Long term Planning - capacity issue

Does any one have a way of running Long Term Planning in SAP.
When checking CM38 for production volumes, the start dates of
the planned orders always fall into the previous month from the
forecast (the monthly forecast is always placed on the first day
of the period and due to lead time scheduling the planned orders
to satisfy that forecast fall into the previous month). If i check the
capacity it show in same month for different month requirment.( it is clubing the requirment)
Though capacity scene was created from June to August , system shows loading from May month.
Month wise loading and availability are shown clubbed in capacity planning sheet.
Thanks in advanc....

Mukesh,
To change the forecast from occuring at start of period ( month) you can always select the Schedule line Tab in MD61,MD62. then select period indicator as Day format as shown below
Per. Ind          Date              Qty
D     17.05.2010     30
D     15.06.2010     40
D     15.07.2010     50
System will then plan PIR (forcast) based on dates assigned by user instead of being placed on the first day
of the period. This will prevent forcast to fall into the previous month. Also it will resolve the capacity issue you are facing.
If you have more questions please come back.
thanks,
Ram

Similar Messages

  • Capacity planning Long-term planning CM38

    Hi,
    I am using Long-term planning scenario. I have created 12 PIRs for 12 months from January 2010 to December 2010. I executed MRP in MS01 in Lead scheduling Mode.
    There are 12 planned orders created for the 12 PIRs for the months Jan to Dec-2010. When I see the planned orders in MS04 the satrt and finish date for the planned orders are showing in respective months beginning.
    But when I check capacity in transaction CM38, all the 12 planned order for Jan to December months are displayed in the month of  January itself instead of the respective months from Jan to December and the work center is overloaded 199%.
    Please suggest to solve this issue.
    thanks and regards
    Murugesan

    Hi,
    In customization for Capacity Planning you can define you own selection profiles to work with. You may specify further selection criteria in selection profile and enhance query speed from database. Slection profiles are assigned to overall profiles and overall profiles can be called by CM07 transaction. CM38 is also working over an overall profile which you may learn from SAP help. This can also be changed.
    Also check OPC5 to limit max data for selection which might be useful.
    Regards.

  • Sap mm md04 and ms04 stock requirement and long term planning issue

    Hi guru's,
    i have one issue regarding MD04 and MS04. in MD04 3 storage locations were showing. in that the stock in 2 storage locations was excluded due to no long term plan.
    now if we see in ms04, these 2 storage locations are not appearing. now my logistics manager wants to maintain the long term planning for these two also.
    in md04,,, 3 storage locations available ..same like ms04 should follow
    provide the solution as soon as possible
    Thanks & Regards
    Prasad.

    Mukesh,
    To change the forecast from occuring at start of period ( month) you can always select the Schedule line Tab in MD61,MD62. then select period indicator as Day format as shown below
    Per. Ind          Date              Qty
    D     17.05.2010     30
    D     15.06.2010     40
    D     15.07.2010     50
    System will then plan PIR (forcast) based on dates assigned by user instead of being placed on the first day
    of the period. This will prevent forcast to fall into the previous month. Also it will resolve the capacity issue you are facing.
    If you have more questions please come back.
    thanks,
    Ram

  • Capacity requirement for long term planning and make to order planning

    hello,
    anybody please guide me.
    my client using make to order scenarion and we are doing regulaly MRP run is MD50 with refernce to sales order.
    sales orders planning will follow for 2 to 3 months.
    at the same time my client wants to do long term planning also. to analize the capacity.
    for that he is creatind planning scenario and multi level planning with MS02 also.
    But the problem is when they are checking capacity requirement in cm38 it is showing only planning scenario load only. my client wants existing load and longterm planning load also. so they can plan the planning is sutibale in existing plan.
    so how can i get both plan in CM 38or is there any other T.code to get that data.
    please suggest me
    Thanks & Regards
    Bhakta

