i have an issue in the report, the problem is
in the selection screen i have an WBS ELEMENT as an select option(there is no belnr in selection scrren)
for eg- if i enter
COMP CODE = 0010
WBS ELEMNT = 23456
YEAR = 2008.
For the above details there are 2 line items in table for that particular belnr as
BUKRS BELNR YEAR BUZEI WBSELT SHKZG
0010 40000050 2008 001 23456 S
0010 40000050 2008 002 00000 H
there is only one line item for WBS ELEMENT IN BSEG TABLE.
So i am getting debit(SHKZG-S) value but i am not getting credit value if i write the select query as below.
SELECT bukrs
belnr
gjahr
buzei
sgtxt
kostl
aufnr
lifnr
ebeln
projk
FROM bseg
into table gt_bseg
for all entries in i_get
where bukrs eq i_get-bukrs
and belnr eq i_get-belnr
and gjahr eq i_get-ryear
and buzei eq i_get-buzei
and projk in s_projk.
please help how to get both values.help with code
thanks in advance,
one of the friend from SDN gave the following solution to my problem
but here he kept KOART = D, WHEREAS FOR MY CODE OTHERLINEITEM MISSED WOULD BE CREDIT OR DEBIT ONCE IT MAY BE MISSED THE CREDIT LINEITEM OR DEBIT ONE.
LOOP AT GT_BSEG.
select single BELNR KOART WRBTR PROJK FROM BSEG INTO wa_bseg WHERE BELNR = BSEG-BELNR AND KOART = 'D'.
append the values of wa_bseg to it_bseg.
endloop.
i have faced same problem if u observe the table BSEG if KOART value is D , in that line item you cant get the PROJK value so
from above select statemnt u can retrieve that value
finally in it_bseg u can get the lineitems which are emitted by your select query
PLEASE HELP ME
>
sai latha wrote:
> hi
>
> i have an issue in the report, the problem is
> in the selection screen i have an WBS ELEMENT as an select option(there is no belnr in selection scrren)
> for eg- if i enter
> COMP CODE = 0010
> WBS ELEMNT = 23456
> YEAR = 2008.
>
If you're trying to select from BSEG using only these selection criteria, then your query is likely to be very, very slow. Since BSEG is a cluster table and therefore only the key is used for the query, you need to specifiy at least BUKRS and BELNR to get any sort of decent performance.
If I wanted to select using WBS element (or any controlling object) my starting point would be the Controlling tables COEP and COBK, or COVP which is a view of the two; after all, the Controlling tables were set up specifically to deal with this sort of query.
Once you've picked up the line you want with your WBS element selection, you can get any of the other lines on the document by selecting from BSEG using the reference document fields held in the Controlling tables.
Similar Messages
-
Creation of settlement rules for WBS element
Hi,
Iam having problem when creating the settlement rules for WBS elements. The business goes like this.
We have XI interface which creates the Idocs and an inbound program(customized) to process the Idocs. When the Inbound program is run the WBS elements are created and settlement rules are created for the WBS elements. The inbound program is run automatically thru batch job.
First time when the Idocs are processed about 95% of the WBS elements have settlement rules created and for other 5% settlement rules are not created. The Idoc is in status 64. I tried reprocessing the Idoc and then the settlement rules are getting created succussfully. The problem is Iam not able to find why the Inbound program is not processing succusfully when its run first time but works when reprocessed.
I appreciate if anyone can send their views.
Best Regards
SKHi!
You might set the processing to check not only once the relevant IDocs, but more times...
Check out these programs, and set them into a batch job periodically...
RBDMANI2
RBDAPP01
Regards
Tamá -
Hi,
I need to modify the document created using FB01 / MIRO for WBS Element. I could not find any user exit or BADI to do the same. So I tried the BTE 1120... I added a structure to BSEGSUBT to add the WBS Elements... And in the FM for 1120, I am passing the WBS Element to BSEGSUBT-PROJK.
But this data is not getting updated in the document. On further investigation, i discovered that the Internal Table T_ACCIT has the field PS_PSP_PNR and not PROJK and its because of these differences in the name of the fields, i am not able to add the data to ACCIT...
How do i get my data in the document?
Appreciate your help.
Kind Regards,
TanujaHelll T ,
i think in that case ,...make use of Substitutions in Controlling area , in FI area system wont allow to change field values which are not part of its substittion fields.
try GGB1(tcode)--->Cost Account ->line item->create Step -->and make use of Exit Module in order to change value of COBL-PS_PSPNR or something like that.
regards
Prabhu -
Planning Layout for WBS Elements
Any one have any idea how to set up the planning layout for WBS ELEMENTS & COST CENTER?
We are trying to plan for WBS elements and Cost center through CJR2 but I don't have any layout designed for this.
Any ideas or suggestions?I doubt if you can have a single layout for planning both at Cost Centre and WBS level.
But you can create your own layout by copying the standard planning layout under a different name and then change the copy (T code OPO1)
We in our project created a layout with WBS Element (PSPGR) and Cost Element (KAGRU) as Characteristic Values with lead column structure 'Characteristic value and name'.
You then create/assign a Planner Profile>Planning Area>Planning layout using T Code KP34.
Call/change your planner profile (T code KP04) to above before doing the cost planning in CJR2.
Regards
Sreenivas -
Search help for user field for WBS element
Hi,
how can I add a search help to one of the user fields for WBS elements without modification? Is there an exit which I can use? I want to have a search help for field PRPS-USR02.
Thanks for your help.Hi
Create an elementary serach help using the Table USR01 or USR03
see the steps
1) Elementary search helps describe a search path. The elementary search help must define where the data of the hit list should be read from (selection method), how the exchange of values between the screen template and selection method is implemented (interface of the search help) and how the online input help should be defined (online behavior of the search help).
