Make net price field in me12 modifiable.

How to make net price field in me12 modifiable.
I have screen Layout & Screen variant but didnt get any clue.

the net price is a calculated field  in case you maintained price conditions (big button on top of the screen), then it is not changable anymore.
the net price is just information  for the user, it is not taken as price to a PO if no condition exists.

Similar Messages

  • How to make net price field in Purchase Order Uneditable

    Hello all,
    I am facing a problem. During creation of purchase orders the material price is picked up from the Info Record, but the net price field is editable. Please guide me how through standard SAP can i make this net price field uneditable.
    Thanks in Advance,
    Ritesh.

    Hi Ritesh,
    You can goto:
    SPRO-MM-Purchasing-Purchase Order-Define Screen Layout at Document Level
    from here you select ME21N-Selection group-Quantity and Price.
    Make the price and price unit as DISPLAY.
    By this it will show only display for price, but you have to take not that there is also condition tab which user can change the price, this price is from INFOREC.
    Goto to M/06 select your Condition type, In Manual entries maintain "D"-Not possible to process manually
    Regards,
    Maia

  • Massage No. 06217-Overflow for net price field during conversions

    Can anybody tell me the S note for the error?
    "Massage No. 06217-Overflow for net price field during conversions"
    There is a S note in OSS ( 576188) which is Obsolete now. I would like to have the correct S note to apply.
    thanks
    SACHIN

    Hi,
    SAP doesn't support item prices larger than 999.999.999,99. This is a limit of the system.
    The field has a length of 11 and output length of 16 for the commas and dots. Therefore, values entered in that field cannot exceed the total length of the field.
    Increasing the field length of the field is challenging. This would
    cause inconsistencies in the existing dataset and more problems in
    in Finance modules.
    You have to look for possible workarounds to resolve this. You may
    choose to split the documents, line items or quantities - what suits
    your business requirements best.
    You may choose to:
    1. Split the line items.
       This is applicable when your company wants to procure 1 single item
       with say 1 Billion value.
       for example:
       Qty  Unit       Net price
       1    EA          1,000,000,000.00
    This may be cost of one machine or asset.
    You may split this into accessories or mountings used for this as
    separate line items, so that the cost of the line item will be less
    than 1 Billion.
    2. Splitting the quantities,
       This is appliable when you are procuring more quantities with higher
       value items.
       For example:
       QTy        Unit        Net price
       1000000      EA          100000.00
    You may split this quantity into 250000 EA * 4 = 1000000. With this
    you may consider having four line items in the same PO or 4 differant
    PO's.
    3. Consider using pricing unit.
       If you use currencies in which higher values become necessary, SAP
       recommends to use smaller units of measure (for example "box"
       "pallet").
       For Example:
       Qty        Unit          Net price
       1        Pallet         1000000000.00
    In this case you may split this into Boxes. May be the Pallet contains
    more than 1 boxes. The net price of the box will be less than
    the Pallet.
    If your prices is not larger than 999.999.999,99 then please open a ticket in SAP, as this would be a bug and you would need a correction, that at the moment does not exist.
    Best Regards,
    Arminda Jack

  • Net price field length limitation in purchase order

    Hi
    The maximum net price PO line item accepts is 999999999.99.
    If in given scenario, it is not possible to break the line into multiple lines nor possible to use alternate units, what are the solutions available?
    How to handle similar situation in services?
    Appreciate any guidance on this.
    Thanks
    Sriram

    I have two business cases that my clients is facing right now.
    1) Capital increase   (Actual)
    Due to the World financial crisis my clients like many other issues had a capital increase transactions done thoriugh issuing bonds. The client has a policy no PO no PAY and this is enforced 100% in this case they needed one SAP PO recorded covering a large amount   Amount was in THB and exceeded the unit price field limitation.
    Work around was to make the PO line item 2 x YYYYYYYYYY
    2) Purchase of a vessel  (Will happen in the future)
    This is a  transaction with 1 x YYYYYYYYYYYYYY large amount which again exceeds the limitation.
    Despite workarounds are available like increasing the quantity, using different currency.. the client is till questioning the limitation that SAP have.