    Hi Pierre and Rajesh,
    When we create the simulation version, you have the possibility to choose the short-term planning. My point of view is, you can use the LTP fonction to do your scheduling for ex the next 3 months.
    I think it's what Pierre did. Am I right ?
    between to scheduling scenario to deliver my customer. With the simulation mode I can do my scheduling + use the MRP simulation to check if the raw material are available or not. Then use the MD04 to do the comparaison (or MS04 to compare between 2 scenario).
    But I found 2 problems :
    First : I don't find the parameters to show in the graphic MFS0, the planed fix order (I can only see the process order)
    Second : When my scheduling is finished, I want to update my operational planning with the simulation version. But I don't want to do article by article : when you have 400 references (raw mat, packaging, finish goods)  it's impossible (same issue like Pierre)
    Have you found a solution for this 2 points ?

  • Long-term planning: planning details of work center capacity

    Hi,
    we need to know what is the effect on planned production orders (generated by MPS, transaction MD40) of the flag <b>&#8220;long-term planning&#8221;</b> in planning details of work center capacity (table name: RC68K; field name: KAPLPL). We made a test  analyzing planned orders scheduling details in <i>Stock requirements list</i> (MD04) and in the <i>Planning table</i> (CM21) in both cases: with "long-term planning" flag set and without this flag for the same work center.
    The schedule of planned production order on that work center is the same in the two instance.
    Could you suggest us something?
    Thank you.

    Hi Rudy,
    Purpose for carrying out Long Term Planning to simulate impact of Future Demand Program on
    u2022 Material Requirements
    u2022 Capacity Requirements
    u2022 Material Cost budgeting (activity by Accounts dept.)
    T.Codes used -
    u2022 Demand      MD61, MD62, MD63
    u2022 Scenario Creation     MS31, MS32, MS33
    u2022 LTP Variant  Creation & Execution     MSBT, SM37
    u2022 LTP statistics Evaluation     SM37, MS04
    u2022 Data Set Up     MS70, MSB&
    u2022 Evaluation based on Set up data     MCB), MCEA, MCEB, MCEC
    u2022 Capacity Evaluation     CM38
    To Summarize -
    u2022 In long-term planning, production plans for future demand programs are simulated using MRP runs with reference to the planning scenarios.
    u2022 The parameters for the simulation in the simulation planning area are defined in the scenario.
    u2022 The Evaluation of LTP Statistics enables identification of Material for which LTP processing was terminated.
    u2022 The Data set for purchasing & Inventory Control enables reports for demand analysis
    u2022 LTP run with setting for u201CLead time scheduling and capacity planningu201D enables simulation of capacity situation/overload on work centers.
    Hope it is helpful to you.
    Srini

  • Long Term Planning Issue - Transaction MS04

    Hi Experts,
    I have two problems looking for solution from you.
    1. Transaction Code MS04 -> After entered Planning Version, Material and Plant... I can see list of orders in the report.  If I click Production Order, Planned Order, Inspection Lot document Element Details (on left hand additional function) and I am able to double click and display these documents.  However If I double click Material Reservsation document It is not allowing me as I can't see "Display element (F7) Icon.   How do I get the display element icon for Material reservation document also.
    2. We have a lot of Quality Inpsection lots documents when we display in MS04 report but the problem here it is peggeging as requirements in Long term planning report.  We want to just display the document here not as requirements. 
    Please let me know the solution for above two.
    Regards
    Rc Gopi

    Dear NNeeti,
    1.In CM38-->in the top menu --->under Planning ->Profiles->Overall Profile.
    2For this over all profile check the Details in OPA6 T Code and find out the option Profile assigned to this over all profile.
    3.Edit the details of this Option profile in OPA3 (change the number of days as 730 instead of 365 in the finish date).
    Check with this setting in CM38 and proceed.
    Check and revert
    Regards
    S Mangalraj

  • Inconsistent - Work Centre's Long-term Planning (KAKO-KAPLPL)

