I found the BAPI-BAPI_PLANNEDORDER_GET_DETAIL has all information what I need.My question is does this BAPI is fetching the values of component from the reservation table against that planned order number.Meaning does this BAPI output of Components and RESB output for that planned order will be same?
Regards,
MBN.Hi
Yes both results are the same if you check the RESB table with reference to the planned order number for which you have fetched data from BAPI BAPI_PLANNEDORDER_GET_DETAIL, both are the quantities are same, Also you can see the same in MD12/MD13, but when you check the RESB table only input as one of the component assigned in Planned order , then the quantities will differ,
The result will be the same only in case when you execute the data from table RESB with respect to the planned order number( given input in BAPI).
Regards,
Anupam Sharma -
Pick List - Planned Orders in Repetitive Manufacturing
Hi All,
Business Process: Cut Planned orders ( No production line, No Routing, No Work Centers). Production done and then these Planned Orders are backflushed.
Any of you have any idea on how to generate pick list to stage material for these planned orders?
I know that Production orders can easily be configured to print automatic pick lists but not planned orders. I have been working my heart out to find a solution but couldnot.
Thanks in advance!
SivaHi Siva,
I think action control should work good for your scenario,
In customizing SPRO->Production->MRP->Planning->Procurement Proposals->Planned orders->Action for Planned orders--->Define action control.
<b>Define Action Control</b>
In this workstep, you define the actions that are allowed for the action control function and the sequence in which the system is to carry out the actions. An action can be followed by several other actions and it can also be preceded by several actions.
<b>Activities</b>
Define the action control. To do this, define a key and the actions that are allowed and which subsequent actions can follow certain actions.
<b>Example</b>
The key 01 is defined. The following actions are to be allowed for this key
BOME (explode BOM)
NEMA (check material availability without BOM explosion)
PRNT (print component list)
The BOM must always be exploded first. The material availability can only be carried out once the BOM has been exploded. Once the availability check has been carried out, the system should print the component list. The table is then mainatained as follows:
<b>Control Action Target action</b>
01 BOME
01 BOME NEMA
01 NEMA PRNT
The action control what is defined needs to be assigned in Material Master MRP4 View under REM section.
Hope this helps...Reward your points,
Regards,
Prasobh -
Firm Planned order List out side Planning Time Fence
Dear Gurus
I have the following requirement.I need to get the list of Firmed Planned order list for my plant, which are the out side of Planning Time Fence.I tried by md19 but it did not give me any list like that.Any urgent solution is appreciated .
Regards
JiaMy requirement is planned order list beyond the planning time fence.In PLAF table we have option to give the firming indicator YES/NO .But while giving the date rage I have difficuly.We have several material which are planned in various plannig time fence and there is no fixed date range.There may be one material planned 21/04/08 to 25/04/08.At same time other material may be having 30/04/08 to 5/05/08 .So we cant give any fixed date range to segregate the firmed planned order out side the date range.
You soultion is appreciated
Regards
Jia -
To build query related to SNP: Planned Order
Hi,
System: SCM 5.0
Scenario: SO received at plant and planning creates PR against SO at plant and accordingly SNP:Planned Order at Vendor location. If SO is cancelled/deleted (manually), sometime only the PR gets cancelled/deleted (automatically during planning run) but corresponding SNP:Planned Orders still remains at vendor location and so the dependent requirements. PR and Planned Orders are pegged to SO so one-to-one relation is maintained.
I could not find any reason why system is not deleting Planned Order at vendor location despite SO and PR is deleted at plant location. So I am planning to build query where SNP:Planned Orders are not pegged to any PR or SO.
Can anyone help with list of SNP:Planned Order tables so that I can build query around it to identify ghost Planned Orders.
Hope I was clear with my query but let me know if any further information is require.
Thanks and regards,
DevangHI Marius,
Sorry for delay reply.
I was working on on some other more critical issues to business.
Finally we decided to built report to identify obsolete Planned Orders for which PR is not available in ordering plant. I have listed below logic for that report:
Get Location ID from table /SAPAPO/LOC based on Location entered in selection screen
Get PEGIDs from FM /SAPAPO/DM_MATLOC_GET_PEGIDS based on IV_SIMID as 000 and location id from step 1
In FM /SAPAPO/OM_PEG_CAT_GET_ORDERS, use SIMVERSION as 000 and in Import Para IS_GEN_PARAMS insert all PEGIDs from step 2.
From Export Para ET_PEG_INPNODE take From_OrderID and store in internal table.
Execute T.Code /SAPAPO/RRP4 with following selection (Use Selection Variant: OBSOLETE PR and add Location as entered in Selection Screen)
Planning Version: 000
From: Current date – 60 days
To: Current date +180 days
Location: 0000201328
Product: *
Order Type: 1F
6. Compare output of step 4 and step 5 and display result.
From FM /SAPAPO/DM_MATLOC_GET_PEGIDS the output (step 4) will be Order ID (22 characters) while step 5 (T.Code /SAPAPO/RRP4) will give Planned Order number (8 character). I am not sure how to compare Internal Order ID (22 characters) for corresponding Planned Order Nos. (8 characters).
