Long term planning material not displayed in MS04

Hi,
May I request your assistance on my issue? When I run the MS04
one of the component material is not displaying. I have change the planning
period and run again the MS03 for a specific material which is the finished material.
My component is now displaying, however the other material now has a negative
value on available qty.
Can you help me understand why the component material is not
displayed in my first run? How it is included on the next run and why the other
material had a negative value on available qty when I run the MS04 after I change
the planning period?
Hope to receive your help.
Thanks,
Aisha

In the MRP Parameters at the time of MRP Run
Planning Mode=Delete and Recreate Planning Data
(Do it in dev server/sandbox/ides )then do it in production server
will bring the Requirements column with Pegged Requirements in Capacity Planning
Pl try
K.Prabakaran

Similar Messages

  • Long Term Planning Issue - Transaction MS04

    Hi Experts,
    I have two problems looking for solution from you.
    1. Transaction Code MS04 -> After entered Planning Version, Material and Plant... I can see list of orders in the report.  If I click Production Order, Planned Order, Inspection Lot document Element Details (on left hand additional function) and I am able to double click and display these documents.  However If I double click Material Reservsation document It is not allowing me as I can't see "Display element (F7) Icon.   How do I get the display element icon for Material reservation document also.
    2. We have a lot of Quality Inpsection lots documents when we display in MS04 report but the problem here it is peggeging as requirements in Long term planning report.  We want to just display the document here not as requirements. 
    Please let me know the solution for above two.
    Regards
    Rc Gopi

    Dear NNeeti,
    1.In CM38-->in the top menu --->under Planning ->Profiles->Overall Profile.
    2For this over all profile check the Details in OPA6 T Code and find out the option Profile assigned to this over all profile.
    3.Edit the details of this Option profile in OPA3 (change the number of days as 730 instead of 365 in the finish date).
    Check with this setting in CM38 and proceed.
    Check and revert
    Regards
    S Mangalraj

  • Sap mm md04 and ms04 stock requirement and long term planning issue

    Hi guru's,
    i have one issue regarding MD04 and MS04. in MD04 3 storage locations were showing. in that the stock in 2 storage locations was excluded due to no long term plan.
    now if we see in ms04, these 2 storage locations are not appearing. now my logistics manager wants to maintain the long term planning for these two also.
    in md04,,, 3 storage locations available ..same like ms04 should follow
    provide the solution as soon as possible
    Thanks & Regards
    Prasad.

    Mukesh,
    To change the forecast from occuring at start of period ( month) you can always select the Schedule line Tab in MD61,MD62. then select period indicator as Day format as shown below
    Per. Ind          Date              Qty
    D     17.05.2010     30
    D     15.06.2010     40
    D     15.07.2010     50
    System will then plan PIR (forcast) based on dates assigned by user instead of being placed on the first day
    of the period. This will prevent forcast to fall into the previous month. Also it will resolve the capacity issue you are facing.
    If you have more questions please come back.
    thanks,
    Ram

  • Excluding storage location from MRP run in Long Term Planning

    Hi,friends,
         In my scenario , i want to exclude storage location from MRP run in long term planning.When i set storage location MRP indicator "2" in SPRO and SLoc MRP indicator "1" MRP4 in material master, i can exclude the storage location after run MRP with MD01/MD02,and i can see the expected result in MD04.But in Long Term Planning scenario the storage location can not be excluded after run MRP with MS01/MS02,and the requirements list in MS04 include the stock in the storage location i want to exclude. i dont know if i miss something.Plz give me some advice.
    Regards
    Joey

    Hi,
    Refer the OSS Note 208017 - LTP: Long-term planning and storage locations
    ==========================================================================
    Symptom
    In long-term planning (Transactions MSBT / MS01 / MS02 / MS03), the MRP indicator of a storage location for a material is not taken into account (material master, view MRP 2 [up to and including Release 3.1I] or MRP 4 [as of Release 4.0A]).
    The storage locations excluded by MRP or planned separately are also planned in the plant segment.
    Additional key words
    LTP, MM01, MM02, MM03, master data, MRP indicator, LGORT ...
    Cause and prerequisites
    The MRP indicator for a certain storage location of a material is only taken into account in operative planning (requirements planning, MRP).
    The long-term planning occurs exclusively at plant level.
    Solution
    This is no error. The system works as intended.
    The individual storage locations should not be distinguished in the long-term planning, in order to perform a comprehensive long-term planning.
    This is important, for example, within the kanban processing where the storage locations with kanban MRP are excluded from the MRP, but in spite of that should be included in the long-term planning.
    ==========================================================================
    Regards,
    Siva

