Long term planning-Scheduling problem

Hi Experts,
When I am doing Long term planning run MS02, i am facing the following problem:
There are 10 stages of operations to make a finished product. Each stage having different order types and planned orders are created at each stage.
For the last stage material i am doing the Long term planning ( ie. Raw material)
After running MS02, The results are like this:
the scheduling for the first 6 stages are according to the requirement dates.
But the last 4 stages the scheduling is not correct. The system is combining 10 days requirement and giving only one planned order.
I want seperate planned orders date wise.
Please give me a solution.
Thanks & Regards
Bala

Hi Dharma,
There is no planning calendar or period lot size assigned for any materials.
MRP type is PD for all materials except the long lead time material and the lot size is EX.
For the long lead time material ( ie. the bottom stage material) MRP type is M1 and lot size EX.
Thanks & Regards
Bala

Similar Messages

  • Long Term Planning get problem!

    Hi Gurus!
              I use LTP for simulation but after I run MS01, I check in MS04, no SimPlannedOrder is generated.
              I'm used to do with LTP many time before but it never happend like this.
              When I explode IndReq in MS04, It has a message "Coverage not provided by master plan"
    More infors: All FG ans RM in my client are maintained with Range of Coverage profile(Dynamic Safty Stock). Last projects I've never use Rang of Coverage Profile and LTP has never  gotten problem.
    Is it because some SAP note or I forgot something?
    Please advise me.
    Best Regards,
    Tony

    Dear Guru!
          Somebody help me?
    Regards,

  • Long term planning,mid point scheduling,finite scheduling

    Dear Sir,
    Please explain the Long term planning,mid point scheduling and finite scheduling in simple words
    thnx.

    Hi,
    LTP: Long term planning used to simulate your future production plan. Based on your future production plan, you can check by simulation, loading the products requirements in the inactive planning version and defining the inactive planning version in the scenario and you can execute the MRP run. Then the system will create the capacity requirements and you can see the overloads. Based on this simulation run, you can include any new work centres and increase the manpower or increase the shifts.
    Finite Scheduling: This will consider the real details, like the no of work centres and working hours per day and working days in a year and considering the existing loads. This is called finite scheduling. R/3 does infinite scheduling. If the capacity not exist also you can release the production orders.
    Regards,
    V. Suresh

  • Capacity requirement for long term planning and make to order planning

    hello,
    anybody please guide me.
    my client using make to order scenarion and we are doing regulaly MRP run is MD50 with refernce to sales order.
    sales orders planning will follow for 2 to 3 months.
    at the same time my client wants to do long term planning also. to analize the capacity.
    for that he is creatind planning scenario and multi level planning with MS02 also.
    But the problem is when they are checking capacity requirement in cm38 it is showing only planning scenario load only. my client wants existing load and longterm planning load also. so they can plan the planning is sutibale in existing plan.
    so how can i get both plan in CM 38or is there any other T.code to get that data.
    please suggest me
    Thanks & Regards
    Bhakta

    Hi Pierre and Rajesh,
    When we create the simulation version, you have the possibility to choose the short-term planning. My point of view is, you can use the LTP fonction to do your scheduling for ex the next 3 months.
    I think it's what Pierre did. Am I right ?
    between to scheduling scenario to deliver my customer. With the simulation mode I can do my scheduling + use the MRP simulation to check if the raw material are available or not. Then use the MD04 to do the comparaison (or MS04 to compare between 2 scenario).
    But I found 2 problems :
    First : I don't find the parameters to show in the graphic MFS0, the planed fix order (I can only see the process order)
    Second : When my scheduling is finished, I want to update my operational planning with the simulation version. But I don't want to do article by article : when you have 400 references (raw mat, packaging, finish goods)  it's impossible (same issue like Pierre)
    Have you found a solution for this 2 points ?

  • Extracting LTP (Long Term Planning) Data from SAP ECC to SAP BW

    Hello all
    Here is the task in hand. There is a standard report that Production Planners execute post their MRP/LTP runs. This report can be accessed through T-code "MCB)". The program in action is RMCB1200. I tried looking for any standard extractors but to no avail. I would be fine to know either or both of the following:
    An extractor
    All the primary tables involved ( I have found a few tables through the program but a list by some expert will help me understand that I have not missed anything significant)
    Also, if anyone has done this before, how was your experience with the extraction in terms of extraction volume and performance.
    Regards
    Gajendra

