Long Term Planning Issue - Transaction MS04

Hi Experts,
I have two problems looking for solution from you.
1. Transaction Code MS04 -> After entered Planning Version, Material and Plant... I can see list of orders in the report.  If I click Production Order, Planned Order, Inspection Lot document Element Details (on left hand additional function) and I am able to double click and display these documents.  However If I double click Material Reservsation document It is not allowing me as I can't see "Display element (F7) Icon.   How do I get the display element icon for Material reservation document also.
2. We have a lot of Quality Inpsection lots documents when we display in MS04 report but the problem here it is peggeging as requirements in Long term planning report.  We want to just display the document here not as requirements. 
Please let me know the solution for above two.
Regards
Rc Gopi

Dear NNeeti,
1.In CM38-->in the top menu --->under Planning ->Profiles->Overall Profile.
2For this over all profile check the Details in OPA6 T Code and find out the option Profile assigned to this over all profile.
3.Edit the details of this Option profile in OPA3 (change the number of days as 730 instead of 365 in the finish date).
Check with this setting in CM38 and proceed.
Check and revert
Regards
S Mangalraj

Similar Messages

  • Sap mm md04 and ms04 stock requirement and long term planning issue

    Hi guru's,
    i have one issue regarding MD04 and MS04. in MD04 3 storage locations were showing. in that the stock in 2 storage locations was excluded due to no long term plan.
    now if we see in ms04, these 2 storage locations are not appearing. now my logistics manager wants to maintain the long term planning for these two also.
    in md04,,, 3 storage locations available ..same like ms04 should follow
    provide the solution as soon as possible
    Thanks & Regards
    Prasad.

    Mukesh,
    To change the forecast from occuring at start of period ( month) you can always select the Schedule line Tab in MD61,MD62. then select period indicator as Day format as shown below
    Per. Ind          Date              Qty
    D     17.05.2010     30
    D     15.06.2010     40
    D     15.07.2010     50
    System will then plan PIR (forcast) based on dates assigned by user instead of being placed on the first day
    of the period. This will prevent forcast to fall into the previous month. Also it will resolve the capacity issue you are facing.
    If you have more questions please come back.
    thanks,
    Ram

  • Long term Planning - capacity issue

    Does any one have a way of running Long Term Planning in SAP.
    When checking CM38 for production volumes, the start dates of
    the planned orders always fall into the previous month from the
    forecast (the monthly forecast is always placed on the first day
    of the period and due to lead time scheduling the planned orders
    to satisfy that forecast fall into the previous month). If i check the
    capacity it show in same month for different month requirment.( it is clubing the requirment)
    Though capacity scene was created from June to August , system shows loading from May month.
    Month wise loading and availability are shown clubbed in capacity planning sheet.
    Thanks in advanc....

    Mukesh,
    To change the forecast from occuring at start of period ( month) you can always select the Schedule line Tab in MD61,MD62. then select period indicator as Day format as shown below
    Per. Ind          Date              Qty
    D     17.05.2010     30
    D     15.06.2010     40
    D     15.07.2010     50
    System will then plan PIR (forcast) based on dates assigned by user instead of being placed on the first day
    of the period. This will prevent forcast to fall into the previous month. Also it will resolve the capacity issue you are facing.
    If you have more questions please come back.
    thanks,
    Ram

  • Capacity planning Long-term planning CM38

    Hi,
    I am using Long-term planning scenario. I have created 12 PIRs for 12 months from January 2010 to December 2010. I executed MRP in MS01 in Lead scheduling Mode.
    There are 12 planned orders created for the 12 PIRs for the months Jan to Dec-2010. When I see the planned orders in MS04 the satrt and finish date for the planned orders are showing in respective months beginning.
    But when I check capacity in transaction CM38, all the 12 planned order for Jan to December months are displayed in the month of  January itself instead of the respective months from Jan to December and the work center is overloaded 199%.
    Please suggest to solve this issue.
    thanks and regards
    Murugesan

    Hi,
    In customization for Capacity Planning you can define you own selection profiles to work with. You may specify further selection criteria in selection profile and enhance query speed from database. Slection profiles are assigned to overall profiles and overall profiles can be called by CM07 transaction. CM38 is also working over an overall profile which you may learn from SAP help. This can also be changed.
    Also check OPC5 to limit max data for selection which might be useful.
    Regards.