2) Collective search helps combine several elementary search helps. A collective search help thus can offer several alternative search paths.
3)An elementary search help defines the standard flow of an input help.
4) A collective search help combines several elementary search helps. The user can thus choose one of several alternative search paths with a collective search help.
5)A collective search help comprises several elementary search helps. It combines all the search paths that are meaningful for a field.
6)Both elementary search helps and other search helps can be included in a collective search help. If other collective search helps are contained in a collective search help, they are expanded to the level of the elementary search helps when the input help is called.
CREATION:
Go to SE11 Tcode
select search help
give the 'z' search help name and create
select the selection method ur table name eg : 'mara'
dialog module 'display value immediately'.
add the field whatever u want and lpos = 1 and spos = 1 and check import and export parameter.
where left position when displaying and spos = search position
and then save and activate ..
See the links:
http://help.sap.com/saphelp_nw04/helpdata/en/cf/21ee38446011d189700000e8322d00/content.htm
http://help.sap.com/saphelp_nw04/helpdata/en/cf/21ee45446011d189700000e8322d00/content.htm
https://forums.sdn.sap.com/click.jspa?searchID=3173469&messageID=2176485
https://forums.sdn.sap.com/click.jspa?searchID=3173469&messageID=3601619
pls go through this for search help creation
http://help.sap.com/saphelp_nw2004s/helpdata/en/41/f6b237fec48c67e10000009b38f8cf/content.htm
http://help.sap.com/saphelp_nw04/helpdata/en/cf/21ee2b446011d189700000e8322d00/content.htm
Search Help Exits:
Re: dynamic values for search help
Re: Dynamic search help
http://help.sap.com/saphelp_nw04/helpdata/en/cf/21ee52446011d189700000e8322d00/content.htm
http://www.sapdevelopment.co.uk/dictionary/shelp/shelp_exit.htm
https://forums.sdn.sap.com/click.jspa?searchID=4390517&messageID=1712818
Regards
Anji -
Segment for WBS element in Inbound Sales Order Idoc
Hi gurus,
I am trying to create an inbound idoc for sales order ' VA01'. I need to populate WBS element in the item level under Account Assignment Tab. I am using ORDERS05 basic type. Please help to find which segment to use for WBS element. Waiting for your reply. Please help.
Regards,
SatyajitHello,
As far as I know, there is no Segment / Field definition in ORDERS05 for WBS Element as it is not mandatory information to be filled in order for the Sales Order to be Complete. So, you need to create an Extension of the IDoc Type ORDERS05. For your requirement, here is the Approach I have.
1. Create an extension for IDoc Type ORDERS05 to ZORDER05 with a Custom Segment Z1EDP01 in which you'll have the Custom Field Name VBAP-PS_PSP_PNR which is the WBS Element field in VBAP Table.
2. Now, use the Customer Exit EXIT_SAPLVEDA_001 in the Enhancement VEDA0001 in which you can actually populate the Field WBS Element that would be already available in the Inbound IDoc to store it in a Work Area. As you are aware, you'll need to create a Project in CMOD for the same.
3. Export the same to some MEMORY ID 'XXX'.
4. Come back to the Selection Program for ORDER05 which is IDOC_INPUT_ORDERS in which you'll find the below CASE Statement.
CASE xaprau.
WHEN ' '.
PERFORM call_va01_new_orders USING ok.
WHEN 'Q'.
Aufruf Transaktion Auftragerfassung VA01 mit Bezug auf Angebot
call transaction Order Entry VA01 with refer to quote number.
PERFORM call_va01_new_orders_angbt USING ok.
WHEN 'C'.
Aufruf Transaktion Auftragerfassung VA01 mit Bezug auf Kontrakt
call transaction Order Entry VA01 with refer to contract number
PERFORM call_va01_new_orders_contk USING ok.
WHEN 'L'.
5. Now, since our Standard Order Type (VBAK-VBTYP) is 'C',
we'll have to choose the Subroutine for the 'C' Option.
6. In this Subroutine, there is another Subroutine va01_dynpro_kopf_kaufmann_kde2 which is for populating Custom Dynpro Fields for the Sales Order. So, we need to choose the same Subroutine inside which we have to Create an Enhancement Implementation.
7. In this Enhancement Implementation (Implicit), we have to IMPORT the value of the WBS Element which was exported in the Customer Exit.
8. Check if it is initial. If it is not, then Call the Perform as below.
IF NOT WA_Z1EDP01 IS INITIAL. "Checking if the Segment
" is Empty
PERFORM DYNPRO_SETZEN USING 'COBL-PS_POSID' WA_Z1EDP01-ZZWBSELEMENT.
ENDIF.
9. Since the Sales Orders are posting using BDC here, by calling the above Subroutine DYNPRO_xxx, we are appending our Custom Segment / Field value to the BDC_DATA table.
10. In Step 8, I've given the Notation for Work Area. It will also be applicable when there are multiple Line Items. All you have to do is to EXPORT an Internal Table instead of Work Area and use the same here for each Line Item.
11. I've given you above procedure because I've worked on similar requirement in which I had to populate the Special Processing Indicator instead of WBS Element.
Hope it would be helpful for you.
Thanks and Regards,
Venkat Phani Prasad Konduri -
FI posting not allowed for WBS Element
Hi All,
While doing down payment billing I'm getting error that FI posting is not allowed for WBS element. But FI periods are open for all months in 2008.
Please suggest how to resolve this issue.
Regards,
HarishHello
Account assignment
If you want to post actual costs and commitments to a WBS element, you have to indicate that the WBS element is an account assignment element in the WBS. All objects that can be assigned costs and commitments within a project (for example, orders, networks, or purchase orders) can only be assigned to a WBS element if you have set the account assignment indicator for the element.
In Customizing for the Project System, you can set an indicator to specify that costs are planned for all WBS elements or only for specific WBS elements.
