LSMW about WBS

Hi all, i ask you how make LSMW about WBS structure with 6 levels for example.
I have WBS structure like this:
Level 1: F-07
Level 2: F-07/01
Level 3: F-07/01-IN
         F-07/01-RN
Level 4: F-07/01-IN-MN
Level 5: F-07/01-IN-MN-01
         F-07/01-IN-MN-02
         F-07/01-RN-MN-03
Level 6: F-07/01-IN-MN-01-HM
So, how can i make LSMW so be it every time make new row for every one new WBS element in one Project, when upload xls file.
My Projet have on Level 6, maximum 9500 rows , so i need yous help.

Hi Keen,
Please try using t-code MBBS.
Regards
Tushar

Similar Messages

  • The question about WBS code

    the WBS code is like GB08FA-B-101-TC1-TRA-001. and so on.
    now i should how to define project coding mask.
    Please explain me all the steps to be required.
    Thanks in advance!

    thanks a lot.
    the first      level code of WBS is  GB08FA
    the second level code of WBS is  GB08FA-B
    the third     level code of WBS is  GB08FA-B-101
    the fourth   level code of WBS is  GB08FA-B-101-TC1
    the fifth      level code of WBS is  GB08FA-B-101-TC1-TRA
    the sixth    level code of WBS is  GB08FA-B-101-TC1-TRA-001
    now i should how to define project coding mask.
    Please explain me all the steps to be required.
    Thanks in advance!

  • About wbs status check ----GR/IR balance check

    hi,dear all
    When I set wbs to "clsd",can system check the purchment order's gi/ir balance of the wbs?(the account assignment of the po is the wbs,the po's goods receive is completed,all commitment is close ,but invoice has been done partially, not complete,the gi/ir balance is not zero.)
    If it can not ,is there any else method can do this?
    thank you!
    maojian

    Hi Jian,
    Since the project is not fully complete, you can use the Status "TECO". This will ensure that no fresh commitments will be allowed. If required you can even use "lock" in the WBS to lock Master data /Account assignment or "all"
    Please follow the following link for various aspects of Status management in Help.sap.com
    Project system --Structure ---Status management ---System Status in WBS.
    Warm regards,
    Srinivas Potluri

  • About wbs status check ----gi/ir balance check

    hi,dear all:
        When I set wbs to "clsd",can system check the purchment order's gi/ir balance of the wbs?(the account assignment of the po is the wbs)
        If it can not ,is there any else method can do this?
    thank you!

    Hi Jian Mao,
    Yes, when you change the WBS elemnt to "CLS" status, system will wheck any Open PR's, PO's and Final confirmation of the Activity assigned to that.
    For closing the PR's or PO's set deletion flag on header or item level OR set the delivery completed flag in PO.
    For Activities you need to confirm them manually using batch or one-by-one.
    Hope this will answer all your requirement.
    Reward me accordingly.
    Harisha

  • WBS element in Material Document List Report

    Hi Guru,
         I have a problem about WBS element which is not show up any data in Material Document List (MB51) movement type 281 and 281 Q event I add WBS in the document.  Anyone know how can i config or do anything to let the system show up, please let me know.
         Thanks in advance.

    Hi,
    Go to SPRO > MM > Inventory Management and Physical Inventory > Reporting > Define Field Selection for Material Document List > Here for Program Name "RM07DOCS", Table "MSEG" add field "MAT_PSPNR" (Valuated Sales Order Stock WBS Element) and activate "Output" indicator.
    And Then check in MB51

  • Reason for Environmental investment in wbs element

    Hello Gurus,
    Anybody knows what is the functionality of the field "Reason for environmental investment" in the wbs element?
    We know that this field can be used for report in assets, but what about wbs element? this field can be transferred automatically from wbs element to its asset master data?
    thank you very much in advance.

    Hi,
    In standard SAP report like S_ALR_87011963 OR ANY REPORTS , select the sort variant as 0008 - Co. code / reason for investment. In the report the field can be selected and included in the layout.
    Muralidhar

  • How to make WBS element field in Notification a mandatory.