    Hi Experts,
    we're upgarding from SAP4.5 to ERP6.
    I reviewed OSS note 950834, but it's not related.
    We extracted from SAP4.5 Work Centre - Capacity Header - Long-term
    Planning.
    It's ticked (X) in CR03, but blank () in table KAKO-KAPLPL.
    We loaded into ERP6 Work Centre - Capacity Header - Long-term Planning.
    It's blank () in CR03, but ticked (X) in table KAKO-KAPLPL.
    Please advise the fix for this issue.
    Thanks,
    Thomas

    Dear Thomas,
    I suggest you to check relevant OSS notes. Also creaete a OSS message for this issue.
    thanks and regards
    muru

  • Use Reorder Point Planning and see VSE Requirements in Long Term Planning

    Hello,
    I would like to use reorder point planning short term and something similar to MRP planning long term. I am trying to drive actual production off of consumption and plan long term for capacity, inventory and BOM components.  Our plan is to delete the near term forecast and leave the long term forecast in to show requirements for LTP.
    I'm configured for Reorder Point Planning as follows:
    MRP type V1, Reorder Point Planning with External Requirements
    Planning Strategy 52
    HB Max Stock Level
    For the longer term forecast requirements I'm configured with:
    Independent Requirement Type VSE, Planning without final assembly.  This is creating non convertible planned order independent requirements.
    The reorder point planning is executing perfectly, but how do I get the VSE planned order independent requirements to show up in long term capacity and inventory planning? What am I missing?  Is it something with MRP type, am I missing an option in the long term planning setup?
    This has been a tough issue and I would greatly appreciate any advice on this.
    Thank you,
    Wes
    Edited by: weslaney on Jul 21, 2009 11:40 PM

    HI
    check the planning scenario in MS31 and the PIR assignment in MS31 also check the plant assignement.
    Check In MD61 you have enter PIRs in simulation version and the same version is to assigned in planning scenario
    Also check T code OPU5 for LTP setting for planned orders
    Regards
    Anupam Sharma
    Edited by: anupam sharma on Sep 3, 2010 2:33 PM

  • How to consider the Purchase Orders in Long Term Planning

    Hi All,
    I wanted to include the Purchase Orders of Finished Material in Long Term Planning.
    I have selected the check box "Long-term planning: include firmed issues and receipts" in the Planning Scenario  but after LTP run system is not considering the Purchase Orders of Finished Materials for Planning.
    Regards,
    Shailendra
    Edited by: Shailendra Hadkar on Apr 5, 2010 12:41 PM

    Dear,
    Could you please explain usage of purchase orders for Finished product?
    Regards,
    SAP CONS

  • Re: Long term Planning

    Dear All,
    I am trying to do Long term Planning. In my case I am not using SOP. Demand is entered into SAP through PIR (i.e. PIR).
    I want to see how much load is there on all the resources available.
    Please advice me how to proceed in this direction.
    Regards,
    Vivek Sharma

    Dear Vivek,
    Check with these steps,
    1.A plannig scenario has to be created for a plant in T code MS31 & for the same Planning scenario
    configuration settings has to be made in OPU5 for the planned orders for LTP.
    2.Requirements has to be given in MD61 in an inactive version and also after giving the requirements
    kindly remove the tick mark against version- active check box.
    3.Assign this plan to the planning scenario in MS32,release it and ensure the planning file entries are
    entered or created,the same can be checked using MS21.
    4.After taking LTP simulation run in MS02(individual material) or MS01 you can see the simulated
    planned orders obtained in MS04 T code.
    5.These Simulated planned orders can't be converted into production orders or it cant be used for any
    business confirmation purpose.
    6. For capacity planning analysis,use T Code CM38,
    Before that Ensure for all the work centers in CR03 which are used for operation under capacity header
    you have included the check box for Long term planning,otherwise in CM38 you can't see any capacity
    requirements data.
    7.Before executing CM38,ensure under settings---> general you are giving the period settings properly.
    Revert back incase of any more clarifications required.
    Regards
    Mangalraj.S

  • Query on Long Term Planning (MS31)

