Maintenance Plan Call Dates

Guys,
In the standard system, the call horizon % is based on the smallest package used in the maintenance plan..
We have a typical scenario where we want the call date to be 6 months earlier than the 3Y or 5Y inspection.
Has anyone managed to manipulate these call dates (not plan dates) in a maintenance plan via user-exit/BADI?
Also posted [here|http://www.sapfans.com/forums/viewtopic.php?f=7&t=316460]
PeteA

Hi Pete,
I think thru the normal process you can even achieve for huge packages.Lets say even if it is 3 years or 5 yrs...call date can be before 6 months and work order get created based on call date.I tested and it is working fine for me.
Vijay

Similar Messages

  • Maintenance Plan Call Completions Changing

    Has anyone noticed in ERP that a maintenance plan call completion date can be changed when the work order for a call is given a new TECO date.  I don't remember this happening with 4.6c.  When scheduling parameters are set to adjust future calls based on the completion of a previous call, the future calls are moved based on last completion date. 
    Is there a setting that can be made to fix the completion date for a call as the first TECO or call completion such that it cannot be changed with TECO reversals and new TECO dates? 
    Thank you,
    Gene

    Gene,
       I don't think there are any new settings there. The completion dates will be provided for input, on TECO, as long as the MP hasn't generated the next call object. Maybe you could schedule the plan to generate the next call object to be Planned and executed in the future, as soon as the existing call object has been set to TECO?
    if not, You could  try using the user exit  IWO10004 Maintenance order: Customer check for order completion to make sure that the date(NPLDA) isn't changed.
    Regards
    Narasimhan

  • Maintenance Plan Calls

    Hello, I am wondering if it is possible to have two maintenance or service orders generated for the same date from one maintenance plan?
    For example, I have a piece of equipment that has a regular monthly check, but at certain times this equipment has to have a thorough inspection done and we need to keep track of when the inspection was done and completed.
    There is no set period for the inspection to take place because it can happen at different times.
    Is this possible in SAP? Please respond ASAP

    Hi Charlie,
    Given your requirement, its advised to make a single cycle plan for your equipment with a cycle unit of 1 month(as you have monthly maintenance requirements).You can then schedule this plan for the scheduling period as per your requirement. This will ensure that you have monthly call dates & planned dates. For your sporadic/unplanned inspection requirements, You can use Manual Call option in tcode IP10 (scheduling) which does not affect your regular schedule and is specifically meant for intermediate maintenance activities.
    Its possible to create seperate orders from the same maintenance plan if u have created more than one maintenance item. For example. if u have an equipment whose electrical and mechanical maintenance activities are to be carried out on similar times, btu u have different task lists for both, then you can create a two maintenance items having their own task lists but will be scheduled as per the cycle/strategy defined in the plan.
    Hope this gives some clarification..

  • Maintenance Plan Call object in Past

    Hi Experts,
    Is it possible to call the object in past in ECC6.0.
    Suppose i want to call the PM order in 2008 through sceduling but system is not allowing me.
    Is it required any setting in system. i dont want to call it through mannual.
    Please tell me is it possible to call the pm order in past through PM Scheduling.
    AR

    Amit,
    It is very much possible to call the object in past from IP10. Only thing you have to ensure is the tasklist attached to maint plan will have to be valid for the past date.
    thks
    Edited by: Talankis on Apr 7, 2010 11:20 AM

  • Passing planned date, call date to equipment master

    Friends
    I just come thro one requirement. We have the instruments going for the calibration process thro Plans. In this what i need is each instruments maintenance plans call date date (calibration due), completion date (calibrated date)  which has to pass on equipment master.
    Is it any functionality available for passing these values into the equipments master.
    Also we are planning shutdown jobs (No PS Module) thro maint order for various equipments. The requirement is in one single order for various machines i have to plan the shutdown jobs instead of going individual order. But its not possible at IW31.
    Can i have some idea how you are handling this shut scanario

    Hi,
    To add these fields in equipment master, i dont think there is a standard way, instead you can use an exit to create a new tab page and add these fields in it.
    Regarding shutdown maintenance you can go for revision no., that will help you collaborate all the orders created during this shutdown maintenance. Or create an order as shutdown maintenance and then create its suborders with individual maintenance tasks.
    Thanks,
    AS.