    After further digging, here is some information that I found out.
    T-code
    Program
    BADI
    MSEX
    RMDMRPEXTRACT02
    MD_SR_LIST_EXTRACT
    This could possibly provide the data required. The program can be scheduled and the output can be managed by SPRO settings for Extraction Mode. I am running tests to confirm if it provides me the correct information and matches with MCB) output.
    Here are some tables, just for reference:
    LTP Tables: PLSC, PBHI, PLPT, MDTP, PLPR, PLPB
    MRP Records:
    MDKP
    MRP Document Header Data
    MDTB
    MRP Table Structure (no data)
    PLSC
    Planning Scenario (Long-term Planning)
    MDFD
    MRP Firming Dates
    MDVM
    Planning File Entries
    S094
    LIS -- Stock/Requirements Analysis

  • I can't see planned order in Long Term Planning Stock/requirements list.

    Hi
    I am trying to use Long Term Planning in SAP.
    I created scenario dates from 01.03.2011 to 03.09.2011. Between those dates i entered planned independent requirements as 300.
    When i went to Long Term Planning Stock/requirements list, i can see all planned independent requirements but i run Multilevel single-item planning and then when i went to  Long Term Planning Stock/requirements list again, i couldnt see planned order for planned independent requirements.
    So what is the problem? Can anyone help me please?
    Thank you.

    HI
    check the planning scenario in MS31 and the PIR assignment in MS31 also check the plant assignement.
    Check In MD61 you have enter PIRs in simulation version and the same version is to assigned in planning scenario
    Also check T code OPU5 for LTP setting for planned orders
    Regards
    Anupam Sharma
    Edited by: anupam sharma on Sep 3, 2010 2:33 PM

  • Capacity planning Long-term planning CM38

    Hi,
    I am using Long-term planning scenario. I have created 12 PIRs for 12 months from January 2010 to December 2010. I executed MRP in MS01 in Lead scheduling Mode.
    There are 12 planned orders created for the 12 PIRs for the months Jan to Dec-2010. When I see the planned orders in MS04 the satrt and finish date for the planned orders are showing in respective months beginning.
    But when I check capacity in transaction CM38, all the 12 planned order for Jan to December months are displayed in the month of  January itself instead of the respective months from Jan to December and the work center is overloaded 199%.
    Please suggest to solve this issue.
    thanks and regards
    Murugesan

    Hi,
    In customization for Capacity Planning you can define you own selection profiles to work with. You may specify further selection criteria in selection profile and enhance query speed from database. Slection profiles are assigned to overall profiles and overall profiles can be called by CM07 transaction. CM38 is also working over an overall profile which you may learn from SAP help. This can also be changed.
    Also check OPC5 to limit max data for selection which might be useful.
    Regards.

  • T399D - Long-term planning allowed for a plant

    Hi gurus,
    I was checking the table T399D and it has the "Long-term planning allowed for a plant" field (T399D-SIMPL), but, I do not know where I can customise this!
    I was checking OMI8 and OPPQ (Parameters for DS section) transactions, but, I cannot find this field.
    Could you help me in order to know where I can customise this?
    Kind regards,
    Sandra

    Hi Sandra,
                     As it is correctly said that there is not much configuration required to Run LTP, but what you  basically need to maintain/configure is as follows-
    To carry out an annual planning or a rolling quarterly planning run you require information on the
    future stock and requirements situation. This means you need to know how sales and operations
    planning influence resources(conceptually)-
    In long-term planning you can also plan materials that usually require very little planning in
    operative planning, such as, materials planned using reorder point planning, bulk material, and
    materials planned using KANBAN. In long-term planning, you can plan these materials as you
    would MRP materials. This provides you with an overview of how these materials influence the
    demand program.
    The materials you want to plan in long-term planning must have already been planned in
    operative MRP.Apart from above conceptual knowledge what else you require to configure /maintain is-
    Planning Scenario(If you are running wity reference to it)-MS31
    And run it through MS02(with reference to planning scenario) where you have to put mandatory  MRP Control Parameters according to your business process eg.Processing key,create MRP list,planning mode,scheduling,firming planned orders.
    Hope it fulfils your purpose at some extent.
    Regards
    Chandra

  • Sap mm md04 and ms04 stock requirement and long term planning issue

    Hi guru's,
    i have one issue regarding MD04 and MS04. in MD04 3 storage locations were showing. in that the stock in 2 storage locations was excluded due to no long term plan.
    now if we see in ms04, these 2 storage locations are not appearing. now my logistics manager wants to maintain the long term planning for these two also.
    in md04,,, 3 storage locations available ..same like ms04 should follow
    provide the solution as soon as possible
    Thanks & Regards
    Prasad.