  • Re: Long term Planning

    Dear All,
    I am trying to do Long term Planning. In my case I am not using SOP. Demand is entered into SAP through PIR (i.e. PIR).
    I want to see how much load is there on all the resources available.
    Please advice me how to proceed in this direction.
    Regards,
    Vivek Sharma

    Dear Vivek,
    Check with these steps,
    1.A plannig scenario has to be created for a plant in T code MS31 & for the same Planning scenario
    configuration settings has to be made in OPU5 for the planned orders for LTP.
    2.Requirements has to be given in MD61 in an inactive version and also after giving the requirements
    kindly remove the tick mark against version- active check box.
    3.Assign this plan to the planning scenario in MS32,release it and ensure the planning file entries are
    entered or created,the same can be checked using MS21.
    4.After taking LTP simulation run in MS02(individual material) or MS01 you can see the simulated
    planned orders obtained in MS04 T code.
    5.These Simulated planned orders can't be converted into production orders or it cant be used for any
    business confirmation purpose.
    6. For capacity planning analysis,use T Code CM38,
    Before that Ensure for all the work centers in CR03 which are used for operation under capacity header
    you have included the check box for Long term planning,otherwise in CM38 you can't see any capacity
    requirements data.
    7.Before executing CM38,ensure under settings---> general you are giving the period settings properly.
    Revert back incase of any more clarifications required.
    Regards
    Mangalraj.S

  • Query on Long Term Planning (MS31)

    During the creation of long term planning the following steps i followed before i am stuck at one point.
    1)T code MS31
    2)Planning Scenarion and detail
    3)Long term Planning Radio Button selection
    4)Planning period +Use Gross Lot Size (EX)
    5)BOM Selection ID 01
    6)Tab Planned Independent requirement details filled
    Now in Plant TAB when i give my plant id  the message is REQUIREMENT PLANNING IS NOT ACTIVE FOR MY PLANT CODE.
    Message no. 61139
    Please tell me how to make it active.
    Thanks in advance
    Rupesh Jha

    Dear Rupesh,
    Plz Refer to Mr. Mangalraj inputs on LTP
    1.A plannig scenario has to be created for a plant in T code MS31 & for the same Planning scenario
    configuration settings has to be made in OPU5 for the planned orders for LTP.
    2.Requirements has to be given in MD61 in an inactive version and also after giving the requirements
    kindly remove the tick mark against version- active check box.
    3.Assign this plan to the planning scenario in MS32,release it and ensure the planning file entries are
    entered or created,the same can be checked using MS21.
    4.After taking LTP simulation run in MS02(individual material) or MS01 you can see the simulated
    planned orders obtained in MS04 T code.
    5.These Simulated planned orders can't be converted into production orders or it cant be used for any
    business confirmation purpose.
    6. For capacity planning analysis,use T Code CM38,
    Before that Ensure for all the work centers in CR03 which are used for operation under capacity header
    you have included the check box for Long term planning,otherwise in CM38 you can't see any capacity
    requirements data.
    7.Before executing CM38,ensure under settings---> general you are giving the period settings properly.
    Revert back incase of any more clarifications required.
    Regards
    kumar

  • Long term planning analysis

    Hi,
    what's long term planning analysis and how to use the blw tcodes.. in this tcode its asking for planning scenerio, how to create it?? pls explain the usages of these t codes?? is it really used in user level??
    MCEA
    MCEB
    MCEC

