Hi,
I have read in SAP help that the maintenance planned for vehicles can be seen in PAM03 planning table. But there is no further information on how to get this.
Kindly provide your valuable suggestions.
Thanks&Regards,
Pavan

Hi Pete,
PAM03 is a tcode (Planning table)used in pool asset management to monitor the vehicle requests,assign, issue, return the vehicles.
This functionality is available from EHP3. Hope i am clear.
Thanks&Regards,
Pavan

Similar Messages

  • Maintenance schedule not visible in PAM03 Planning table

    Hi,
    I have read in SAP help that the maintenance planned for vehicles can be seen in PAM03 planning table. But there is no further information about the required customizing steps.
    Who can help?
    Udo

    Hi Dean,
    try this:
    IMG
      > Plant Maintenance and Customer Service
        > Maintenance and Service Processing
          > Pool Asset Management
           > Edit Object Processing
        Application = Pool Asset Management
        Notification Type = M1
        Order type = (blank)
        Dir. Sched = (selected)
    That should give me 10 Points
    Regards and good luck
    Udo

  • Splitting in REM planning table

    Hello,
    I am presently working with REM planning table.In planning table there is functinality of splitting the monthly quantities to daily quantities or weekly quantities.
    When you split the quantities what calculation system is doing internally?
    How system determines the start and end dates for the splitted orders.
    If I want to split the quantities on the basis of fixed percentages that is 18  % first week , then 23 % second week , 25 % third and rest percentages for last week.
    Can this weekwise varying distibution is possible in Planning table ?
    Waiting for reply from the REM Gurus.
    Regards,

    Hi ravindra,
    if u are working with longer lead time planned order, u can use various functinality to split the order qty for day or shift wise.
    The Avilable Capacity of the workcenter plays important Role.With refernce to this Avilable capacity the sytem schedules (spilts) order qty as per your need.
    Lead time scheduling will be carried out to determine start and end date of planned orders.
    For example u want distribute planned order day wise, system schedules the planned order with reference to Daywise Avilable capacity of WC. if the capacity requirements of planned order exceeds the avilable capacity of one day, system will automatically spilit the order qty for next day for remaining capacity requirements.
    This is way, system works to spilit the order. Before that u have to select correct scheduling data under "scheduling" tab of planning table.
    For your last question, system will schedule planned order according to Avilabale capacity and capacity requirements.
    i think u can spilit manually accorting to your need .Since  u have Avilable capacity for full week why do u want to spilit with some percentage.
    Regards
    pradeep

  • Maintenance schedule is not getting generated

    Hi....
    Past one year, maintenance schedule is not getting generated.
    Could you please let me know to where i have to look out for this problem in Equipment & Functional Locations?
    What are all the fields will be mandatory and triggering the maintenance schedule / Notification in Equipment / Functional Locations?
    Need your response at the earliest.
    Regards,
    Mohd Ali.

    Hi
    There May be several resons...
    Check Whether Maintenace for perticualr maintenance plan is not scheduled... their could completion requirement tick might selected previous maint. not done for the equipment.
    Check any scheduling for inactive equips/fl
    check any long offset has been set....
    check while scheduling any sortfield key is set or genral...if pertiucalr sort key is belong to Eq/fl which will not help
    regards
    krish

  • Error message in capacity planning table

    Hi,
    I am  using REM planning table.I enter the planning table by giving the selection criteria of Plant and production line.
    System is giving following error message,
    the error message and dignosis of the error message is given here.
    'No prod. dates for material MTI_FERT011, version 0001, production line 2279'
    Message no. REMPT315
    Diagnosis
    The planned order has no production dates for the combination of material, production version and production line you specified.
    This may be as a result of the following, for example:
    The planned order was scheduled but not using the production line you selected. (The production line is determined by the production version you entered in a planned order.)
    Procedure
    One possibility of finding out what is causing the problem is:
    To access the planned order from the detailed dialog box in the table via "Change" and reschedule the planned order. Check the scheduling log by choosing "Goto --> Scheduling log". More information is displayed in the log's warning or error messages.
    But which master data to be corrected is not known.
    Experts please guide me.
    Regards,
    Ravindra

    Hello,
    I had the same error while working with the REM planning table, despite the consistency of the data.
    Another cause that can lead to the error message REMPT315 is that in the production version detailed screen, "Planning data" table you have entered the routing next to rate-based planning. You must enter the routing (number of the group and the group counter) on the line detailed planning.
    After that, choose check again and try to introduce new quantities in the planning table. It worked for me!
    Irina

  • How to change duration of Preventive Maintenance cylce in strategy plan?

