LPA Sheduling Agreement can not do GR
Hello all:
I creat a LPA Sheduling Agreement,and generate Forc/JIt Sched.the delivery time is today
But when i use MIGO can not make GR
Error message is"Document 5500000149 does not contain any selectable items"
Someone can give me some advice?
Thanks a lot
Hi!
Yes, in a LPA Scheduling Agreement the fact that no messages have been transmitted to the vendor is the reason why no goods receipts can be posted.
See the SAP Note 874264 (MB01/MIGO: Default quantity for goods receipt posting) about this:
This document type 'LPA' has been customized to work with Release Documentation:
Under the IMG path:
Materials Management
-> Purchasing
-> Scheduling Agreement
-> Define Document Types
you will see that the document type LPA has the "Indicator for scheduling agreement release documentation" (V_T161-LPHIS) set.
Starting with Release 4.5, for Scheduling Agreements with Release Documentation (this is, those with document type LPA), the open quantity is determined on the basis of the quantity known by the vendor:
When goods receipting a scheduling agreement that uses release documentation, in order to process a goods receipt, the system proposes the quantity from the last transmitted output message (please, take into account that this logic only works with scheduling agreements with release documentation (LPA), not so with LP).
This information can also be seen in the note 493404 - FAQ: Scheduling agreements.
The explanation given in this message is contained under the question number 9.
I hope this helps!
Esther
Similar Messages
-
Forwarding agreement can not release; Check items and calculation sheets.
Hi Experts,
While releasing status of a forwarding agreement to getting error message "Agreement can not release; Check items and calculation sheets''.
Please refer the screen shot attached and suggest.
Thanks & Regards,
Shaktiprasad DashHello Shakthi,
Firstly, have you maintained TCCS in your forwarding agreement?
You migt have inserted new item. However, there are no TCCS maintinaed in that agreement item.
In such cases those error messages are displayed. Restricting you from releasing the agreement.
Other cases:
is your TCCS local?
If your TCCS is global then ideally the charge usage should be any of the below: "customer", "Customer & service" or "ALL" for Forwarding Agreement to consume it.
For Local TCCS by defalut charge usage will be set to "Customer".
If Local, check whether have you missed any mandatory fields like amount, Currency.
If there are any % charge line, then the refrence number would have been missing or you might be referencing incorrectly.
For Global TCCS if any of the above is incorrectly maintianed it will not allow you to save the TCCS.
If you can attach the screenshot of the TCCS it will be helpful for me to solve your issue.
Best Regards,
Dimpu -
I am unable to open any pdf files because I have not accepted the end user licensing agreement for adobe reader. I can not find the accept button. I have a mac.
What is your screen resolution? Can you post a screenshot of what you see: https://forums.adobe.com/thread/1070933
-
I can not open documents using adobe reader because I have to accept "end user agreement". How do I get to agreement?
thx but the only thing that happens when I open Adobe Reader is that a small icon appears in the bottom-line. There is no dialogue box where I can accept!
-
Sheduling Agreement item are not appearing in MIGo
Hi,
Good receipt (MIGO) for Sheduling Agreement some items are not display(not appear in item detail screen in MIGO)
Delivery shedule is maintain and SA is released
where to check to slove this problem.
shakirHi,
Very help full tip ,now it is showing item with zero quantity
but not the missing item.
Hope to get some tip ...to slove.
shakir -
When I try to download apps, a message appears saying that to move forward I have to agree to the new terms of the contract, but does not allow me to agree and not low Apps. Someone can explain what is happening?? thank you
Delete some stuff to make room on the device.
iCloud is not local storage and has nothing to do with your situation. -
after update.. i can not start the ipad, when i press agree in the terms ...it will freeze and the screen not working///help please
What to Do When Your iPad Won't Turn On
http://ipad.about.com/od/iPad_Troubleshooting/ss/What-To-Do-When-Your-Ipad-Wo-No t-Turn-On.htm
iOS: Not responding or does not turn on
http://support.apple.com/kb/TS3281
iPad Frozen? How to Force Quit an App, Reset or Restart Your iPad
http://ipadacademy.com/2010/11/ipad-frozen-how-to-force-quit-an-app-reset-or-res tart-your-ipad
iPad: Basic troubleshooting
http://support.apple.com/kb/TS3274
iOS: Resolving update and restore alert messages
http://support.apple.com/kb/TS1275
iPad: Unable to update or restore
http://support.apple.com/kb/ht4097
Cheers, Tom -
I can not get past the license agreement and term and conditions page after updating my i5 IOS
Restart your phone and if that doesn't help, reboot the device.
Restart the iPhone by holding down on the sleep button until the red slider appears and then slide to shut off. To power up hold the sleep button until the Apple logo appears and let go of the button.
Reboot the iPhone by holding down on the sleep and home buttons at the same time for about 10-15 seconds until the Apple Logo appears - ignore the red slider if it appears on the screen - let go of the buttons. Let the phone start up. -
Link from the Sales order/Sheduling Agreement to planned order
Hi,
SAP SD Gurus,
Can you please tell me the the link from sales order/sheduling agreement to planned order.
Thanks,
Anand. I would like to know why only for this character the values is not displayed.
Dear,
Please check the relevant characteristic in CT04
select the addnl data tab
You can find the table name and field name
and also you can find the check mark in not ready for Input in procedure of value assignment -
Converting Purchase requisition to Shedule agreement shecule lines
Dear All gurus,
can we convert already available purchase requisition to Shedule agreement shedule lines by any means of MRP run or so.
