Long-term planning: planning details of work center capacity
Hi,
we need to know what is the effect on planned production orders (generated by MPS, transaction MD40) of the flag <b>“long-term planning”</b> in planning details of work center capacity (table name: RC68K; field name: KAPLPL). We made a test analyzing planned orders scheduling details in <i>Stock requirements list</i> (MD04) and in the <i>Planning table</i> (CM21) in both cases: with "long-term planning" flag set and without this flag for the same work center.
The schedule of planned production order on that work center is the same in the two instance.
Could you suggest us something?
Thank you.
Hi Rudy,
Purpose for carrying out Long Term Planning to simulate impact of Future Demand Program on
u2022 Material Requirements
u2022 Capacity Requirements
u2022 Material Cost budgeting (activity by Accounts dept.)
T.Codes used -
u2022 Demand MD61, MD62, MD63
u2022 Scenario Creation MS31, MS32, MS33
u2022 LTP Variant Creation & Execution MSBT, SM37
u2022 LTP statistics Evaluation SM37, MS04
u2022 Data Set Up MS70, MSB&
u2022 Evaluation based on Set up data MCB), MCEA, MCEB, MCEC
u2022 Capacity Evaluation CM38
To Summarize -
u2022 In long-term planning, production plans for future demand programs are simulated using MRP runs with reference to the planning scenarios.
u2022 The parameters for the simulation in the simulation planning area are defined in the scenario.
u2022 The Evaluation of LTP Statistics enables identification of Material for which LTP processing was terminated.
u2022 The Data set for purchasing & Inventory Control enables reports for demand analysis
u2022 LTP run with setting for u201CLead time scheduling and capacity planningu201D enables simulation of capacity situation/overload on work centers.
Hope it is helpful to you.
Srini
Similar Messages
-
Blocking of work center capacity for capacity planning
How can i block a work center capacity for capacity planning during Machine breakdown( via a Preventive maintenance order)?
i believe it will reduce machine capacity, yet how can i view this, against the previous capacity? is there a possible report or can it be shown through a transaction?Hi,
In capacity header details screen not exactly as "can be used for capacity evaluation " but
"relevent to finite sceduling"
"can be used for several operations"
"long term planning"
these all indicators you can deflag this and check the results ,it may helpful to you. -
Dear,
I would appreciate it if some one can help me in finding the best source or information about the Long Term Manpower Plan in SAP HCM, I dont know if it is in the new releases of compensation management or personal development / career and succession planning?
We are in SAP 4.6 c and Portal 6.0 with ESS and MSS, planning to upgrade soon,
RegardsDear,
I would appreciate it if some one can help me in finding the best source or information about the Long Term Manpower Plan in SAP HCM, I dont know if it is in the new releases of compensation management or personal development / career and succession planning?
We are in SAP 4.6 c and Portal 6.0 with ESS and MSS, planning to upgrade soon,
Regards -
Work center-CApacity-Work force planning
Dear Expert !
Please tell me all necessary steps to configure Work center , Capacity and workforce planning .........please provide me all the information of business scenerio where I can use this at user level....with screen shot.
Thanks in Advance
ROBERT SMITH "HP"Check out below links....
http://help.sap.com/bp_bblibrary/600/Documentation/Q60_BB_ConfigGuide_EN_US.doc
http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPCRPPS/PPCRP_PS.pdf
Venkat -
Hi,
Is there any new tool or sub module introduced in the next release (ECC 6.0) of HCM on Long Term Manpower Planning (between 3-5 years) for planning the manpower composition? We are on 4.6C & I have checked the Personnel Cost Planning & Quota Planning functionalities in SAP HR. These don't suit our purpose.
Thanks & regards,
SameerHi ,
1.In the Longterm planning check till what duration your planning scenario is valid.
2. also if you have maintained the planned independent requirement check if the values are available for the future periods.
You can check this in primarily .
reg
DSK -
Work Center Capacity Shift Interval
Hello,
I'm looking for a function or Tables from which I can get Work Center Capacity Shift & Interval data, Transaction CRC3.
Any help in this regard will be highly appreciated.
Regards,
Hashir Ahmed.hi,
check these tables.
AFIH Transparent table Maintenance order header Application table (master and transaction data)
AFKO Transparent table Order header data PP orders Application table (master and transaction data)
AFRU Transparent table Order Confirmations Application table (master and transaction data)
AFVC Transparent table Operation within an order Application table (master and transaction data)
CABN Transparent table Characteristic Application table (master and transaction data)
CBPR Transparent table CO-ABC: Activity Master Table Application table (master and transaction data)
COEP Transparent table CO Object: Line Items (by Period) Application table (master and transaction data)
CRCA Transparent table Work Center Capacity Allocation Application table (master and transaction data)
CRHD Transparent table Work Center Header Application table (master and transaction data)
CSKS Transparent table Cost Center Master Data Application table (master and transaction data)
CSSL Transparent table Cost Center / Activity Type Application table (master and transaction data) -
Work Center Capacity Intervals
HI,
Where can I get the work center capacity interval dates i.e. valid from, valid to and corresponding week days that are being populated in the table control when you follow the following path in transaction IR03->Enter Work Center and Plant-> Press Enter->Go to Capacity Tab-> Press Capacity Button on the lower left hand corner->Press Intervals and shifts
My requirement is to calculate the weekly capacity of a work center. I have to find the valid interval for current date then find the number of working days in this interval so that I can use it in calculating the weekly capacity.
Regards,
Bharat.I de-bugged the main program behind IR03 and found out that the Valid-from-date is being calculated during runtime for all the records from table KAPA for given work center KAPID.