  • Make Net Value Field at item level Editable in Sales Order

    Hi
    All pricing in our system are manual .
    So the client wants to change the Net Value Field in Credit and Debit Memo Request to be Editable ( Currently it is not modifiable)
    Plz suggest how to g about it.
    Do i need to use Userexit_ Field_ Modification, if yes how , The field VBAP-NETWR.
    REgards
    Rohit

    Hi Yadav
    Changing Net Value will effect the updation of various tables ...so u r right not the correct approach .
    Can i put condition type and its value in Credit Request Memo and its value aditable same as in screen for Sales Order .if yes how , changing screen sequence group in credit memo request is creating problems
    Regards
    Rohit

  • Net price field should not be edited in PO, when created reff. to contract

    Dear friends,
    I have a requirement like this.....
    User referring the contract in creating the purchase order, details of the contracts are copied in to the purchase order. the price field is in edit mode....
    requirement is that user should not edit this field, the price carried from the contract should be not edit mode. this is to be hapen only when purchase order is created referrence of contract.
    here we are using only the standard document type is used for creating Purchase orders with and without the referrence of contract.   
    Thanks in advance...
    Shashidhar

    What I did for a client was implementing enhancement (user exit) MM06E005 to perform checking during PO creation.
    OSS note 310154 explains how to issue error messages from ME21N from the user exit.

  • Net rpice field optional in Pur requistion

    Hi all
    I need to make the net price field (MEPO1211-NETPR) optional in Purchase requisition while creating it. Please let me know how to do it. Please some one guide me how to do the config.
    Thanks
    Nagiamar

    Hi Amar,
    You can do that by going to SPRO.
    IMG > Material Management > Purchasing > Purchasing Requisition > Define  Screen Layout  at Document Level
    Look for the related field selection and go into the detail screen. Double click on Quantity and price to set the Price as optional by checking the Opt Entry.
    Thanks and regards,
    JT

  • PO Net Price and Gross Price should not bechange once GR happen for the sam

    Hi Friends,
    For my client they need the below requiremet
    As of now my client is able change a PO price(net price & Gross Price) after GR happen for the PO.
    I maked the Net price field as Display mode under the below Path
    Go to ->spro->mm->purchasing ->Purchse Order->define screen layout at document
    level-> Choose NBF->select price and price unit and make it display
    and i recieved the GR for the PO.
    But still am able to change the Gross Price for the material under the Item Detail-> Condition Tab.
    if am changing the Gross price means the same reflecting in netprice also.
    So,User should not do any Price level changes in a PO once GR done for that.
    Kindly suggest me how i can solve this issue.
    How i can remove the option in the Purchase Order?.

    Hi,
    Standard SAP does not provide any setting to meet your req.
    however, you can Use an user exit i.e. when the user is using T.code ME22N or ME29N the system should not allow to change the price if there is follow-on documents in the PO history.
    Refer SAP Note- 457511.
    OR
    Create a variant for field price in ME22N & M329N using T code shd0.
    http://wiki.sdn.sap.com/wiki/display/Snippets/TransactionVariant-AStepbyStepGuidefor+Creation
    Regards,
    Pravin
    Avoid Changes in PO price after Gr has been done .

  • Net Price Update in Inforecord through transaction XK15

    Hello Experts,
    For a combination of Vendor,Material,Purch. Organization & Plant, when the "amount" field is maintained with some value in XK15, it is not reflecting OR updating in inforecord master data--> "Net Price" field (for the same combination of values).
    But when we update it in ME12 transaction for the above combination, it is updating in inforecord "Net Price" field.
    1)Whether amount updation through XK15 will update the inforecord (As a standard SAP functionality or feature)?
    2)If the SAP standard feature as per point No.1 exists, then what could be the root cause for the 'net price' not being updated in inforecord?
    Regards
    Mahesh

    hi,
    Please refer this post
    Table EINE is not get updated with the new net price per unit.
    and
    Function to Update Info Record price
    Edited by: redriver on Nov 29, 2011 12:49 PM

  • Using gross price instead of net price at Quotation

    Hi,
    I'm working at a company that just bought SAP ERP ECC 6.0. Our consultants told us that SAP only works with Net price in MM. It sounds a little bit weird for us, because here in Brazil we usually use Gross price in all our transactions.
    Here in Brazil we have some taxes that are included in gross price and it's a hard work ask the final user to calculate the taxes out of SAP and input net Price in the system.
    I read a little bit some documentation provided by SAP at Internet called SAP Library and I found an article titled:Entering a Quotation Against an RFQ
    In this article says the following: " You enter the net price per unit in the Net price field. This price includes the vendor's normal discounts and surcharges only. Cash discounts (for prompt payment) and taxes (e.g. value-added tax) are calculated separately.
    You enter the gross price in the Net price field, and maintain the conditions for the item. Then the system automatically replaces the entered gross price with the calculated net price (see Maintaining Conditions)."
    As we can see, there are two ways to input the price. Gross price and Net price. I'd like to know if is there the possibility to configure the "mentioned conditions" for a group material and at the moment I type the gross price in Quotation the system automatically calculate the net price?
    Our consultant told us that this procedure should be done for each item in quotation, in my opinion I guess that SAP can link the applicable taxes for the material based on its group material. If something like that is possible, our daily work will be simplified so much because the system will know the taxes that should be discounted for the material and calculate automatically the net price.
    If this possibility exists, could you please tell me in technique terms (transactions) that should be set?
    Another question is about Taxable Income, is there any place in SAP where I can configure the Taxable Income for a material or group material for the taxes set at "mentioned conditions"?
    Thanks in advance,
    Sorry about my English.
    Best Regards,
    Amorim, Rodrigo.