    How to make WBS element field in Notification a mandatory.
    Should I use USer Exit.
    In cutomization I didnt find ant standard customization

    Hi,
         If it is about WBS element field in Maintenance Order then check up user exit ;- IWO10009 PM Order: Customer Check for 'Save' Event
    For Notification i am not sure whether this field is ther , but anything u can perform checkings via 
    QQMA0014 QM/PM/SM: Checks before saving a notification
    Alternatively u can also explore via Transaction variant SHD0 ..
    regards
    pushpa

  • Change WBS code to WBS description in CJ30

    Hi All,
    How can we change the layout from the WBS code to WBS description, because in CJ30 it shows that the WBS with no WBS description . It make the user confuse when put original budget.
    Cheers,
    Nies

    Appreciate ur advice.
    How about this report S_ALR_87013558 ...can we make the description longer.
    Sreenivas, could you advice me in my thread....which i am asking about WBS and WBS + network..please..
    cheers,
    Nies

  • WBS Hierarchy Logic build up with dynamic values

    Hello ABAP Crew.
    I currently using BAPI_PROJECT_MAINTAIN, and I have to pass I_WBS_HIERARCHIE_TABLE with the hierarchy table made by me.  Does anyone have a logic on how to do this from values within a table?
    Here are the values coming from a proxy:
    111520
    111520-111234
    111520-111234-19
    111520-111234-19-1
    111520-111234-19-2
    111520-111234-20-1
    111520-111234-20-4
    The purpose is to place this into the table of I_WBS_HIERARCHIE_TABLE in the UP DOWN LEFT RIGHT  format. 
    Now the problem is, the list of values received will always be different.
    Thanks.

    Hi Jotorres,
    Did you get a response for this question about WBS hierarchy logic build up with dynamic values? I have been trying to build it up myself, but its getting increasingly difficult. I wanted to know how you resolved this issue?
    Thanks a dozen !
    Regards
    Aradhana

  • MIGO IN 2007 - MIRO in 2008 - WBS budget problem

    Hi,
    I have the folowin situation. GR was done on a PO with WBS using 2007's budget. A few days later invoice arrives (2008), MIRO is used but system displays error about WBS budget for 2008. Of course the invoice budget of the WBS is in 2007 not in 2008.
    How can I fix this without posting the invoice in 2007, or reversing GR and rerunning it on 2008 ?.
    Thanks in advance.
    Nies

    Hi,
    I reconstruct : CJEN and then CJBN. and make sure that budget 2008 is allocated.
    Thank you.
    Best Regards,
    Nies

  • How do we get complete hierarchy for a WBS element??

    Hi All,
    Is there any FM to get complete hierarchy for a WBS element??
    Or any other method that would achieve this requirement ??
    Eg:
    C.00103.1
    C.00103.1.1
    C.00103.1.2.3
    C.00103.2
    C.00103.2.1 etc
    If i give C.00103.1, all the WBS elements in the hierarchy should be displayed.
    Any pointers are of  great help.
    Regards
    Prathima