Billing
If you want to post revenues to a WBS element, you have to indicate that the WBS element is a billing element in the WBS.
Reg
assign points if useful -
Error when processing asset under construction (AuC) for WBS element message no cj824
Hi,
i am getting error message when i change dates in activities.
Error when processing asset under construction (AuC) for WBS element
Message no. CJ 824
i have checked related post but did not find any solution. also check SAP Note but not related to my issue.
Please guide.
thanks
SunilHi Ken,
Please check below screens:
according to this error message AUC has some missing field or some incorrect value. but when i checked via program RAUNVA00 which will display
Incomplete Assets - Detail List.
but this program does not return any incompleteness.
i found many threads and SAP Not but none of is related to my program. this problem comes when i change dates in activity and save the project.
Please suggest what to do now.
thanks
Sunil -
Autharisation object for project team for WBS element
Hi all
My client requirement is when they allotment project team for WBS element some of the user restrict to delete it from menu tab in CJ20N transaction code and particular user only delete it. could any one guide me under which object i can manage this authorization to restrict the user so that in menu tab delete tab is gray out.
RegardsHi,
Using ACL, you can give four authorizations like 'read', 'write', 'admin' and 'no authorization' for a user for the each element (object) of project.
For a user, you maintain the ACL for the whole hierarchy(inheritance) or for individual element.
You can maintain ACL for user group or for Organization Group instead of users as well.
In the project profile in SPRO, we can see three radio buttons for ACL like 'No ACL', 'ACL (No Inhr.)', 'ACL (with Inh.)'. You choose according to your requirement.
For more details please go through SAP Help. Explained in detail there.
Regards,
Gokul -
User Status Change Log for WBS Element
Hi All,
I have a requirement to capture the user and time when the user status has changed for WBS Element in TCODE CJ20N.
How do I enhance the standard table to add these 2 fields and also which enhancement is used to populate these fields?
Thanks
Davidhi david,
if your looking for status changes in WBS for CJ20N tcode then
have changes documents tick marked in OPSA tcode for a particular project profile and then create project in CJ20N with that project profile and go to that respective WBS and click the blue icon and goto
Extras->changedocuments->All---> here click on all changes or history ... here this should give you required data your looking for ...
regards
pushpa -
Changing Status Profile for WBS Element
Hi Freinds,
How can we change the Status Profile for the WBS Elements.
say for Eg : need to chage status Profile Z0000005 to Z0000008
where they reflect in DB Table JSTO for OBJNR in filed STSMA
Please suggest me the function modules or BAPIs
Thanks in Advance,
Ganeshhi,
try the below given link
[Changing Status Profile for WBS Element|Update WBS element;
hope this helps
Regards
RItesh J -
Internal order creation for wbs element
hi
I want to settle internal order for wbs element ,but while creating internal order in KO01,required Order type type not appearing mean in my company wbs element required for order type PS01,Category -20(network),so for this 20 cat. where should i create internal order.please advise me
thanks
chanduHi,
you can't use the order type related to category is 20, because it will use full only PS. you can create the internal order with category 10 and maintain the settlement rule said that to be settled at WBS element.
Thanks and Regards
Nagaraju SSV -
Functional Area for WBS Element
Hi Friends
While posting Invoices in SRM 7.0 for WBS elements the Functional Area is sometimes picked up from WBS element directly and sometimes from Responsible Cost Center of the WBS.
Also in cases when we have split account assignment with CC and WBS elements then many times only the COST Center Functional Area is passed for all the account assignment split.
E.G. we have 1 line item with 10000 value and Account Assignment is split in 4 parts 1 CC and 3 WBS element. For this functional are of the Cost Center is passed for all four account assignments rather than passing 4 different functional areas based on each cost element.
Can someone help me understand how the standard functionality works or is there any specific condition in which the responsible cost center Functional Area is picked up instead of WBS element Functional Area.
There are some documents where in case of split accounts system is passing separate functional area for each account assignment. So i am not able to conclude what is the standard function to determine Functional Area.
Regards
UshirHi Akash,
The scenario you mentioned is correct it will pick up the CC functional area in case there is no functional are on WBS but in our case that is not the case. For all the WBS we have the functional area maintained but still some times the functional area is picked up from responsible cost center of the WBS.
The problem is we are not able to replicate this in Q or D environment. The documents posted by users in production are pointing to some wrong Functional Area and its not correct.
Regards
Ushir -
Creating a Validation for WBS Element in the Asset Master Record
I would like to know how to create a validation in the AMR for the WBS Element field. I would like to have a particular Business Area when used be required to only use a WBS element that starts with, let's say, AL. Can someone shed some light on how I would set up my check in OACV?
Hello
You can validate or substitute data directly at the input stage. You make the settings for validation and substitution in the Implementation Guide (IMG) for Controlling, under Controlling General ® Account Assignment Logic ® Define Validation or Define Substitution
Substitution and validation are only intended for actual postings
For a complete description of validation and substitution, see the SAP Library under Accounting - FI Financial Accounting ® Special ledger ® Tools ® Validation and Substitution Rules
Coordinate with ABAPer and make settings.
Reg
*assign points if useful -
Very urgent- find parent-child relationship for wbs element
Hi,
There is a certain parent child heirachy in WBS elements.My requiremnet is to delete WBS element depending on certain field , say depending on some ""status"".If the status is active in some or any of the child then I am not suppose to delete its respective parent too. This parent-child relation can have say 5 levels.
For this I require a logic /program which shall maintain the parent reference for that particular child whih I want/ dont want to delete.
I am maintaining bottom- to -top approach.
That is I shall be checking for the status of the lowest level of WBS and then going to the highest.
Please Help!
Kshitijahi you can use following code....
REPORT zpmgmt_rpt_projinfo NO STANDARD PAGE HEADING LINE-SIZE 160.