Anyway thank you all who cared to check the thread.
Regards,
Bharat. -
Hello experts
I am truing to compare between actual Work center capacity (I am using data source 2LIS_04_P_ARBPL).
And standard work center capacity (transaction cro3 in the R3)
I canu2019t find an info cube or data source that will help we extract the standard capacity.
Thanks.
Tal shalomHello,
You can use [0PP_C13 InfoCube (Capacity Load Utilization)|http://help.sap.com/bp_biv170/BBLibrary/documentation/B58_BB_ConfigGuide_EN_DE.doc]
Thanks
Chandran -
Block PP Work Center capacity when breakdown maintenance order create on that work center
Hi All,
My Client want to Block PP Work Center capacity when breakdown maintenance order create on that work center, how can i do it ..
Please help me.
PayalDear Sir,
I have Done Every think but still Production Order is create.
CM50
OIOI
CO02
Payal -
Work center capacity header freezed
Dear Gurus,
we're not able to edit the work center capacity header. not able to edit the start and finish times.
it is happening only for one work center. in other work centers same capacity category is editable.
Please help us in resolving this.
Regards,
GowriHi,
Check your work center categeroy definition for which edit is not possible.
The work center category determines which data can be maintained in a work center.
Each work center category is assigned to the applications (for example, production, plant maintenance or quality management) whose menus allow you to maintain work centers with this category.
Each work center category has a number of screens assigned to it which the system displays when work centers of this category are displayed. The screens contain groups of fields (for example, scheduling data). Depending on the work center category, you can make field selections on these screens (for example, defining required entry fields).
Thanks,
nandha -
Any ideas what tables work center capacity gets its data?
I am looking at cube 0pp_c13 in BW and it looks at capacity. I can't seem to find the underlying table it pulls from to populate the structure. would anyone know where to look? I've looked in the code and it seems like it is already filled by the time it gets to the extractor so i can't tell where it pulls.
thanksHi,
Pl check table:CRCA
Work center capacity is allocated here.
Regards,
Senthilkumar SD -
Work center capacity graphical view
Greetings!
How do I see work center available capacity in graphical form?
Also how can I see work center capacity utilization in graphical form?
-HemantHi
I don't exactly remember, the T-CODE is CM02 or CM03.
Regards
MUHAMMAD HUNAIN AHMED -
Maintenance Work Center : Capacity Planning CM01
Hello Gurus,
We are using T-code CM01 to determine the Requirements / RemAvailCap of the Maintenance Work Orders in a given Maintenance Work Center.
After executing CM01, the detail capacity list contains Not Scheduled orders( CRTD )and capacity of these not Released orders also taking into consider.
How to restrict CM01 Order selection based on the work order System status or User status ?
I found below discussions on SCN but couldn't get precise answere.
Plant Maintenance: Capacity planning CM01/ CM07
Configuring profiles in CAPACITY PLANNING (CM07)
Please help.
Thanks in Advance
Ashok MThere are a few ways:
Create a new status profile via BS42 and assign the REL status only (see image 1). Then in the CM01 display screen, use menu path: Planning->Selection->Order and enter the status profile created above (see image 2)
Create a new selection combination via OAP0. In the CM01 display screen, use menu path: Planning->Selection->Combination and enter the selection combination created above (see image 3)
The above settings can then be defaulted via the various capacity planning profiles. -
Function with production/planned orders of a work center or capacity
Hi,
does anybody know if a function exists which we could use in a tailor made report, which will list all production and planned orders for a given work center or capacity ? The aim should be to create a report which is more or less equal to the capacity evaluation overviews in CM01-CM07, but then in ALV and with customer specific fields in it.
Many thanks for any valuable feedback !
Kristof Wylin.Will be done in another way. Orders will be collected via KBED.
-
Long term, interactive planning
Hi,
I have having problem in long term planning
In MS annual planning, i can see that till 2008 planned order has been created.Ater firming and run MD43, i can see only few months not all month for next year.After i save this and go to MD15 i cant see required planed orders for next year.
Please let me know where exactly is the problem.I request everyone to give me some solution as it is ver urgent.
regards
satyajit kumarHi Geeta,
I had checked the period that time only. It's ok. I think problem is some where else. Anyway thnx for your response.Plz get back to me if you find anyhting else on this issue.
Regards
Satyajit Kumar
Maybe you are looking for
-
Kdl40s5100 picture cuts out for about 1 minute then comes back
when i'm watching programs the pictuture (and sound) will cut out then return in about one minute... this will repeat itself about every 30 -45 minutes.... problem does not occur when watching videos - only cable or antenna
-
I have two questions here, or I would say two cases here to discuss. 1. I have shutdown my standby db and unmount archive location from server for 2 hours. After that mount the file system again and bring up the standby DB. As we we ASYNC Standby rec
-
Hello, In HFM Data forms, is there a ways that I can make the Form columns dynamic - I wanted my columns to pull the base members of the entity selected in POV. Is that possible? Thanks, Samy
-
Can Someone Help With My Fonts?
I understand that OS 10.4 won't use my old bitmap fonts, but what is the solution? There are programs that convert Postscript and True Type to bitmap, but what can I do with my bitmap fonts? Do I just have to buy all new fonts? G5 Quad Mac OS X (10
-
Problems installing Mastersuite CS6
I've twice downloaded the files for Mastersuite CS6. Each time it says that a restart is imminent - ignore or quit. First time I ignored and it didn't work. I downloaded the files again overnight, with the same error message. I restarted and the file