    Hi,
    How one can change duration of Preventive Maintenance cylce in strategy plan?
    e.g. In IP11 we set Preventive Maintenance schedule as monthly and we want to change it as quarterly i.e. every 3 months from starting date.
    With Best Regards,
    Rajkumar

    Hi Mr Ramesh
    Thanks for reply .
    Kindly guide us about as what steps /Tcode need to be used to perform the following actions as suggested by you :
    a) Delete orders.
    b) Go to IP10 and Do a 'manual call' by entering the planned date to create orders for the deleted packages.
    Or
    Reschedule the Whole Maintance plan by entering appropriate dates.
    c) Also please clarify , that how the new Orders will get generated against the Deleted Orders .
    With Thanks and Rgds
    Sonia

  • Use of Planning Table (MF50) in Capacity Levelling with Production Order

    Hello Experts
    I wish to know that is it possible to perform Capacity Levelling in planning table (tcode MF50) with respect to a Production Order ? It is known that MF50 is used in Repetitive manufacuring to do the capacity levelling with respect to Planned orders. But in our discrete manufacturing scenario we want to use planning table to the capacity levelling with respect toa Production order.
    Any clue or help pertaining to this will be highly appreciated.
    Thanks in advance
    Regards
    Jayanta

    Dear ,
    MF50 is does the cacapcity leveling based on mateail -run schedule order (planned order ) where as in discrete manufacturing , when you run the MRP ,  MRP system assume Infinite Capacity  and schedule the order as per your selection in MD02(2,1,3,3,2)  and then you convert those planned order to Production order .Here you checkied the Capacity in Production Order level .
    In stanadrd SAP  , it is not possible to use MF50 for discrete production order.
    In discrete order or process order ,  do the caapcity leveling , there are seperate planning table available based on Over all Capacity Profile and Schedule type .This can be done  in following way :
    1.CM31-Production Order Wise -Tabular
    2.CM23-PO wise -Graphical
    3.MC88: Ruf Cut Planning
    Work Centre Wise : CM21 -Graphical , CM22-Tabular Planning Table .
    Make sure the below set up before  you carry on the Capacity leveling :
    .Define time profile in OPD2.
    Define the strategy profile in OPDB
    Define the Overall profiles in OPD0.
    In OPJK  maintained check capacity with SAPSFCG013 profile for your production order type
    In OPU3 , scheduleing parametre s: Generate Capacity , Scheduling Type , Automatic Log ,Start date in Past as per your req.
    In OPJU , chekc the contol tab of the scheduleing as per OPU3
    In OPKP- Production scheduling paranmeters assing the overall capacity profile -SAPSFCG013  with finte scheduling tick.
    Master Data :
    1.Materials Master define the Production scheduler and production scheduling profile
    2.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
    3.Routing - enter the values for the standard values. Use control key with scheduling.
    Hope this will help you .
    Regards
    JH

  • Maintenance Schedule Approval

    Hi Experts
    There is a particular requirement at my client side wherein a preventive maintenance schedule has to be approved by maintenance incharge. How can this be mapped into system?
    I tried exploring user status for maintenance plan. In SPRO maintenance plan is being shown as object type for user status, but for some reasons which i couldnt figure out, it (User Status) wasnt assigned to the maintenance plan.
    Please share if somebody has worked upon such requirement before.
    Regards
    Ruhail

    Hi Joey and Balachandar
    Thanks for the response.
    In some industries it is a common practise that maintenance supervisors prepare the preventive schedules and thereafter it is sent to maintenance head of department (Incharge) for approval. Its more or less a formality but it has to be carried out.
    In SAP if approval is sought after scheduling there is no way that it can be changed (Ofcourse schedule schedule can be restarted but calls with status 'called' remain as so). And moreover if it is rejected then it will lead to creation of junk data in the system.
    Maintenance schedules are as such prepared in Excel and approval in form of signature is sought from deptt head.
    Thats why i was interested in knowing if somebody has come across such a requirement before and what could be possible solution be?
    Regards
    Nalin

  • PP-PI: Planning table customising (CM29)

    Hi,
    I have a question with regard to the planning table. The planning table basically exists of two parts, on the left side is the information of the planned orders and process orders, on the right side is the scheduling of the orders.
    I'd like to customise the left side of the screen. I want the users to have to possibility to see the material description, and maybe some sorting possibilities. So far, my search has not been succesful,
    Will award points to useful answers,
    Mark

    Hi, Mark
    I worked a lot some years ago about this issue and it is really cumbersome ...It has to do with the different profiles that can be changed in Customizing.  If you want to change the displayed fields then you should change the Layout Key - Select Display Fields. There you can select Field-table to use and the field length.
    Here you have a link where you can start to design your own table. 
    http://help.sap.com/saphelp_47x200/helpdata/en/1a/f2f33419ec8d44e10000009b38f844/frameset.htm
    Hope this can help you
    Dario

  • Default setting for Planning Table

    Dear gurus,
    How to default user setting in planning table?
    ( Not at individual user level) how it is possible?
    Pl. reply.
    Srini

    Hi Srini,
    you can customize some settings.
    Define scheduling parameters for planned orders - OPU5
    Maintain Entry Parameters - Production\Repetitive Manufacturing\Planning\Planning Table\Maintain Entry Parameters
    Maintain Row Selection - Production\Repetitive Manufacturing\Planning\Planning Table\Maintain Row Selection
    For the capacity planning in the planning table you can maintain different profiles.
    Kind regards,
    Frank

  • Planning table ( REM)

    Hi Experts,
                 When we opening planning table (mf50) with material selection ,then complete capacity data  section is not appearing& in header view of capacity requirement planning (change capacity display isin grey color).
    we have already set the parameter related to REM senario (e.g,rem profile,prod.schdl.profile,scheduling parameters (PE),w.c capacity data etc).
    where i had mistake ,plz let me know....