    Dear,
    Basically LTP is simulative MRP to simulate and see all the results like production capacity plan/ raw material plan/ profit margin. here we are using the same master data like material master, recipe, BOM etc.
    In MS31 - you create a LTP version where you can mention the PIR version where you enter the planning data in MD61.
    Release this version and maintain the planning data like qty per period in MD61 with the version mentioned in MS31, make sure that the version is not active so that LTP consider this inactive qty data.
    Run MS01/MS02/MS03 etc to run simulative MRP.
    Results can be seen in MS04/MS05.
    Inn MSF0 you can see the capacity requirement and adjust the qty to se that 100% capacity is utilized.
    We can see the raw material requirement in Pur info system in MCEC/MCEA/MCEB/MCB&/MCB)
    Also refer my reply from this link also,
    Re: LTP - S012 Tables
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Capacity requirement for long term planning and make to order planning

    hello,
    anybody please guide me.
    my client using make to order scenarion and we are doing regulaly MRP run is MD50 with refernce to sales order.
    sales orders planning will follow for 2 to 3 months.
    at the same time my client wants to do long term planning also. to analize the capacity.
    for that he is creatind planning scenario and multi level planning with MS02 also.
    But the problem is when they are checking capacity requirement in cm38 it is showing only planning scenario load only. my client wants existing load and longterm planning load also. so they can plan the planning is sutibale in existing plan.
    so how can i get both plan in CM 38or is there any other T.code to get that data.
    please suggest me
    Thanks & Regards
    Bhakta

    Hi Pierre and Rajesh,
    When we create the simulation version, you have the possibility to choose the short-term planning. My point of view is, you can use the LTP fonction to do your scheduling for ex the next 3 months.
    I think it's what Pierre did. Am I right ?
    between to scheduling scenario to deliver my customer. With the simulation mode I can do my scheduling + use the MRP simulation to check if the raw material are available or not. Then use the MD04 to do the comparaison (or MS04 to compare between 2 scenario).
    But I found 2 problems :
    First : I don't find the parameters to show in the graphic MFS0, the planed fix order (I can only see the process order)
    Second : When my scheduling is finished, I want to update my operational planning with the simulation version. But I don't want to do article by article : when you have 400 references (raw mat, packaging, finish goods)  it's impossible (same issue like Pierre)
    Have you found a solution for this 2 points ?

  • How to consider the Purchase Orders in Long Term Planning

    Hi All,
    I wanted to include the Purchase Orders of Finished Material in Long Term Planning.
    I have selected the check box "Long-term planning: include firmed issues and receipts" in the Planning Scenario  but after LTP run system is not considering the Purchase Orders of Finished Materials for Planning.
    Regards,
    Shailendra
    Edited by: Shailendra Hadkar on Apr 5, 2010 12:41 PM

    Dear,
    Could you please explain usage of purchase orders for Finished product?
    Regards,
    SAP CONS

  • MS05 Long Term Planning

    I need  to stock available qty at long term planing (ms05) not calculate some location that qty status nettable.
    Example : Location   yy   stock onhand 100 EA   (Nettable)
                    Location   xx   stock onhand 10  EA    (Nettable)
         MRP                          display stock available 100  ea  but
         Long Term Planning     display  stock available 110  ea  (I need to display       100 ea  same MRP because MRP can set config exclude from MRP)  
    Please advise me?

    Hi,
    Can you make this Location stock XX as blocked or Restricted stock, then you will be able to exclude it from the Net requirement calculation.
    By deselecting the Blocked Stock or Restricted use stock for avaialbile stock in Avaialble stock configuration.

  • Long term planning in ECC for materials planned in SAP APO

    Hi SAP PP and APO Experts,
    I would like to know whether it is possible to plan a material in SAP ECC with Long Term Planning to create Simulative Planned Orders in ECC, when the MRP Type for the material is set to X0 (Planning in SAP APO).
    Warm regards,
    Prem

    Hi Dhaivakumar,
    Appreciate your prompt response.
    My business is MTS. I have made all settings for LTP planning for the material. (M|RP Type is set to X0-Planning in APO). When I execute the transaction MS02, I get the error message "Material 5200000013 J310  is not planned automatically. Message no. 61008". The details of the error message is:
    The material 5200000013 in plant J310 or in MRP area  is not included in automatic MRP because
    either the MRP data for plant J310 or MRP area  has not been created
    or an MRP type has been entered for the material in plant J310 or MRP area  that does not allow automatic MRP.
    Warm regards,
    Prem