*& Includes
INCLUDE <icon>.
INCLUDE zdata_declare_n. " include for data declaration
INCLUDE zsubr_n. " include for both subroutines
DATA: gv_index LIKE sy-tabix,
lv_index LIKE sy-tabix,
date_index TYPE sy-tabix.
*& Start of Selection ( Get Data )
START-OF-SELECTION.
For initial display cnt is set to X
IF cnt EQ 'X'.
PERFORM getdata.
CLEAR it_final.
PERFORM hierarchy.
cnt = ''.
ENDIF.
*& Form GETDATA
Fetches the data and logic for T1 and T2
--> p1 text
<-- p2 text
FORM getdata.
Getting project header data
SELECT * FROM proj
INTO CORRESPONDING FIELDS OF TABLE it_proj
WHERE pspid IN so_posid
AND werks IN so_plant
AND stort IN so_loc
AND erdat IN so_date.
IF sy-subrc <> 0.
MESSAGE 'Enter the valid entry' TYPE 'I'.
STOP.
ENDIF.
LOOP AT it_proj.
PROJECT = it_proj-pspid.
Get project & WBS element details
BAPI used gives the output in some specific format
which is used for roll-up logic.
CALL FUNCTION 'BAPI_PROJECT_GETINFO'
EXPORTING
project_definition = project
with_activities = 'X'
IMPORTING
e_project_definition = e_project_definition
TABLES
e_wbs_hierarchie_table = e_wbs_hierarchie_table.
Appending all the projects in the e_wbs.
LOOP AT e_wbs_hierarchie_table.
MOVE-CORRESPONDING e_wbs_hierarchie_table TO e_wbs.
APPEND e_wbs.
CLEAR e_wbs.
ENDLOOP.
CLEAR PROJECT.
ENDLOOP.
SET COUNTRY 'US'.
i_repid = sy-repid.
Getting data into internal tables
Getting project WBS element
SELECT * FROM prps
INTO CORRESPONDING FIELDS OF TABLE it_prps
FOR ALL ENTRIES IN it_proj
WHERE psphi = it_proj-pspnr.
Getting project activities
SELECT * FROM afvc
INTO CORRESPONDING FIELDS OF TABLE it_afvc
FOR ALL ENTRIES IN it_prps
WHERE projn = it_prps-pspnr.
SORT it_afvc BY vornr.
Getting activities start & end dates from AFVV
SELECT * FROM afvv
INTO CORRESPONDING FIELDS OF TABLE it_afvv
FOR ALL ENTRIES IN it_afvc
WHERE aufpl = it_afvc-aufpl
AND aplzl = it_afvc-aplzl.
Getting plant name
SELECT * FROM t001w
INTO CORRESPONDING FIELDS OF TABLE it_t001w
FOR ALL ENTRIES IN it_proj
WHERE werks = it_proj-werks.
Logic for passing data to final internal table
Passing Project master data
READ TABLE it_proj INDEX 1.
IF sy-subrc EQ 0.
CALL FUNCTION 'CONVERSION_EXIT_ABPSN_OUTPUT'
EXPORTING
input = it_proj-pspid
IMPORTING
output = it_proj-pspid.
it_final-posid = it_proj-pspid.
it_final-post1 = it_proj-post1.
APPEND it_final.
CLEAR it_final.
ENDIF.
Passing WBS element to the final internal table IT_FINAL
LOOP AT it_prps.
CALL FUNCTION 'CONVERSION_EXIT_ABPSN_OUTPUT'
EXPORTING
input = it_prps-posid
IMPORTING
output = it_prps-posid.
CLEAR color.
Get WBS element status ans color(T2)from OBJNR
CALL FUNCTION 'ZGET_STATUS_N'
EXPORTING
objnr = it_prps-objnr
IMPORTING
color = color
TABLES
t_status = it_tj30t.
IF color = 'RED'.
it_final-t2 = '@0A@'.
ELSEIF color = 'YELLOW'.
it_final-t2 = '@09@'.
ELSEIF color = 'GREEN'.
it_final-t2 = '@08@'.
ENDIF.
SORT it_tj30t DESCENDING.
Getting User statuses of WBS element at component level.
READ TABLE it_tj30t INDEX 1.
IF sy-subrc EQ 0.
CONCATENATE it_tj30t-txt04 '' INTO it_final-txt04 SEPARATED BY space.
ENDIF.
READ TABLE it_tj30t INDEX 2.
IF sy-subrc EQ 0.
CONCATENATE it_tj30t-txt04 it_final-txt04 INTO it_final-txt04 SEPARATED BY space.
ENDIF.
MOVE-CORRESPONDING it_prps TO it_final.
READ TABLE it_proj WITH KEY pspid = it_prps-posid.
IF sy-subrc EQ 0.
it_final-werks = it_proj-werks.
ENDIF.
APPEND it_final.
CLEAR it_final-txt04.
Passing activity to the final internal table IT_FINAL
LOOP AT it_afvc WHERE projn EQ it_prps-pspnr.
CLEAR color.
Getting user status and color(T2) for Activity from OBJNR
CALL FUNCTION 'ZGET_STATUS_N'
EXPORTING
objnr = it_afvc-objnr
IMPORTING
color = color
TABLES
t_status = it_tj30t.
IF color = 'RED'.
it_final-t2 = '@0A@'.
ELSEIF color = 'YELLOW'.
it_final-t2 = '@09@'.
ELSEIF color = 'GREEN'.
it_final-t2 = '@08@'.
ENDIF.
CLEAR: it_final-fsavd,
it_final-fssad.
MOVE-CORRESPONDING it_afvc TO it_final.
Getting User statuses of WBS element at activity level.
SORT it_tj30t DESCENDING.
READ TABLE it_tj30t INDEX 1.