  • Preventive Maintenance Planning - change call date of future calls

    Hello,
    we are using time based maintenance plans to schedule our maintenance obligations towards customers. After creating the plan and scheduling (IP10) we get the scheduled calls proposed by the system.
    Now we want to use IP10 or IP19 to move those planned call dates that are in the future without releasing the predecssor calls but it gives us an error: "Maintenance plan 16.04.2009: Predecessor to still on hold".
    Does anyone know if there is a way around this?
    Thanks,
    Tobias

    Hi Tobias
    As per your query... you cannot move the call dates which are in the future. First you have to skip the cal which are before the future cal date. then only you can do...
    - Pithan

  • Counter based maintenance Maintenance plan

    Dear all,
    I Required help from all of you , I have made one no maintenaance plan with following details :
    Annual estimate          120000 Nos
    cycle lenth                  10000 Nos
    schedule the plan  0 Nos and
                         Plan date       call date                                                                       Next planed counter reading
    1                   22.2.2011     22.2.2011               New start  Hold                       10000
    2     23.03.2011     23.03.2011                    Scheduled  Hold                      20000
    3     22.04.2011     22.04.2011                    Scheduled  Hold                      30000
    4     23.05.2011     23.05.2011                    Scheduled  Hold                      40000
    5     22.06.2011     22.06.2011                    Scheduled  Hold                      50000
    6     22.07.2011     22.07.2011                    Scheduled  Hold                      60000
    7     22.08.2011     22.08.2011                    Scheduled  Hold                     70000
    8     21.09.2011     21.09.2011                    Scheduled  Hold                     80000
    9     22.10.2011     22.10.2011                    Scheduled  Hold                     90000
    10     21.11.2011     21.11.2011                    Scheduled  Hold                   100000
    11     22.12.2011     22.12.2011                    Scheduled  Hold                   110000
    12     21.01.2012     21.01.2012                    Scheduled  Hold                   120000
    In this case system  check both pland date and next planned counter readind and generate   the maintenance order on the call  date  although next planned counter reading not reach uptpo the  planned counter.
    But our clint want the maintenance order on next planned counter reading only not on call date please help  me the any solution  for fullfilling the requirment.
    Raghav

    Hi Raghav,
    Maintenance order will be generated on counter reading entered in measuring document only.
    It is the annual estimate because of which we can see the planned & call dates, which are used for maintenance planning purpose.
    Call date and plan dates keep on changing according to measurement documents creation. You create the any measurement document against the same counter which used in plan and see whether dates changes or not.
    Dates get changed on counter reading and hence order is generated on counter reading only, not on the dates shown in scheduling as dates are dependent on counter reading.
    Sundar

  • How to change maintenance Strategy in Maintenance Planning?

    Hi Friends
    In our maintenance plan, maintenance plan additional data, maintenance strategy is defined as 3M6M. Within this strategy, maintenance cycles are defined. Now we want it to change  to  the maiintenance strategy, 2M that is bi monthly. How to do it?
    Do I need to chage it in the maintenance plan category? I am very new to PM. Pls explain.
    Thanks
    Sangeeta

    Dear,
    It is not possible to change the maintenance strategy once assinged to task list,other option just try in the task list select the operation and select the maintenace package ,here delesect all the maintenance package alloted and then try to change it.
    First delete all the operations in the task list ,then system wil allow you to change the maintenance strategy.
    Best way is to create new maintenace plan with new strategy.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Steps to create the counter based Maintenance plan

    Hi!
    Can any body give "Steps to create the counter based Maintenance plan"
    (Mater Data,Transactional Data and Customizing Data creation)
    Regards,
    MDSFR

    hi
    please refer the following link
    http://help.sap.com/saphelp_46c/helpdata/en/fe/67ef189d6f11d189b60000e829fbbd/content.htm
    regards
    thyagarajan

  • Maintenance plan package change resulting in incorrect call dates

    When we change a maintenance package on an existing maintenance plan to a package whose frequency is not an exact multiple of the previous package (for example, changing from a 6M 180-day package to a 1Y 365-day package) and then restart the plan, the call horizon of the plan seems to be ignored and the new call dates are always a day or so before the plan date regardles
    Why is the call horizon being ignored in this situation?