    During the creation of long term planning the following steps i followed before i am stuck at one point.
    1)T code MS31
    2)Planning Scenarion and detail
    3)Long term Planning Radio Button selection
    4)Planning period +Use Gross Lot Size (EX)
    5)BOM Selection ID 01
    6)Tab Planned Independent requirement details filled
    Now in Plant TAB when i give my plant id  the message is REQUIREMENT PLANNING IS NOT ACTIVE FOR MY PLANT CODE.
    Message no. 61139
    Please tell me how to make it active.
    Thanks in advance
    Rupesh Jha

    Dear Rupesh,
    Plz Refer to Mr. Mangalraj inputs on LTP
    1.A plannig scenario has to be created for a plant in T code MS31 & for the same Planning scenario
    configuration settings has to be made in OPU5 for the planned orders for LTP.
    2.Requirements has to be given in MD61 in an inactive version and also after giving the requirements
    kindly remove the tick mark against version- active check box.
    3.Assign this plan to the planning scenario in MS32,release it and ensure the planning file entries are
    entered or created,the same can be checked using MS21.
    4.After taking LTP simulation run in MS02(individual material) or MS01 you can see the simulated
    planned orders obtained in MS04 T code.
    5.These Simulated planned orders can't be converted into production orders or it cant be used for any
    business confirmation purpose.
    6. For capacity planning analysis,use T Code CM38,
    Before that Ensure for all the work centers in CR03 which are used for operation under capacity header
    you have included the check box for Long term planning,otherwise in CM38 you can't see any capacity
    requirements data.
    7.Before executing CM38,ensure under settings---> general you are giving the period settings properly.
    Revert back incase of any more clarifications required.
    Regards
    kumar

  • Long term Planning in SAP

    Hi Gurus,
    I am new to SAP,this my 1st query in SDN.
    I have been given sales figures of last 5 years of particular organization and i have been told to create a long term planning report in SAP please tell me the detailed methodology of create a long plan for the next 6 months in SAP.
    Regards
    Krish

    Dear Krish,
    LTP is a planning tool,where simulated planned orders's are obtained for an inactive plan.
    It will be more helpful from production perspective.
    To carry out an annual planning or a rolling quarterly planning run you require information on the future stock and requirements
    situation. This means you need to know how sales and operations planning influence resources. That is, whether the results
    of sales planning can actually be produced with capacity on hand. If such information is available it is possible to decide at an
    early date whether extra work centers will be required to cope with bottlenecks, or whether additional machinery will have to
    be purchased to reach the sales target.
    Steps for LTP:
    1.A plannig scenario has to be created for a plant in T code MS31 & for the same Planning scenario
    configuration settings has to be made in OPU5 for the planned orders for LTP.
    2.Requirements has to be given in MD61 in an inactive version and also after giving the requirements
    kindly remove the tick mark against version- active check box.
    3.Assign this plan to the planning scenario in MS32,release it and ensure the planning file entries are
    entered or created,the same can be checked using MS21.
    4.After taking LTP simulation run in MS02(individual material) or MS01 you can see the simulated
    planned orders obtained in MS04 T code.
    5.These Simulated planned orders can't be converted into production orders or it cant be used for any
    business confirmation purpose.
    6. For capacity planning analysis,use T Code CM38,
    Before that Ensure for all the work centers in CR03 which are used for operation under capacity header
    you have included the check box for Long term planning,otherwise in CM38 you can't see any capacity requirements data.
    7.Before executing CM38,ensure under settings---> general you are giving the period settings properly.
    8.Use T Code KSPP to transfer the planned activity requirements for production.
    Revert back incase of any more clarifications required.
    Regards
    Mangalraj.S

  • Long term Planning -PP

    Hi Gurus,
                  Can any one explaine me the config step by step of creating long term planning. I am using APO DP PIR in SAP ECC and trying to generate Long term planning.
    It will be really great if ayone can help me in step-by step.
    Thanks & Regards,
    kumar