IF sy-subrc EQ 0.
CONCATENATE it_tj30t-txt04 '' INTO it_final-txt04 SEPARATED BY space.
ENDIF.
READ TABLE it_tj30t INDEX 2.
IF sy-subrc EQ 0.
CONCATENATE it_tj30t-txt04 it_final-txt04 INTO it_final-txt04 SEPARATED BY space.
ENDIF.
APPEND it_final.
lv_index = sy-tabix.
CLEAR it_final-txt04.
CLEAR it_final-ltxa1.
CLEAR it_tj30t.
REFRESH it_tj30t.
Start Date and End Date fetched from AFVV.
LOOP AT it_afvv WHERE aufpl EQ it_afvc-aufpl
AND aplzl EQ it_afvc-aplzl.
MOVE-CORRESPONDING it_afvv TO it_final.
MODIFY it_final INDEX lv_index TRANSPORTING fsavd fssad.
ENDLOOP.
CLEAR it_afvc.
CLEAR lv_index.
ENDLOOP.
ENDLOOP.
Logic for T1.
T1 is based on T2 and start date and end date of activities.
LOOP AT it_final WHERE stufe = 3
AND ltxa1 IS NOT INITIAL.
gv_index = sy-tabix.
PERFORM date_difference.
CASE it_final-t2.
WHEN '@0A@'. " If Red
IF sy-datum GT it_final-fssad.
it_final-t1 = '@0A@'.
ELSEIF sy-datum LE it_final-fssad AND
sy-datum GE it_final-fsavd.
IF gv_diff > 1.
PERFORM date_monitor.
ENDIF.
it_final-t1 = '@09@'.
ELSEIF
sy-datum LT it_final-fsavd.
it_final-t1 = '@08@'.
ENDIF.
WHEN '@09@'. " If Yellow
IF sy-datum GT it_final-fssad.
it_final-t1 = '@0A@'.
ELSEIF sy-datum LE it_final-fssad AND
sy-datum GE it_final-fsavd.
IF gv_diff > 1.
PERFORM date_monitor.
ENDIF.
it_final-t1 = '@09@'.
ELSEIF
sy-datum LT it_final-fsavd.
it_final-t1 = '@08@'.
ENDIF.
WHEN '@08@'. " If Green
it_final-t1 = '@08@'.
ENDCASE.
MODIFY it_final INDEX gv_index TRANSPORTING t1.
CLEAR gv_index.
ENDLOOP.
ENDFORM. " GETDATA
*& Form hierarchy
Displays the data in ALV hierarchical manner.
In coding 3 tables are used for roll-up functionality.
FORM hierarchy .
DATA: it_final1 LIKE it_final OCCURS 0 WITH HEADER LINE.
DATA: it_final2 LIKE it_final OCCURS 0 WITH HEADER LINE.
DATA: it_final3 LIKE it_final OCCURS 0 WITH HEADER LINE.
DATA: count TYPE i VALUE 1.
DATA: posid LIKE prps-posid.
DATA: change,
date_mask TYPE c LENGTH 10,
lv_index2 LIKE sy-tabix.
DATA: index TYPE sy-tabix.
DATA: up LIKE prps-posid.
Deleting duplicate entries from the it_final.*****************
DELETE ADJACENT DUPLICATES FROM it_final.
LOOP AT it_final WHERE stufe EQ 2.
IF posid NE it_final-posid.
posid = it_final-posid.
ELSE.
DELETE it_final INDEX sy-tabix.
ENDIF.
ENDLOOP.
CLEAR posid.
LOOP AT it_final WHERE stufe EQ 3
AND ltxa1 EQ space.
IF posid NE it_final-posid.
posid = it_final-posid.
ELSE.
DELETE it_final INDEX sy-tabix.
ENDIF.
ENDLOOP.
Updating a new intrnal table for roll up functionality. ********
it_final1[] = it_final[].
CLEAR: lv_index2.
LOOP AT it_final1 WHERE stufe = 3
AND ltxa1 IS NOT INITIAL.
READ TABLE it_final WITH KEY stufe = 3
posid = it_final1-posid
post1 = it_final1-post1.
clear change.
IF sy-subrc = 0.
lv_index = sy-tabix.
IF lv_index2 <> lv_index.
CLEAR: change.
lv_index2 = lv_index.
ENDIF.
IF it_final1-t1 = '@0A@'.
it_final-t1 = '@0A@' .
MODIFY it_final INDEX lv_index TRANSPORTING t1.
DELETE it_final1 WHERE posid = it_final-posid.
CONTINUE.
ENDIF.
IF it_final1-t1 = '@09@'.
it_final-t1 = '@09@'.
change = 'Y'.
MODIFY it_final INDEX lv_index TRANSPORTING t1.
CONTINUE.
ENDIF.
IF it_final1-t1 = '@08@'.
it_final-t1 = '@08@' .
IF change IS INITIAL.
MODIFY it_final INDEX lv_index TRANSPORTING t1.
ENDIF.
CONTINUE.
ENDIF.
ENDIF.
ENDLOOP.
it_final2[] = it_final[].
CLEAR: lv_index2.
LOOP AT it_final2 WHERE stufe = 3
AND ltxa1 IS INITIAL.
READ TABLE e_wbs WITH KEY wbs_element = it_final2-posid.
IF sy-subrc = 0.
READ TABLE it_final WITH KEY stufe = 2
posid = e_wbs-up.
IF sy-subrc = 0.
CHECK it_final-t1 <> '@0A@'.
lv_index = sy-tabix.
IF lv_index2 <> lv_index.
CLEAR: change.
lv_index2 = lv_index.
ENDIF.
IF it_final2-t1 = '@0A@'.
it_final-t1 = '@0A@' .
MODIFY it_final INDEX lv_index TRANSPORTING t1.
CONTINUE.
ENDIF.