    >
    panney wrote:
    > Thanks for reply... I am sending 2 images, please refer the images.The problem is complete capacity data tab is not displaying,so,plz let me know were i have gone wrong.
    Images path:
    http://picasaweb.google.com/112717423459525953218/PlanningTable#
    http://picasaweb.google.com/112717423459525953218/PlanningTable#
    Panney,
    Its a simple problem, you need to assign your resource to the production line field of the production version( use transaction C223 or MM02 in MRP4 view to make this correction). Once the production version has the Production line assigned you should be getting the Capacity data in MF50.
    Regards,
    Prasobh

  • Activating capacity display in Planning table of MF50.

    Hi Experts,
    I intend to use the MF50 for Planning my FG. My scenario is a normal PP PI and not REM. I am using production version to distinguish the work centre (defined as production place). I want to display the Capacity of the Workcentre on the MF50 screen along with the Planning table. I am able to see the Prod Versions, planned ordes / requirements on the screen. My only concern is I want to display the capacity on the same screen, I found that the Activate graphic and set graphic settings in the Capacity reqt planning have got greyed out.
    I request the experts to guide me in this case.
    Regards,
    A S K

    Hi
    Check the following settings :
    1. In  production Version whether work center is maintained as production line or not ? .Also make sure that  same work center ins maintained in  Routing or not .
    2. In MF50 Initial selection screen Scheduling TAB check whether  'capacity requirement ' along with detailed planning  is activated or not.It must be activated.
    Regards,
    Velmurugan S

  • Importance of Planning Table

    hi! Gurus,
    can you please expalin me the importance of Planning Table (MF50).
    i can see the capacity data & material data, with a barchart (Capacity Planning Table). but, wht information i can get from that? how it is useful for planning? because, i felt MD04 can give better information than a planning table.
    and moreover i am unable to interpret the barchart.....it is displaying all production orders in tat week or month. but, whats the use (who needs tat information & for what)?
    i think i clearly explaind my agony....please help me
    with regards,
    SAP Friend

    In MF50,
    You will get many options,
    Mainly you will get the requirement and after running MRP, you will get receipt element(planned orders), This planned orders can be scheduled alone the axis by distibuting the order qty considering the capcity so that you can see that wc is over loadded.
    From here you can create production order or planned order directly.
    See the link below
    http://help.sap.com/saphelp_47x200/helpdata/en/5f/1faba54aee11d189740000e8322d00/frameset.htm

  • Planning Table MF50

    Hello experts,
    Can some one please explain the purpose of the planning table MF50 and how to use it for capacity levelling. I am in a REM environmnt.
    Thanks
    Raman

    HI
    1)In Repetitive Manufacturing, the master plan is represented by the planning table. The planning table is a tool for operative planning and is used to plan the production quantities:
    2) In a repetitive manufacturing environment, planning and control is usually carried out in a period and quantity basis. The layout of the planning table has been designed to support this requirement and is also based on periods to provide a very clear, easy-to-interpret overview of materials and production lines.
    3)The planning table is the planneru2019s/MRP controlleru2019s most important tool for planning the production quantities. At a glance the planner can check production quantities, monitor the available capacity of the production lines and check up on the availability situation of the products produced on each line.
    4)You can directly enter and change production quantities in the planning table. You can assign u2018non-assignedu2019 production quantities to the production lines or you can reassign production quantities to alternative production lines.
    5) You create the production quantities or assign them to the production line in the planning table.
    6 )You can also use the planning table with capacity planning. Here, planning is based on lead time scheduling. The basis for lead time scheduling is the routing. You can access the capacity planning table directly from the REM planning table.
    Regards
    Anupam Sharma

  • What is the need for planning table.

    can anybody explain me about planning table, how and where to use that..

    Dear
    Use of planning table :
    1.Capacity Requirement Planning in Discrete and PP-PI indistutry
    2.For demanad management , you can create PIR and also generate MTS production order based on planned order for those PIR
    3.Decision making on CRP in planning table for operation dispatch , work centre , scheduling , detail scheduling , time , dates of capacity avalution is possible through Planning table under particular overall profile .
    refer : Use of Planning Table (MF50) in Capacity Levelling with Production Order
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPCRPPPPI/PPCRP_PPPI.pdf
    Regards
    JH