  • Excluding storage location from MRP run in Long Term Planning

    Hi,friends,
         In my scenario , i want to exclude storage location from MRP run in long term planning.When i set storage location MRP indicator "2" in SPRO and SLoc MRP indicator "1" MRP4 in material master, i can exclude the storage location after run MRP with MD01/MD02,and i can see the expected result in MD04.But in Long Term Planning scenario the storage location can not be excluded after run MRP with MS01/MS02,and the requirements list in MS04 include the stock in the storage location i want to exclude. i dont know if i miss something.Plz give me some advice.
    Regards
    Joey

    Hi,
    Refer the OSS Note 208017 - LTP: Long-term planning and storage locations
    ==========================================================================
    Symptom
    In long-term planning (Transactions MSBT / MS01 / MS02 / MS03), the MRP indicator of a storage location for a material is not taken into account (material master, view MRP 2 [up to and including Release 3.1I] or MRP 4 [as of Release 4.0A]).
    The storage locations excluded by MRP or planned separately are also planned in the plant segment.
    Additional key words
    LTP, MM01, MM02, MM03, master data, MRP indicator, LGORT ...
    Cause and prerequisites
    The MRP indicator for a certain storage location of a material is only taken into account in operative planning (requirements planning, MRP).
    The long-term planning occurs exclusively at plant level.
    Solution
    This is no error. The system works as intended.
    The individual storage locations should not be distinguished in the long-term planning, in order to perform a comprehensive long-term planning.
    This is important, for example, within the kanban processing where the storage locations with kanban MRP are excluded from the MRP, but in spite of that should be included in the long-term planning.
    ==========================================================================
    Regards,
    Siva

  • Long-term planning: planning details of work center capacity

    Hi,
    we need to know what is the effect on planned production orders (generated by MPS, transaction MD40) of the flag <b>&#8220;long-term planning&#8221;</b> in planning details of work center capacity (table name: RC68K; field name: KAPLPL). We made a test  analyzing planned orders scheduling details in <i>Stock requirements list</i> (MD04) and in the <i>Planning table</i> (CM21) in both cases: with "long-term planning" flag set and without this flag for the same work center.
    The schedule of planned production order on that work center is the same in the two instance.
    Could you suggest us something?
    Thank you.

    Hi Rudy,
    Purpose for carrying out Long Term Planning to simulate impact of Future Demand Program on
    u2022 Material Requirements
    u2022 Capacity Requirements
    u2022 Material Cost budgeting (activity by Accounts dept.)
    T.Codes used -
    u2022 Demand      MD61, MD62, MD63
    u2022 Scenario Creation     MS31, MS32, MS33
    u2022 LTP Variant  Creation & Execution     MSBT, SM37
    u2022 LTP statistics Evaluation     SM37, MS04
    u2022 Data Set Up     MS70, MSB&
    u2022 Evaluation based on Set up data     MCB), MCEA, MCEB, MCEC
    u2022 Capacity Evaluation     CM38
    To Summarize -
    u2022 In long-term planning, production plans for future demand programs are simulated using MRP runs with reference to the planning scenarios.
    u2022 The parameters for the simulation in the simulation planning area are defined in the scenario.
    u2022 The Evaluation of LTP Statistics enables identification of Material for which LTP processing was terminated.
    u2022 The Data set for purchasing & Inventory Control enables reports for demand analysis
    u2022 LTP run with setting for u201CLead time scheduling and capacity planningu201D enables simulation of capacity situation/overload on work centers.
    Hope it is helpful to you.
    Srini

  • Capacity requirement for long term planning and make to order planning

    hello,
    anybody please guide me.
    my client using make to order scenarion and we are doing regulaly MRP run is MD50 with refernce to sales order.
    sales orders planning will follow for 2 to 3 months.
    at the same time my client wants to do long term planning also. to analize the capacity.
    for that he is creatind planning scenario and multi level planning with MS02 also.
    But the problem is when they are checking capacity requirement in cm38 it is showing only planning scenario load only. my client wants existing load and longterm planning load also. so they can plan the planning is sutibale in existing plan.
    so how can i get both plan in CM 38or is there any other T.code to get that data.
    please suggest me
    Thanks & Regards
    Bhakta

    Hi Pierre and Rajesh,
    When we create the simulation version, you have the possibility to choose the short-term planning. My point of view is, you can use the LTP fonction to do your scheduling for ex the next 3 months.
    I think it's what Pierre did. Am I right ?
    between to scheduling scenario to deliver my customer. With the simulation mode I can do my scheduling + use the MRP simulation to check if the raw material are available or not. Then use the MD04 to do the comparaison (or MS04 to compare between 2 scenario).
    But I found 2 problems :
    First : I don't find the parameters to show in the graphic MFS0, the planed fix order (I can only see the process order)
    Second : When my scheduling is finished, I want to update my operational planning with the simulation version. But I don't want to do article by article : when you have 400 references (raw mat, packaging, finish goods)  it's impossible (same issue like Pierre)
    Have you found a solution for this 2 points ?