IF it_final2-t1 = '@09@'.
it_final-t1 = '@09@'.
MODIFY it_final INDEX lv_index TRANSPORTING t1.
change = 'Y'.
CONTINUE.
ENDIF.
IF it_final2-t1 = '@08@'.
it_final-t1 = '@08@' .
IF change IS INITIAL.
MODIFY it_final INDEX lv_index TRANSPORTING t1.
ENDIF.
CONTINUE.
ENDIF.
ENDIF.
ENDIF.
ENDLOOP.
it_final3[] = it_final[].
CLEAR: lv_index2.
CLEAR change.
LOOP AT it_final3 WHERE stufe = 2.
READ TABLE e_wbs WITH KEY wbs_element = it_final3-posid.
CHECK sy-subrc = 0.
READ TABLE it_final WITH KEY stufe = 1
posid = e_wbs-up.
IF sy-subrc = 0.
CHECK it_final-t1 <> '@0A@'.
lv_index = sy-tabix.
IF lv_index2 <> lv_index.
CLEAR: change.
lv_index2 = lv_index.
ENDIF.
IF it_final3-t1 = '@0A@'.
it_final-t1 = '@0A@' .
MODIFY it_final INDEX lv_index TRANSPORTING t1.
DELETE it_final3. " WHERE stufe = 2.
CONTINUE.
ENDIF.
IF it_final3-t1 = '@09@'.
it_final-t1 = '@09@'.
MODIFY it_final INDEX lv_index TRANSPORTING t1.
change = 'Y'.
CONTINUE.
ENDIF.
IF it_final3-t1 = '@08@'.
it_final-t1 = '@08@' .
IF change IS INITIAL.
MODIFY it_final INDEX lv_index TRANSPORTING t1.
ENDIF.
CONTINUE.
ENDIF.
ENDIF.
ENDLOOP.
Building hierarchy table ***************
LOOP AT it_final.
IF it_final-stufe = '0'.
node_tab-type = 'T'.
node_tab-name = 'Project'.
node_tab-tlevel = '01'.
node_tab-nlength = '8'.
node_tab-color = '4'.
node_tab-text = it_final-post1.
node_tab-tlength ='20'.
node_tab-tcolor = 5.
APPEND node_tab.
it_final_hsk-node = node_tab.
APPEND it_final_hsk. CLEAR it_final_hsk.
CLEAR node_tab.
ELSEIF it_final-stufe = '1'.
node_tab-type = 'P'.
node_tab-name = 'Project'.
node_tab-tlevel = '02'.
node_tab-nlength = '10'.
node_tab-color = '1'.
node_tab-kind2 = 'I'.
node_tab-text3+0(4) = it_final-t1.
node_tab-tlength3 = '5'.
node_tab-tcolor3 = 1.
node_tab-kind3 = ' '.
node_tab-text4 = it_final-posid.
node_tab-tlength4 ='20'.
node_tab-tcolor4 = 3.
Code added for plant name
CALL FUNCTION 'CONVERSION_EXIT_ABPSN_INPUT'
EXPORTING
input = it_final-posid
IMPORTING
output = it_final-posid.
READ TABLE it_proj WITH KEY pspid = it_final-posid.
CHECK sy-subrc = 0.
READ TABLE it_t001w WITH KEY werks = it_proj-werks.
CHECK sy-subrc = 0.
Code End.
node_tab-kind4 = ' '.
node_tab-text5 = it_t001w-name1. " Plant Name
node_tab-tlength5 ='25'.
node_tab-tcolor5 = 4.
node_tab-kind5 = ' '.
node_tab-text6 = it_proj-stort.
node_tab-tlength6 ='15'.
node_tab-tcolor6 = 4.
node_tab-kind6 = ' '.
node_tab-text7 = it_final-post1.
node_tab-tlength7 ='25'.
node_tab-tcolor7 = 4.
APPEND node_tab.
it_final_hsk-node = node_tab.
APPEND it_final_hsk. CLEAR it_final.
CLEAR node_tab.
ELSEIF it_final-stufe = '2'.
node_tab-type = 'P'.
node_tab-name = 'Gate Id'.
node_tab-tlevel = '03'.
node_tab-nlength = '10'.
node_tab-color = '1'.
node_tab-kind2 = 'I'.
node_tab-text3+0(4) = it_final-t1.
node_tab-tlength3 = '5'.
node_tab-tcolor3 = 1.
node_tab-kind3 = ' '.
node_tab-text4 = it_final-posid.
node_tab-tlength4 ='20'.
node_tab-tcolor4 = 3.
node_tab-kind4 = ' '.
node_tab-text5 = it_final-post1.
node_tab-tlength5 ='25'.
node_tab-tcolor5 = 4.
APPEND node_tab.
it_final_hsk-node = node_tab.
APPEND it_final_hsk.
CLEAR it_final.
CLEAR node_tab.
ELSEIF it_final-stufe = '3' AND it_final-ltxa1 EQ space.
node_tab-type = 'P'.
node_tab-name = 'Component'.
node_tab-tlevel = '04'.
node_tab-nlength = '11'.
node_tab-color = '1'.
node_tab-kind2 = 'I'.
node_tab-text3+0(4) = it_final-t1.
node_tab-tlength3 = '5'.
node_tab-tcolor3 = 1.
node_tab-kind3 = ' '.
node_tab-text4 = it_final-posid.
node_tab-tlength4 ='25'.
node_tab-tcolor4 = 3.
node_tab-kind4 = ' '.
node_tab-text5 = it_final-post1.
node_tab-tlength5 ='25'.
node_tab-tcolor5 = 4.
Code added for start date and end date for component level.
SELECT SINGLE pstrm petrf INTO (v_pstrm, v_petrf)
FROM prte WHERE posnr = it_final-pspnr.
it_final-fsavd = v_pstrm.
it_final-fssad = v_petrf.