  • Short term planning & long term Planning

    Hi PP Guru's
    !  . I have scenario like this I am having many trading Plant and the requirements are collected and Sales person preparing VA31
    Scheduling agreement for 1 week ( Short term ) also for 10 weeks ( long term ). In trading plant ( planning  / delivery plant ) there
    is no master data other than material master is Maintained in SAP system 
    2  . I am having Production Plant  and  need  to address this requirement May be through SPk 40 .
       My question is How the requirement should I transfer whether i need to manually create manually PIR and copy into Production
       Plant or is there any other way to transfer the requirements from SA ( VA31 )
    3. I want to adopt planniing strategy 52 - Planning without Final assembly because my Planning of certain SFG Procured externally
       should not trigger as per my FG requirements but as per my rolling Plan for 10 weeks for which I am PR having from MRP for
       Long term procurement material which is having lead time say 2 Months I am converting PR into PO using ME59N transaction with
      weekly Lot size .
    4.  For Short term Procurement material I have lot size as TB which is having less lead time say 2 - 5 days max.
    Could you please tell me using this strategy 52 how my PIR will consume and  Reduce and in which stage . If i am doing PGI using
    641 Movement type from Production Plant and PGR using 101 movement type .
    5. For my Procurement for Long term with A class material how can I reduce my inventory may be space constraint and Cost
       Constraint how can I receive this material for my Production.
    Marks will be awarded with Max for right answer
    Regards,
    jaya

    Hi,
    Hope you know the rules of the forum too many questions in single thread is not permitted.
    kindly break them to get proper reply.

  • Capacity planning Long-term planning CM38

    Hi,
    I am using Long-term planning scenario. I have created 12 PIRs for 12 months from January 2010 to December 2010. I executed MRP in MS01 in Lead scheduling Mode.
    There are 12 planned orders created for the 12 PIRs for the months Jan to Dec-2010. When I see the planned orders in MS04 the satrt and finish date for the planned orders are showing in respective months beginning.
    But when I check capacity in transaction CM38, all the 12 planned order for Jan to December months are displayed in the month of  January itself instead of the respective months from Jan to December and the work center is overloaded 199%.
    Please suggest to solve this issue.
    thanks and regards
    Murugesan

    Hi,
    In customization for Capacity Planning you can define you own selection profiles to work with. You may specify further selection criteria in selection profile and enhance query speed from database. Slection profiles are assigned to overall profiles and overall profiles can be called by CM07 transaction. CM38 is also working over an overall profile which you may learn from SAP help. This can also be changed.
    Also check OPC5 to limit max data for selection which might be useful.
    Regards.

  • Report on  Long term Planning

    Hi Gurus,
    Is there a std SAP report in PP which gives out the demand of  a material based on long term planning and also informs the actual consumption of the material other than MD62 , MD73, by which we can have a variance  of planned demand and actual consumption displayed.
    Edited by: Raj Muthu on Feb 1, 2008 11:14 PM

    Dear,
    You can use MD67 to see the demand in excel or on the screen...consumption i donot think you will get so easily...

  • T399D - Long-term planning allowed for a plant

    Hi gurus,
    I was checking the table T399D and it has the "Long-term planning allowed for a plant" field (T399D-SIMPL), but, I do not know where I can customise this!
    I was checking OMI8 and OPPQ (Parameters for DS section) transactions, but, I cannot find this field.
    Could you help me in order to know where I can customise this?
    Kind regards,
    Sandra

    Hi Sandra,
                     As it is correctly said that there is not much configuration required to Run LTP, but what you  basically need to maintain/configure is as follows-
    To carry out an annual planning or a rolling quarterly planning run you require information on the
    future stock and requirements situation. This means you need to know how sales and operations
    planning influence resources(conceptually)-
    In long-term planning you can also plan materials that usually require very little planning in
    operative planning, such as, materials planned using reorder point planning, bulk material, and
    materials planned using KANBAN. In long-term planning, you can plan these materials as you
    would MRP materials. This provides you with an overview of how these materials influence the
    demand program.
    The materials you want to plan in long-term planning must have already been planned in
    operative MRP.Apart from above conceptual knowledge what else you require to configure /maintain is-
    Planning Scenario(If you are running wity reference to it)-MS31
    And run it through MS02(with reference to planning scenario) where you have to put mandatory  MRP Control Parameters according to your business process eg.Processing key,create MRP list,planning mode,scheduling,firming planned orders.
    Hope it fulfils your purpose at some extent.
    Regards
    Chandra

Maybe you are looking for