    Mukesh,
    To change the forecast from occuring at start of period ( month) you can always select the Schedule line Tab in MD61,MD62. then select period indicator as Day format as shown below
    Per. Ind          Date              Qty
    D     17.05.2010     30
    D     15.06.2010     40
    D     15.07.2010     50
    System will then plan PIR (forcast) based on dates assigned by user instead of being placed on the first day
    of the period. This will prevent forcast to fall into the previous month. Also it will resolve the capacity issue you are facing.
    If you have more questions please come back.
    thanks,
    Ram

  • Long Term Planning Issue - Transaction MS04

    Hi Experts,
    I have two problems looking for solution from you.
    1. Transaction Code MS04 -> After entered Planning Version, Material and Plant... I can see list of orders in the report.  If I click Production Order, Planned Order, Inspection Lot document Element Details (on left hand additional function) and I am able to double click and display these documents.  However If I double click Material Reservsation document It is not allowing me as I can't see "Display element (F7) Icon.   How do I get the display element icon for Material reservation document also.
    2. We have a lot of Quality Inpsection lots documents when we display in MS04 report but the problem here it is peggeging as requirements in Long term planning report.  We want to just display the document here not as requirements. 
    Please let me know the solution for above two.
    Regards
    Rc Gopi

    Dear NNeeti,
    1.In CM38-->in the top menu --->under Planning ->Profiles->Overall Profile.
    2For this over all profile check the Details in OPA6 T Code and find out the option Profile assigned to this over all profile.
    3.Edit the details of this Option profile in OPA3 (change the number of days as 730 instead of 365 in the finish date).
    Check with this setting in CM38 and proceed.
    Check and revert
    Regards
    S Mangalraj

  • Long-term planning: how can I reorganize "bulk" independent requirements ?

    Hello,
    Due to some circumstances I have dependent simulative requirements with no relation to any independent requirements.
    I thought that with ms01 (Processing key NEUPL -Regenerative planning and Planning mode 3 - Delete and recreate planning) those independent requirements will
    be deleted because the former independet requirements are no more existing.
    But they remain existing. (in mfs0)
    How can I reorganize "orphaned" independent requirements in long term planning.
    Thanks for any help
    Thomas

    Thanks a lot for answer.
    The subject of my original-question was
    wrong. It should say "dependent" requirements
    instead of "independent" requirements.
    I solved the problem by deleting the
    respective entries in MDSM-Table
    But anyway, the usage of md74/75 was a
    good recommandation, thanks very much.

  • Long term Planning - capacity issue

    Does any one have a way of running Long Term Planning in SAP.
    When checking CM38 for production volumes, the start dates of
    the planned orders always fall into the previous month from the
    forecast (the monthly forecast is always placed on the first day
    of the period and due to lead time scheduling the planned orders
    to satisfy that forecast fall into the previous month). If i check the
    capacity it show in same month for different month requirment.( it is clubing the requirment)
    Though capacity scene was created from June to August , system shows loading from May month.
    Month wise loading and availability are shown clubbed in capacity planning sheet.
    Thanks in advanc....

    Mukesh,
    To change the forecast from occuring at start of period ( month) you can always select the Schedule line Tab in MD61,MD62. then select period indicator as Day format as shown below
    Per. Ind          Date              Qty
    D     17.05.2010     30
    D     15.06.2010     40
    D     15.07.2010     50
    System will then plan PIR (forcast) based on dates assigned by user instead of being placed on the first day
    of the period. This will prevent forcast to fall into the previous month. Also it will resolve the capacity issue you are facing.
    If you have more questions please come back.
    thanks,
    Ram

  • Long Term Planning : Requirements from "Consumption based planning" missing

    Hello,
    I'm trying to use long term planning ( MSBT,MS01..) for simulation. In the scenario I've set up I want to have all actual requrements and orders as well as fixed orders.
    The problem is that requirements(=forecast) for materials with consumption based planning ( MRP type =VV ) are not transferred from the operative planning. How can this be achieved ?
    Best Regards
    Bernt

    Hi,
    Hard to say... have you looked in the details of the VV MRP setting, your LTP scenario, or your copy transaction in case there is some parameter about this?
    In case you are looking for information about this process, here is a good document  with a detailed description of the Long-Term Planning Process in SAP (with detailed T-codes as well): http://expertplug.com/materials/training/long-term-planning-in-sap
    You have a preview and a detailed description to see if it suits your needs.
    Cheers
    Matthieu