    Hello
    Please check the Option Start in Cycle while scheduling the Plan.
    Also refer the below thread too
    http://scn.sap.com/thread/1788240
    Br
    Rakesh
    Message was edited by: RAKESH MANE

  • Maintenance Plan which has two call dates for year

    Hi all,
    I need to create a Maintenance Plan which has two call dates for year. The dates have to be the last Sunday of March and the last Sunday of October for the same Maintenance Plan. Does anyone know the solution? Please do throw some light on it.
    Thanks
    S
    Edited by: Sara Silva on May 14, 2008 11:39 AM

    Sara,
    You could do this without user-exits...
    Create a factory calendar with two working days. Then create a maintenance plan with a package of 1 day.
    Once scheduled it should produce the required maintenance cycles.
    There are two things you need to be very careful about:
    1. Keep the factory calendars updated, say, 3 years into the future
    2. Ensure you comprehensively test the IP30 transaction
    PeteA
    [www,pjas.com]

  • How to look for New start Called call for a Maintenance plan

    Hi,
    I need to find out all calls for a maintenance plan of scheduling type- 'New Start' and Status- 'Called'. How to find this using tables.
    For 'New Start' scheduling type probably table field and value is MHIS-TERMA = 'N'. There are different statuse in this table but I am not able to identify the status 'called'. Also what is the field MHIS-ZAEHL(Maintenance package number) for?
    Thanks,
    Vimal

    Taken from the standard IP10 program:
    * possible status combinations
    * TSABR - Scheduling status: planned date called
    * TSVBT - Scheduling status: call outstanding
    * TSENQ - Scheduling status: call horizon not reached
    * TSENM - Scheduling status: stopped manually
    * TSTAT - Sceduling status
    * TSABR   TSVBT   TSENQ   TSENM   TSTAT
    *   X       -       -       -       A     called with order
    *   X       -       -       -       -     called without order
    *   -       X       X       -       -     on hold (TSENQ), due (TSVBT)
    *   -       X       X       -       F     on hold, due and fixed
    *   X       -       -       -       X     skipped
    *   -       X       X       X       -     blocked
    *   -       X       X       X       F     blocked
    *   X       -       -       -       -     LRMDT <> 0, completed

  • Difference in Maintenance Plan date to Order basic start date

    If i creat a strategy plan and schedule, i am getting difference in PLan date in Maint plan to Basic start date. What is making this difference. How to overcome this. I need Order start date same as PLan date.
    Plz help me frnds.
    Guruprasad

    hi
    can you explain in details with your maintenance plan with the dates.Normally your call date and plan date will be different becase of call horizon ,but the order basic start date and plan date will be equal only
    kindly revert back
    regards
    thyagarajan
    your order basic date will be when you have maintenance call is generated.kindly check
    Edited by: thyagarajan krishnamurthy on Feb 25, 2009 9:46 AM

  • Change start of cycle date in maintenance plan

    Dear Experts,
    We would like to change start of cycle date in maintenance plan. Iwe have rescheduled the plan but the start of cycle date remains the same.
    could you please confirm, whether it can be changed. The requirement is because of some Mt plan created with future start date in production (Year-2020) and we want to correct the same.
    Thanks

    Don,
    To determine the next maintenance call date you need to tell the system when the last maintenance call occured
    Example:
    You want the next call date on the 1 June based on a six month cycle. Therefore the last maintenance date would have been 1 January (assuming key date scheduling).
    In your case you need to RESTART your single-cycle plan on the 1 January and the system then calculates the next maintenance calls.
    PeteA

  • How to compute Maintenance Plan's Plan Date

    Dear Gurus,
    I would like to request help from you.  I have a problem wherein I would like to know how is the Maintenance Plan's Plan Date is computed.
    Below is the parameters of the Maintenance Plan:
    cycle = 1500
    offset = 1478
    annual estimate = 5070
    first meas reading = 22.5
    Start of cycle is = Jun 16, 2011
    The plan date computed is = Sept 7, 2011
    Please let me know if there are other information needed.
    I hope you can share your knowledge on my problem.  Thank you.

    Hi,
        Please note that for Plant date calculate in Counter Based Plans system takes the below into preference for calculation :-
    1. Start of Counter reading value
    2. Date of Last counter reading udpate ..
    If you maintain offset then system first plans the offset then starts the cycle
    If ur annual estimate is  5070  , if scheduling is done by time then daily activity is 5070/365 = 13.89  round to 14
    Now if your start of counter reading value is 0KM
    And if your date of last counter reading is :- 2/3/2012
    Then your first planned date would be based on the offset :- 1478 -22.5 = 1455.5 /daily activity =1455.5/14 =104days
    So counting 104days from 2/3/2012 you would getting your First Plan date ..
    If u put call horizon as 100% then it will be in HOLD status
    regards
    giri