  • Long Term Planning-Planning File Entry

    Hi Gurus/Friends
    In the long term planning after PIR with inactive version and creating Scenario, assinging versions, Plants,....then
    during Release+Save it is giving the Result of Planning File Entries
    Logically the system has suppose to give the Number of Planning File Entries in Propotionate to the Specific Planning Scenario number and materials inside
    But it is giving for all the Materials inside the Plant
    Is there any settings to restrict the Planning File Entry creation w.r.t Planning scenario during Release+Save
    other than the solutions through Transaction MS20,MS22 and MSAB
    (Because during Release+save logically it has to call the MS22 t.code  and do planning file entries for the materials in that scenario)
    Awaiting for reply
    thanks
    K.Prabakaran

    Hi,
    Please Refer Below SAP help .
    *Releasing a planning scenario*
    You first have to release a planning scenario before you can plan it in the long-term planning run. When you release the planning scenario, the system creates planning file entries for all materials in all the plants allocated to the planning scenario. There is a separate planning file entry for this purpose. This guarantees that your operative planning is kept completely separate from your simulative planning. This long-term planning file contains all the materials that are also contained in the operative planning file. After the release, every change relevant to MRP triggers an entry in the planning file as in operative planning.
    Pradeep
    Edited by: Pradeep Kumar on May 9, 2008 4:22 PM

  • How to consider the Purchase Orders in Long Term Planning

    Hi All,
    I wanted to include the Purchase Orders of Finished Material in Long Term Planning.
    I have selected the check box "Long-term planning: include firmed issues and receipts" in the Planning Scenario  but after LTP run system is not considering the Purchase Orders of Finished Materials for Planning.
    Regards,
    Shailendra
    Edited by: Shailendra Hadkar on Apr 5, 2010 12:41 PM

    Dear,
    Could you please explain usage of purchase orders for Finished product?
    Regards,
    SAP CONS

  • Long term planning in ECC for materials planned in SAP APO

    Hi SAP PP and APO Experts,
    I would like to know whether it is possible to plan a material in SAP ECC with Long Term Planning to create Simulative Planned Orders in ECC, when the MRP Type for the material is set to X0 (Planning in SAP APO).
    Warm regards,
    Prem

    Hi Dhaivakumar,
    Appreciate your prompt response.
    My business is MTS. I have made all settings for LTP planning for the material. (M|RP Type is set to X0-Planning in APO). When I execute the transaction MS02, I get the error message "Material 5200000013 J310  is not planned automatically. Message no. 61008". The details of the error message is:
    The material 5200000013 in plant J310 or in MRP area  is not included in automatic MRP because
    either the MRP data for plant J310 or MRP area  has not been created
    or an MRP type has been entered for the material in plant J310 or MRP area  that does not allow automatic MRP.
    Warm regards,
    Prem

  • Inconsistent - Work Centre's Long-term Planning (KAKO-KAPLPL)

    Hi Experts,
    we're upgarding from SAP4.5 to ERP6.
    I reviewed OSS note 950834, but it's not related.
    We extracted from SAP4.5 Work Centre - Capacity Header - Long-term
    Planning.
    It's ticked (X) in CR03, but blank () in table KAKO-KAPLPL.
    We loaded into ERP6 Work Centre - Capacity Header - Long-term Planning.
    It's blank () in CR03, but ticked (X) in table KAKO-KAPLPL.
    Please advise the fix for this issue.
    Thanks,
    Thomas

    Dear Thomas,
    I suggest you to check relevant OSS notes. Also creaete a OSS message for this issue.
    thanks and regards
    muru

  • Long Term Planning MCB)

    Hi,
    Please suggest how to analyze the output of MCB) transaction for long term planning.
    Thanks & Regards,
    Nataraj

    Hi there,
    Could you please give more details such as what are your objectives, the type of material (high frequency demand, low frequency, etc) and the span of long term planning (1 year, 5 years, 10?).
    Cheers,
    Rodrigo

  • Re: Long term Planning

    Dear All,
    I am trying to do Long term Planning. In my case I am not using SOP. Demand is entered into SAP through PIR (i.e. PIR).
    I want to see how much load is there on all the resources available.
    Please advice me how to proceed in this direction.
    Regards,
    Vivek Sharma

    Dear Vivek,
    Check with these steps,
    1.A plannig scenario has to be created for a plant in T code MS31 & for the same Planning scenario
    configuration settings has to be made in OPU5 for the planned orders for LTP.
    2.Requirements has to be given in MD61 in an inactive version and also after giving the requirements
    kindly remove the tick mark against version- active check box.
    3.Assign this plan to the planning scenario in MS32,release it and ensure the planning file entries are
    entered or created,the same can be checked using MS21.
    4.After taking LTP simulation run in MS02(individual material) or MS01 you can see the simulated
    planned orders obtained in MS04 T code.
    5.These Simulated planned orders can't be converted into production orders or it cant be used for any
    business confirmation purpose.
    6. For capacity planning analysis,use T Code CM38,
    Before that Ensure for all the work centers in CR03 which are used for operation under capacity header
    you have included the check box for Long term planning,otherwise in CM38 you can't see any capacity
    requirements data.
    7.Before executing CM38,ensure under settings---> general you are giving the period settings properly.
    Revert back incase of any more clarifications required.
    Regards
    Mangalraj.S