  • Long-term planning: planning details of work center capacity

    Hi,
    we need to know what is the effect on planned production orders (generated by MPS, transaction MD40) of the flag <b>&#8220;long-term planning&#8221;</b> in planning details of work center capacity (table name: RC68K; field name: KAPLPL). We made a test  analyzing planned orders scheduling details in <i>Stock requirements list</i> (MD04) and in the <i>Planning table</i> (CM21) in both cases: with "long-term planning" flag set and without this flag for the same work center.
    The schedule of planned production order on that work center is the same in the two instance.
    Could you suggest us something?
    Thank you.

    Hi Rudy,
    Purpose for carrying out Long Term Planning to simulate impact of Future Demand Program on
    u2022 Material Requirements
    u2022 Capacity Requirements
    u2022 Material Cost budgeting (activity by Accounts dept.)
    T.Codes used -
    u2022 Demand      MD61, MD62, MD63
    u2022 Scenario Creation     MS31, MS32, MS33
    u2022 LTP Variant  Creation & Execution     MSBT, SM37
    u2022 LTP statistics Evaluation     SM37, MS04
    u2022 Data Set Up     MS70, MSB&
    u2022 Evaluation based on Set up data     MCB), MCEA, MCEB, MCEC
    u2022 Capacity Evaluation     CM38
    To Summarize -
    u2022 In long-term planning, production plans for future demand programs are simulated using MRP runs with reference to the planning scenarios.
    u2022 The parameters for the simulation in the simulation planning area are defined in the scenario.
    u2022 The Evaluation of LTP Statistics enables identification of Material for which LTP processing was terminated.
    u2022 The Data set for purchasing & Inventory Control enables reports for demand analysis
    u2022 LTP run with setting for u201CLead time scheduling and capacity planningu201D enables simulation of capacity situation/overload on work centers.
    Hope it is helpful to you.
    Srini

  • Long Term Planning-Planning File Entry

    Hi Gurus/Friends
    In the long term planning after PIR with inactive version and creating Scenario, assinging versions, Plants,....then
    during Release+Save it is giving the Result of Planning File Entries
    Logically the system has suppose to give the Number of Planning File Entries in Propotionate to the Specific Planning Scenario number and materials inside
    But it is giving for all the Materials inside the Plant
    Is there any settings to restrict the Planning File Entry creation w.r.t Planning scenario during Release+Save
    other than the solutions through Transaction MS20,MS22 and MSAB
    (Because during Release+save logically it has to call the MS22 t.code  and do planning file entries for the materials in that scenario)
    Awaiting for reply
    thanks
    K.Prabakaran

    Hi,
    Please Refer Below SAP help .
    *Releasing a planning scenario*
    You first have to release a planning scenario before you can plan it in the long-term planning run. When you release the planning scenario, the system creates planning file entries for all materials in all the plants allocated to the planning scenario. There is a separate planning file entry for this purpose. This guarantees that your operative planning is kept completely separate from your simulative planning. This long-term planning file contains all the materials that are also contained in the operative planning file. After the release, every change relevant to MRP triggers an entry in the planning file as in operative planning.
    Pradeep
    Edited by: Pradeep Kumar on May 9, 2008 4:22 PM

Maybe you are looking for

  • Ios 5 problem with Calender

    After upgrading to Ios 5, my calendar events are all gone and the plus button in the calender is gone. I don't use Outlook btw. Please help!

  • Finding the "best" application for backing up

    Any advice for a computer illiterate who needs to find the best app to use for backing up to a portable external drive. I have seen many mentioned. I need a user-friendly, cheap, reliable one (for tiger). I am computer dumb, so please understand if I

  • PrintOut method Fails

    We have a remote system that uses Crystal Reports XI.  Lately, our application has been crashing apparently due to Crystal.  The most recent change is that we put a laser printer at another remote site that connects to this site.  The connection curr

  • Flash Professional CC Audio Problems

    I recently purchased Flash Professional CC. When using the trial version, I bumped into a pretty serious error.. When importing audio (or opening a previous .fla file that has audio), upon hitting play I'm confronted by a loud buzz, and no audio. The

  • French translation of "Back* button

    Hello, when logging on to the Web UI in french the "Back" button of the Web UI (not the one from the Internet Explorer) is displayed in german (Zurück). I searched via transaction SOTR_EDIT for all "Zurück" texts in language french and found the foll