MODIFY it_final INDEX sy-tabix.
WRITE it_final-fsavd TO date_mask MM/DD/YYYY.
node_tab-tpos1 = '0'.
node_tab-kind5 = ' '.
node_tab-text6 = date_mask.
node_tab-tlength6 ='10'.
node_tab-tcolor6 = 3.
CLEAR date_mask.
WRITE it_final-fssad TO date_mask MM/DD/YYYY.
node_tab-tpos1 = '0'.
node_tab-kind6 = ' '.
node_tab-text7 = date_mask.
node_tab-tlength7 ='10'.
node_tab-tcolor7 = 3.
CLEAR date_mask.
APPEND node_tab.
it_final_hsk-node = node_tab.
APPEND it_final_hsk.
CLEAR it_final_hsk.
CLEAR node_tab.
ELSEIF it_final-ltxa1 IS NOT INITIAL.
node_tab-type = 'P'.
node_tab-name = 'Element'.
node_tab-tlevel = '05'.
node_tab-nlength = '11'.
node_tab-color = '1'.
node_tab-kind = 'I'.
node_tab-text1+0(4) = it_final-t1.
node_tab-tlength1 = '5'.
node_tab-tcolor1 = 1.
node_tab-kind2 = 'I'.
node_tab-text3+0(4) = it_final-t2.
node_tab-tlength3 = '5'.
node_tab-tcolor3 = 1.
node_tab-kind3 = ' '.
node_tab-text4 = it_final-ltxa1.
node_tab-tlength4 ='45'.
node_tab-tcolor4 = 3.
node_tab-kind4 = ' '.
node_tab-text5 = it_final-txt04.
node_tab-tlength5 ='10'.
node_tab-tcolor5 = 3.
WRITE it_final-fsavd TO date_mask .
node_tab-kind5 = ' '.
node_tab-text6 = date_mask.
node_tab-tlength6 ='10'.
node_tab-tcolor6 = 3.
CLEAR date_mask.
WRITE it_final-fssad TO date_mask.
node_tab-tpos1 = '0'.
node_tab-kind6 = ' '.
node_tab-text7 = date_mask.
node_tab-tlength7 ='10'.
node_tab-tcolor7 = 3.
CLEAR date_mask.
APPEND node_tab.
it_final_hsk-node = node_tab.
APPEND it_final_hsk.
CLEAR it_final_hsk.
CLEAR node_tab.
ENDIF.
ENDLOOP.
CALL FUNCTION 'RS_TREE_CONSTRUCT'
TABLES
nodetab = it_final_hsk.
CALL FUNCTION 'RS_TREE_LIST_DISPLAY'
EXPORTING
callback_program = i_repid
callback_user_command = 'USER_COMMAND'
callback_gui_status = 'ZLD_TREE_N'
screen_start_column = 0
use_control = 'L'.
ENDFORM. " hierarchy
*& Form MYGUI
text
-->EX_TAB text
FORM zld_tree_n.
SET PF-STATUS 'ZLD_TREE_N'.
ENDFORM. "zld_tree.
**& Form user_command
Code for REFRESH button
FORM user_command TABLES node STRUCTURE seucomm
USING ucomm CHANGING exit
list_refresh.
CASE ucomm.
WHEN 'REFR' .
CLEAR it_final.
REFRESH it_final_hsk.
REFRESH it_final.
PERFORM getdata.
CLEAR it_final.
PERFORM hierarchy.
WHEN 'BACK1'.
LEAVE TO TRANSACTION 'ZCN41_N'.
ENDCASE.
ENDFORM. "user_command
include.....
*& Include ZDATA_DECLARE
*& Tables used for the report
TABLES: proj, prps, aufk, afvc, jest, tj30t, afvv, prte.
*& Type Pools used
TYPE-POOLS: slis, icon, fibs, stree.
*& Class & Data defination
CLASS DEFINATION
CLASS cl_gui_resources DEFINITION LOAD.
DATA DECLARATION
DATA: g_lights_name TYPE lvc_cifnm VALUE 'LIGHT',
pspid LIKE proj-pspid,
l_pos TYPE i VALUE 1,
gs_layout TYPE slis_layout_alv,
color TYPE zcn41_color_n-color.
DATA : cnt VALUE 'X'.
DATA : i_repid TYPE sy-repid.
DATA : t_node TYPE snodetext.
DATA : node_tab LIKE t_node OCCURS 0 WITH HEADER LINE.
DATA : gv_diff TYPE p, stort LIKE proj-stort.
CONSTANTS: st_formname_top_of_page TYPE slis_formname
VALUE 'TOP_OF_PAGE-ALV'.
*& Internal Table Declarations
DATA it_proj TYPE STANDARD TABLE OF proj WITH HEADER LINE.
DATA it_prps TYPE STANDARD TABLE OF prps WITH HEADER LINE.
DATA it_afvc TYPE STANDARD TABLE OF afvc WITH HEADER LINE.
DATA it_tj30t TYPE STANDARD TABLE OF tj30t WITH HEADER LINE.
DATA it_afvv TYPE STANDARD TABLE OF afvv WITH HEADER LINE.
DATA it_jcds TYPE STANDARD TABLE OF jcds WITH HEADER LINE.
DATA it_t001w TYPE STANDARD TABLE OF t001w WITH HEADER LINE.
DATA: BEGIN OF it_final OCCURS 0,
stufe LIKE prps-stufe,
pspnr LIKE prps-pspnr,
t1 TYPE icon-id,
t2 TYPE icon-id,
node LIKE node_tab,
posid LIKE prps-posid,
post1 LIKE prps-post1,
ltxa1 LIKE afvc-ltxa1,
txt04(20),
objnr LIKE afvc-objnr,
vornr LIKE afvc-vornr,
aufpl LIKE afvc-aufpl,
aplzl LIKE afvc-aplzl,
fsavd LIKE afvv-fsavd, "Ear. Start date
fssad LIKE afvv-fssad, "Ear. finish date
werks LIKE t001w-name1, " added after update
stort LIKE proj-stort, " added after update
END OF it_final.