  • Query on Long Term Planning (MS31)

    During the creation of long term planning the following steps i followed before i am stuck at one point.
    1)T code MS31
    2)Planning Scenarion and detail
    3)Long term Planning Radio Button selection
    4)Planning period +Use Gross Lot Size (EX)
    5)BOM Selection ID 01
    6)Tab Planned Independent requirement details filled
    Now in Plant TAB when i give my plant id  the message is REQUIREMENT PLANNING IS NOT ACTIVE FOR MY PLANT CODE.
    Message no. 61139
    Please tell me how to make it active.
    Thanks in advance
    Rupesh Jha

    Dear Rupesh,
    Plz Refer to Mr. Mangalraj inputs on LTP
    1.A plannig scenario has to be created for a plant in T code MS31 & for the same Planning scenario
    configuration settings has to be made in OPU5 for the planned orders for LTP.
    2.Requirements has to be given in MD61 in an inactive version and also after giving the requirements
    kindly remove the tick mark against version- active check box.
    3.Assign this plan to the planning scenario in MS32,release it and ensure the planning file entries are
    entered or created,the same can be checked using MS21.
    4.After taking LTP simulation run in MS02(individual material) or MS01 you can see the simulated
    planned orders obtained in MS04 T code.
    5.These Simulated planned orders can't be converted into production orders or it cant be used for any
    business confirmation purpose.
    6. For capacity planning analysis,use T Code CM38,
    Before that Ensure for all the work centers in CR03 which are used for operation under capacity header
    you have included the check box for Long term planning,otherwise in CM38 you can't see any capacity
    requirements data.
    7.Before executing CM38,ensure under settings---> general you are giving the period settings properly.
    Revert back incase of any more clarifications required.
    Regards
    kumar

  • T399D - Long-term planning allowed for a plant

    Hi gurus,
    I was checking the table T399D and it has the "Long-term planning allowed for a plant" field (T399D-SIMPL), but, I do not know where I can customise this!
    I was checking OMI8 and OPPQ (Parameters for DS section) transactions, but, I cannot find this field.
    Could you help me in order to know where I can customise this?
    Kind regards,
    Sandra

    Hi Sandra,
                     As it is correctly said that there is not much configuration required to Run LTP, but what you  basically need to maintain/configure is as follows-
    To carry out an annual planning or a rolling quarterly planning run you require information on the
    future stock and requirements situation. This means you need to know how sales and operations
    planning influence resources(conceptually)-
    In long-term planning you can also plan materials that usually require very little planning in
    operative planning, such as, materials planned using reorder point planning, bulk material, and
    materials planned using KANBAN. In long-term planning, you can plan these materials as you
    would MRP materials. This provides you with an overview of how these materials influence the
    demand program.
    The materials you want to plan in long-term planning must have already been planned in
    operative MRP.Apart from above conceptual knowledge what else you require to configure /maintain is-
    Planning Scenario(If you are running wity reference to it)-MS31
    And run it through MS02(with reference to planning scenario) where you have to put mandatory  MRP Control Parameters according to your business process eg.Processing key,create MRP list,planning mode,scheduling,firming planned orders.
    Hope it fulfils your purpose at some extent.
    Regards
    Chandra

Maybe you are looking for

  • Error while downloading file

    Hi all, I am facing some problem while downloading the data to presentation server.In the program they are using the FM 'WS_DOWNLOAD' to download the file.But its not working and setting the sy-subrc eq 2 which means 'Cannot Write to File'.wat could

  • HT1414 it will not update. how do i fix that?

    i log onto itunes and it asks me if i want to update my itouch to the updated version (5) and i click yes. it starts the backing up process but then stops. how do i fix that?

  • Installing Yosemite = dead screen, disaster

    I have a number of Macs, and first installed Yosemite on two home machines before tackling the main one I use at work. Those installations went fine. The installation on my main machine (a 2014 Mac Pro) has been catastrophic. I left it running overni

  • I want add new column in matrix in "Inventory Transfer" Form (System Form)

    hai, i want to add new column in Matrix in "Inventory Transfer" Form (System Form) Is it possible or not? bye gopinath

  • Is it safe to delete...

    Is it safe to delete the following folders in the Macintosh HD > Library? "Printers" +except for Installed Printers.plist, the PDD Plugins folder and the Brother folder (I use a Brother printer)+ "*Application Support > hp*" "Receipts" "*Updates > (a