    HI
    These are the main steps for LTP:
    1.A plannig scenario has to be created for a plant in T code MS31 & for the same Planning scenario
    configuration settings has to be made in OPU5 for the planned orders for LTP.
    2.Requirements has to be given in MD61 in an inactive version and also after giving the requirements
    kindly remove the tick mark against version- active check box.
    3.Assign this plan to the planning scenario in MS32,release it and ensure the planning file entries are
    entered or created,the same can be checked using MS21.
    4.After taking LTP simulation run in MS02(individual material) or MS01 you can see the simulated
    planned orders obtained in MS04 T code.
    5.These Simulated planned orders can't be converted into production orders or it cant be used for any
    business confirmation purpose.
    6 For capacity planning analysis check T code CM38
    Regards
    Anupam Sharma

  • Long Term Planning for Quotation

    Hi
    My client wants to plan Long term Planning w.r.t to sales quotation and not with demand planning.Kindly provide me the details steps.
    Regards
    P.Srinivasan

    Dear shankar,
    I'm not sure whether LTP can fulfill your requirement completely,but for such requirements generally LTP run for an inatice version
    can show the capacity required for meeting such a demand for the mentioned period and also the procurement analysis.
    For checking the split of requirements into multiple production line try by creating different production versions and maintain quota
    for the same.
    Check this link to explore more,
    [Quota Arrangement in LTP|Re: Quota Arrangement in LTP]
    Regards
    S Mangalraj

  • Long term planning analysis

    Hi,
    what's long term planning analysis and how to use the blw tcodes.. in this tcode its asking for planning scenerio, how to create it?? pls explain the usages of these t codes?? is it really used in user level??
    MCEA
    MCEB
    MCEC

    Dear,
    Basically LTP is simulative MRP to simulate and see all the results like production capacity plan/ raw material plan/ profit margin. here we are using the same master data like material master, recipe, BOM etc.
    In MS31 - you create a LTP version where you can mention the PIR version where you enter the planning data in MD61.
    Release this version and maintain the planning data like qty per period in MD61 with the version mentioned in MS31, make sure that the version is not active so that LTP consider this inactive qty data.
    Run MS01/MS02/MS03 etc to run simulative MRP.
    Results can be seen in MS04/MS05.
    Inn MSF0 you can see the capacity requirement and adjust the qty to se that 100% capacity is utilized.
    We can see the raw material requirement in Pur info system in MCEC/MCEA/MCEB/MCB&/MCB)
    Also refer my reply from this link also,
    Re: LTP - S012 Tables
    Hope clear to you.
    Regards,
    R.Brahmankar

Maybe you are looking for

  • How to access the caption of the text field??

    Can someone give me the javascript to access the caption property of the test fields.Actually i've tried with 'TextField.caption' but it isn't working properly. Waiting for anyone to fix the problem Thanks and Regards Shoaib

  • Table filtering is case sensitive

    ADF Version: Oracle JDeveloper 11 g Update 2 (Build 5205) (11.1.1.0.2) We are using an older version of ADF / jDeveloper for our application. We have run into the issue where all of the filter fields on our tables seem to be case sensitive. I am awar

  • Can i get the scratches off my ipod, Can i get the scratches off my ipod

    The back of my ipod has scratches and i hav a see through case. I was wondering if i can bring my ipod to the apple store and get the scratches off of it.

  • How to set httponly cookies in J2EE 5

    Hi folks, I ma using Tomcat 6 which implements Servlet API 2.5 (part of the J2EE 5). I know I could set the usehttponly="true" in the context.xml to turn on all cookies to httponly. However, if I only need to set certain cookies to be httponly, how t

  • Deskjet F4480: what causes horizontal gaps when printing from the web?

    I just installed a Deskjet F4480 printer. I'm using Windows 7 64-bit.  Printing a word-processing document works just fine - no problems.  Printing from a web page, however, produces horizontal streaks or gaps in the print.  The bottom of some lines