Regards,
Vimleshproblame is that this purchase requisition i am creating through production order release and for external processing which is not haveing any material number
so that why all these purchse requision with acc assingment with F and items cate as L , I need to convert to shedule lines in sheduleing agreement which already exist.
so i can not maintain the source list for the same.
Pl suggest
Vimlesh -
Sheduling Agreement for import
Hi,
Here i want to configure sheduling agreement for import vendors.I follow the steps
ME31L - ME38 - MIGO .Is there necessity of inforecord or source list in this Scenario.And pricing condition as per pricing procedure is not picked up while making the SA.
I have check the schema group settings for vendor as well as pur.org.,but it found ok.Still the condition not picked up.
Pl suggestHi,
In the create / change scheduling agreement transaction, select the item for which additional conditions are to be entered. Click on button 'Item Conditions', enter / choose the validity period. Maintain the required conditions & save.
If clearing agent (other than the supplying vendor) is to be assigned to the condition you can go the the details of the condition & assign the required vendor.
Regards,
Prashant -
Import conditions in Sheduling Agreement
Dear All,
We use Import schema group in Import vendor master so that whenever we create PO automaticlly the conditions are available in PO for CVD and customs so we can enter relavant rate.
but in case of sheduling agreements for same vendor where we enter such % of CVD and customs.
Pl suggest
Regards,
VimleshHi Vimlesh
I am facing an similar issue, trying to post planned delivery cost for the Import Schedule agreement ( CVD,Customs,etc..). But even though after maintaining supplementary pricing procedure for the gross price condition and maintaining the delivery cost conditions in Schedule agreement, MIRO is not allowed for posting delivery cost for Schedule agreement.
Experts please help!
Regards
Arvind -
Hi All,
May I know what is LPA Scheduling Agreement and how do we set up messaging functionality for these Scheduling Agreements?
Kindly revert ASAP.
Thanks
SuryaYou can use scheduling agreement with or without release documentation.The advantage of working with scheduliing agreement release documentation is that you always have a record of when you sent which delivery schedule information to your vendor,which you can display at any time.
Without release documentation(Document type LP)
The delivery schedule lines have official character-that is to say,they are transmitted to the vendor as they are saved in the system.The system does not document in detail releases aganist the scheduling agreement that have been sent to the vendor.Therefore,in the case of the document type without release documentation,the message control facility should be set up in such a way that a message is immediately sent to vendor if any changes are made to the delivey schedule stored in the system.
With release documnetation(Document type LPA)
If you use scheduling agreement with release documentation,the delivery schedule lines are not transmitted directly to the vendor.Intially ,the lines of the delivery schedule stored in the system for an LPA scheduling agreement for an internal information only.A message informing the vendor of your material requirements cannot be transmitted to the vendor until you explicitly create an SA release,that is forecast (FRC) or Just in Time(JIT) delivey schedule.Through this process,you can change the way schedule lines are represented.With release documentation,you can disply the SA releases(delivery schedules) transmitted to a vendor over a certain period of any time.This enables you to trace precisely when you sent which information to vendor.
Chk the link below for profile creation and assigning the same to SA, for LPA process
http://help.sap.com/saphelp_47x200/helpdata/en/75/ee0ef255c811d189900000e8322d00/frameset.htm
Hope this will help you
BR,
Krishna -
Shedule agreement with item category D
Dear All,
can i create an shedule agreement for services using item category 'D'
Regards
mspPlease check the allowed item categories in the cutomizing under MM-> Purchasing-> Scheduling agrement-> define document types. Standard SAP has not defined SA to be created for item category D.
However you can add it over here and check if it works.
Edited by: Subramaniam Iyer on Dec 1, 2008 9:57 AM -
Hi
1. I have craeted a Shedule agreement ( Doc type LP ) - ME31L
2. Created the Shedule line - ME38
3. Not able to create the SA Release - ME84
What can be the reason?
RegardsIF THERE IS NO RELEASE STRATEGY THEN U SHOULDNOT EXPECT THAT UR AGGREMENT WILL GO FOR A RELEASE.
U HAVE TO DEFINE CHARACTERISTIC THRU TCODE CT04
DEFINE CLASS THRU CL02
DEFINE RELEASE GROUP,CODE,INDICATOR,STRATEGIES THRU SPRO
ASSIGN OBJECT WITH STRATEGY THRU T CODE CL20N.
REGARDS,
INDRANIL
Maybe you are looking for
-
SAP GRC NF-e 10.0 - Problema durante Upgrade (mensagem /XNFE/APP 011)
Boa tarde a todos! Realizamos o "Upgrade" do SAP GRC NF-e da versão 1.0 para a versão 10.0 (SLL-NFE 900, nível 0008) e estamos convivendo com um problema em uma mensagem XML do PI. Na transação SXMB_MONI, monitor de mensagens processadas, ao filtrar
-
TOO_MANY_ROWS leaves variable in indeterminate state - Is this a bug?
Hello all, Please see below that despite the handled exception, PL/SQL still alters the coontents of the variable. - I cannot reply on its initial state if there is a possibility of a TMR exception ..... it seems. SQL> select * from v$version; BANNER
-
External hard drive has to be updated each time I boot up.
Hi I have moved my iTunes music to an external Hard drive (F:). I have pointed the software to the new folder and iTunes successfully recognizes it and all works fine. The problem occurs when I reboot. I seem to have to "add the folder" (File > Add F
-
Soundblaster X-Fi Surround 5.1 Beta Driver 1.02.0061 Problem
Plain and simple. The Driver does NOT detect my USB Card.
-
Help! Download shuts down
When I initiate updating of my older version 6.0.4.2 the download lasts less than a minute and then shuts down while the ITunes download site opens to the page that states: "Thank you for downloading Itunes". I have repeatedly tried to download and e