I have not marked your post as correct answer as still need to find answer of above query.
Thank you in advance for your guidance.
Regards,
Devang Shah -
Dear gurus,
Any one can explain what is meant by Scheduled Planned Orders and not scheduled planned orders.
I observe this in T.Code MF51.
SriniHi,
Here is the extract from the help.sap.com.
==========================================================================
Select Only firmed orders if you only want the system to display firmed planned orders and production orders in the list.
Select Only assigned orders if you only want the system to display planned orders and production orders that have been assigned to a production line.
Select Only dispatched orders if you only want the system to display planned orders and production orders that have been dispatched in the capacity planning table.
Select Only scheduled orders if you want the system to display planned orders and production orders that have been scheduled.
==========================================================================
Refer below link for further details.
http://help.sap.com/saphelp_erp60_sp/helpdata/en/8a/a5a7c24adc11d189740000e8322d00/content.htm
Hope this helps..
Regards,
Siva -
How to restrict planned order by production order type
we develop one Z-report which include planned order as well as production .on restriting the output by order type given on selection screen of report, production order can be restricted but it show all the planned order which is to be converted to selected order type production order or not.
is there any suggesion to display that planned order only to the output of report which will convert to the production order of the type given on selection screen of report.
i know that we define prod scehu profile in work sched view of material and in production schedu. profile we define the order type picked while conversion of planned order to production order.but i am not able to connect them by using table...please guideHi,
Could you explain your problem correctly.
regards
mkrk -
How to bring material description in case of planned order in CM25 trnx?
Hi All,
On CM25 for Process Orders, the material description is what is displayed on the bars of work. For Planned orders it displays the planned order number and material desciption filed remains empty. Is this SAP standard behaviour when it comes to planned order in CM25? How do I bring the description as well to Planned Order number#s?
Any pointers would be a great help!!
Thanks,
NitinHi,
Thanks for your reply. My requirement is to display "material description text" in the "Mat description field". This field is already exits in planning table. However i cannot see material description in case of planned order and just see planned order number, material no etx ;but in case of process order, i can see material description text in the same field...
Thanks,
Nitin -
Planned orders table/report
Hi all,
IS there any table/report which lists out the Planned orders and the converter Purchase requisitions from planned orders? I want a report/table which lists out Purchase requisitions and the related Planned orders.
Thanks,
Avani.Hi,
no standard report for your reqirement
pls check planned order table
PLAF - planned order table
once converted planned to pur. req, there is no table to store this converted data
EBAN - Pur. req table
Hope you understand
Regards,
Sankaran -
Planned Order Components Table
I have a question. Is there a table that holds the components of a Planned Order?
When I see the technical data of a component field in MD13 it tells me they are in MDPM, but this is a structure, not a table.
that made me think that perhaps this is being fed directly from the BOM. But when I make a change to the BOM, the components in the planned order are not automatically updated.
So they must be stored somewhere. Anyone knows which table it is?
Otherwise, what FM can I use to fetch them?Fernando,
You can get the components list of a planned order in RESB table for field PLNUM = Planned order number and BDART = SB.
Regards,
Prasobh -
What is the effect of the planned order after it is converted to production
Hello Gurus,
1.There was a planned order with wrong date 2041 instead of 2011
2. plannedorder is already converted to production order and is visble in assignment tab of the production order
3.when I am tryng to display the planned order it gives error planned order is not exists.
4. Production order is already delivered
Now will there be any effect on finanace or any other ,if the planned order was created with wrong date,
can we now change the date of planned order , but it says does not exist as it is already converted to prod order.
Please let me know the implications of wrong date and how we can correct the date from 2041 to 2011
Thanks in Advance
HimakarDear Himakar,
As explained by our forum member,once after the planned order is converted into production order,the entire planned order
details gets deleted from table PLAF and the planned order dates can be changed in the production order and there is no
business impact other than the planned/production/actual dates.
However the planned order no deatils can be checked in the production order.
Regards
Mangalraj.S
Maybe you are looking for
-
I have the above MB in an Emachine. Called there tech support because I want to upgrade to Win 7. Answer "we dont support that" . I have looked on MII's site and cant find any chip set drivers for my MB for Win 7. I have Win 7 installed but do no
-
Hi everyone, I'm trying to create a 8 1/2 by 11 inch landscape document with 7 art boards.. the 8 1/2 by the 11 document I can do no problem. but after that I need to create 7 art boards inside the document.. That I do no know how. They need to be 6"
-
How do I get iTunes U
-
Oracle Enterprise Repository post installation steps failed.
Hi, I was able to install Oracle 11g Express and Weblogic 10.3.6.0 and 11.1.1.6.0 and when try to follow post installation steps to extend a domain installation fails with following steps. Could you please assist me what could i have done wrong or su
-
hi , i have exported the data from one server using script , but i gave the delimeter as comma(,) and now the file is not being loaded in the application . It works fine when i give the tab but its not getting loaded with comma .The size of the expor