DATA: BEGIN OF it_hsk OCCURS 0,
t2 TYPE icon-id,
t1 TYPE icon-id,
posid LIKE prps-posid,
post1 LIKE prps-post1,
objnr LIKE afvc-objnr,
stufe LIKE prps-stufe,
END OF it_hsk.
DATA: BEGIN OF it_new OCCURS 0,
objnr LIKE afvc-objnr,
fsavd LIKE afvv-fsavd,
fssad LIKE afvv-fssad,
udate LIKE jcds-udate,
t2(10),
END OF it_new.
CLEAR : node_tab, node_tab[].
DATA : entval TYPE prps-posid.
DATA : ct_fieldcat TYPE slis_t_fieldcat_alv.
DATA : BEGIN OF it_final_hsk OCCURS 0,
node LIKE node_tab,
END OF it_final_hsk.
DATA : project LIKE bapipr-project_definition,
e_project_definition LIKE bapi_project_definition_ex.
DATA : e_wbs_hierarchie_table TYPE STANDARD TABLE OF bapi_wbs_hierarchie
WITH HEADER LINE.
DATA : e_wbs LIKE e_wbs_hierarchie_table OCCURS 0 WITH HEADER LINE.
DATA: v_pstrm LIKE prte-pstrm, v_petrf LIKE prte-petrf,
v_posnr LIKE prps-pspnr.
*& Selection Screen of the report
SELECTION-SCREEN BEGIN OF BLOCK pms WITH FRAME TITLE text-001.
SELECT-OPTIONS so_posid FOR proj-pspid OBLIGATORY.
SELECT-OPTIONS so_plant FOR proj-werks.
SELECT-OPTIONS so_loc FOR proj-stort.
SELECT-OPTIONS so_date FOR sy-datum.
SELECTION-SCREEN END OF BLOCK pms.
*AT SELECTION-SCREEN .
READ TABLE it_proj WITH KEY pspid = so_posid.
IF sy-subrc <> 0.
MESSAGE 'Project Name dose not exist' TYPE 'E.
ENDIF.
include..
*& Include ZSUBR
*& Form date_difference
text
--> p1 text
<-- p2 text
FORM date_difference .
CALL FUNCTION 'ZDATETIME_DIFFERENCE_N'
EXPORTING
date1 = it_final-fsavd
time1 = '000000'
date2 = it_final-fssad
time2 = '000000'
IMPORTING
datediff = gv_diff
EXCEPTIONS
INVALID_DATETIME = 1
OTHERS = 2
IF sy-subrc <> 0.
MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
ENDIF.
ENDFORM. " date_difference
*& Form date_monitor
text
--> p1 text
<-- p2 text
T1 for more than 1 days activities
Subroutines result out the T1 on basis of 80% of activity ( Green )
or if 20 % reamined. ( Yellow )
FORM date_monitor .
DATA: date TYPE string,
temp_date TYPE string,
lv_date LIKE afvv-fsavd,
lv_date_final LIKE afvv-fsavd,
lv_days LIKE bseg-dtws1 VALUE 0.
CONSTANTS: con TYPE f VALUE '0.8'.
*lv_date = it_new-fsavd.
IF gv_diff EQ 2.
lv_days = 1.
CALL FUNCTION 'ZCALC_DATE_N'
EXPORTING
date = it_final-fsavd
days = lv_days
months = '00'
sign = '+'
years = '00'
IMPORTING
calc_date = lv_date_final.
IF sy-datum LE lv_date_final.
it_final-t1 = '@08@'.
ELSEIF sy-datum GT lv_date_final AND
sy-datum EQ it_final-fssad.
it_final-t1 = '@09@'.
ENDIF.
ELSEIF gv_diff > 2.
lv_days = con * gv_diff.
CALL FUNCTION 'ZCALC_DATE_N'
EXPORTING
date = lv_date
days = lv_days
months = '00'
sign = '+'
years = '00'
IMPORTING
calc_date = lv_date_final.
IF sy-datum LE lv_date_final.
it_final-t1 = '@08@'.
ELSEIF sy-datum GT lv_date_final AND
sy-datum EQ it_final-fssad.
it_final-t1 = '@09@'.
ENDIF.
ENDIF.
ENDFORM. " date_monitor
this code will give you exact out put as you required from bootom to top functinality....with status....
Maybe you are looking for
-
Can I transfer music from my iPad to my iPod nano without a laptop?
I do not seem to be able to transfer music between Apple products. Both my iPad and my iPod nano have a lightening fitting but there do not seem to be any lightening to lightening cables around in order to transfer from my iPad to my iPod? I'm downlo
-
How to limit the number of items that a list control can hold?
Hi, I am using a Flex3 List control for one of my projects. I add drag & drop functionality to it, so that i can drag & drop elements from one control to another. How to limit the number of items that a list control can hold / can be dropped in a lis
-
Error in oim Role creation using Role Manager Service API from Standalone Java client
Hi, Facing the following error when trying to create Role using Role Manager Service API from a standalone java client . Tried with the solution of changing , Login into the Web Logic Admin Console --> Servers --> OIM Server --> Protocols --> Modif
-
OBIEE 11g-- Graph Data Display
Hi All, I have been facing a big problem in making the report. I need to display month wise bar chart (Sales Value), On top of the Bar i have to display the Amount in terms of Millions, I have achieved by using Custom Number format, but It is difficu
-
I have forgotten the answers of security questions and the line of "forgot your answers? send reset security info email to ......." how can i reset them?