    Hi,
    Available Methods
    Getinfo : Read detailed information about WBS [ BAPI_PROJECT_GETINFO ]
    Maintain : BAPI: Project maintenance [ BAPI_PROJECT_MAINTAIN ]
    SaveReplica : Replicate work breakdown structure (ALE) [ BAPI_PROJECT_SAVEREPLICA ]
    The WBS hierarchy object type defines the hierarchy of the WBSelements. A project definition always has exactly one hierarchy. If theposition of a WBS element changes, the whole hierarchy has to berebuilt. Therefore, the WBS hierarchy object type has only one command:
    Create. Every WBS element receives exactly one entry in the table parameter IWbsHierarchieTable with which it defines its position.
    Command: Create
    Use this command to create or change a WBS element hierarchy for aproject definition. Enter the WBS hierarchy object type and the Create
    command in the table of the IMethodProject parameter. The commandrefers to all entries in the table of the IWbsHierarchieTable parameterthat contains the data for the data for the hierarchy. Each entry inthe IWbsHierarchieTable refers to a WBS element that describes its position relative to the other WBS elements.
    Example
    - Positioning WBS elements TRAINING , TRAINING.1 and TRAINING.2 . (WBS elements TRAINING.1 and TRAINING.2 are subordinate toWBS element TRAINING. WBS element TRAINING1 is positioned on the left of TRAINING.2.)
    IMethodProject
    OBJECTTYPE = WBS-Hierarchy
    METHOD = Create
    OBJECTKEY =
    REFNUMBER =
    OBJECTTYPE =
    METHOD = Save
    OBJECTKEY =
    REFNUMBER = I
    ProjectDefinition
    PROJECT_DEFINITION = PD-TRAINING
    IWbsHierarchieTable
    WBS_ELEMENT = TRAINING
    PROJECT_DEFINITION = PD-TRAINING
    UP =
    DOWN = TRAINING.1
    LEFT =
    RIGHT =
    WBS_ELEMENT = TRAINING.1
    PROJECT_DEFINITION = PD-TRAINING
    UP = TRAINING
    DOWN =
    LEFT =
    RIGHT = TRAINING.2
    WBS_ELEMENT = TRAINING.2
    PROJECT_DEFINITION = PD-TRAINING
    UP = TRAINING
    DOWN =
    LEFT = TRAINING.1
    RIGHT =
    Notes
    Further Information
    For more information, see the R/3 Library under PS Project System -> Structures -> EPS Interface
    Regards,
    Vijetha.

  • Autorization on WBS hierarchie

    hello experts,
    I have a question about WBS element and authorization. i would like to know if it's possible to inherit from an authorization in the WBS structure. I work on user AREA USR2 on PRPS table. A user that have the authorization to see one level of an WBS with the code in the user area, can see all the subordinated WBS element ... I search a solution to inherite the access.
    thanx
    M.

    Hello,
    Anybody can help me?
    Thanks,
    M.

  • Field and table needed

    please give the table and fieldname for object description and object number

    Venkat,
    Table for Object number is PRPS and field name is OBJNR. I don't see any field for object description, if you asking about WBS description the table is PRPS and field name is POST1.
    Thanks.
    BS

  • PS Text - Authorization

    Our client wants to attach PS Text to the WBS.
    If any user mentioned any comment in the document, then nobody should be able to delete it. The remarks in the document should be there forever.
    But if seniors want, then should be able to write another comment or their view about WBS, without authorization to delete the earlier comment or comments.
    How to achieve this?
    In the authorization, we have object C_PSTX_ART and actions
    Masked
    Display
    Edit
    Display from archive
    Print
    Single-item planning
    Add
    Copy reference
    Delete
    Planning file entry
    Standard parameter: normal mode
    Convert indiv. planned order
    Change
    Initial transaction
    I have given
    Display
    Display from archive
    Print
    Single-item planning
    Add
    Copy reference
    Change
    Initial transaction
    there is no authorization to delete/EDIT but still user can delete earlier comments, since he/she is having CHANGE authorization.
    If I remove the CHANGE authorization, then user is not able to add comment in the document.
    Kindly suggest.

    Hi,
    Refer SAP Note:554415. ( Points 1.4 and 2.4)
    Regards,

  • Need Information Related to Finance

    Hi Everyone,
    Can anyone explain me about WBS ,WIP, AP ,AR, GL & related things..
    With Regards
    Pavan

    Hi,
    WBS
    Go through the below link
    http://www.sap-img.com/project/what-is-wbs-element.htm
    WIP
    http://help.sap.com/saphelp_470/helpdata/EN/90/ba6609446711d189420000e829fbbd/content.htm
    AP
    http://www.sap-basis-abap.com/sapfiar.htm
    AR
    http://www.sap-basis-abap.com/sapfiar.htm
    GL
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/FigL/FigL.pdf
    Regards,
    Marasa.