    What you need is a new pricing procedure design to fit your requirements. The standard pricing procedure allows you to enter the net price. Then the gross price is calculated after taking into account the discounts, taxes etc. These discounts and taxes can be designed to determined automatically through material group also. So to achieve your requirement the pricing procedure has to be changed accordingly to calculate the net price from gross price entered. While this can be done, but all other impacts on pricing reports and accounting document posting with correce valuation price etc. have to be tested in detail.

  • Net price could not be changed in Scheduling agreement

    Hi Gurus,
       It has been observed that from last few days we are not able to change the Net Price in the scheduling agreement.
    When we analysed the issue it was observed that system is fetching the condition type PB00.
    Earlier system was fetching the standard pricing procedure and the gross price condition fetched was PBXX. In this case the net price field is editable.
    There is no change in vendor schema group.
    Can anybody throw some light on this as what would have happened.
    Regards,
    Rajesh Satope

    It seems earlier for the line item the conditions was not maintained ,Due to this you are able to maintain the price for condition PBXX.
    Now PB00 condition is automatically comming means ,there should be some info record or contract is maintained for the sku.So system is picking the price from any one of master data.Check in conditions from there you will come to know from where is system is picking the price.Change the price in master data then it will pick changed price.

  • Purchase Order Net Price not editable after GR/IR

    Hi Friends!
    I am facing a problem that, I want the price of the Purchase Order document should not be changed after the GR or IR is posted for this document.
    I have checked that making the net price field as display or M/06 is not the solution of the above mentioned problem.
    Can anyone help?

    Hi,
    If you want the price not to be changeable, set the tolerances in the IMG menu:
    MM -> PUR -> PO -> Set tolerance limits.
    Cheers

  • PIR net price not follow the condition screen

    Hi all,
    I have a question regarding my pricing condition maintained in a PIR.
    In one of my PIR record, there is two validity line records in the pricing condition with the following date range and value:
    1 - 2008.04.01 to 2010.12.31 ==> PB00 is USD853,00/1 PC
    2 - 2011.01.01 to 2999.12.31 ==> PB00 is USD853,00/1 PC
    However, the strange thing is that in the Purchasing Org screen in the PIR, the NET price value is "879,00 per 1pc" even with the VALID-TO field value as "2999.12.31".
    May I know why the the Net price in this view not picking up the USD853? Something go wrong in the PIR?
    (in between the Pr Date Category is 2-delivery date).
    Please help.
    tuff

    Hi Jurgen,
    I am still a little bit confuse as of why in the Purchasing Org screen in the PIR, the NET price value is "879,00 per 1pc" even with the VALID-TO field value as "2999.12.31".
    Question1-
    Shouldn't the above field automatically pick-up what is maintained in the condition screen of the most latest pricing record which is the USD853,00 for the second line item I described previously?
    Question2 -
    What have caused the 879,00 being inserted into the Purchasing Org screen in the PIR, the NET price field? where is this USD879,00 coming from??
    Thanks and please help.
    Tuff

  • Programme RM06INP0 is NOT updaing Net price value at in ME13 screen in ECC

    Hi Experts ,
    We are on  ECC 6.04 with SRM 7. We are using PIR as one of the SoS in Shopping cart in Classic scenario.
    When we are running the programme RM06INP0 in ECC in foreground /background to update the Net price field ( NETPR), but  it is only updating at value at Table Level ( EINE-NETPR) and NOT at Screen Level  ( or sometimes it update at Screens level)
    It does not affecting any functionality in ECC or SRM, since  system propose the Price from EINE-NETPR for PIR in SoS in SRM Shopping Cart & from last PO in ECC PO in ME21N , but user do NOT able to able to see the Price in ME13 ( Display Pur. Info Record)
    Can anyone please suggest what should be the issue ?
    Thank you .
    NAP

    Thanks Patilmallinath .
    I saw below information for this programe in "i" in SE38
    Short text
    Price Determination for Purchasing Info Records
    The report calculates the current prices of the info records and (if desired) updates the latter with the results.
    Description
    For each info record that satisfies the criteria set out in the initial screen, this report calculates the new net and effective prices from the currently valid conditions.
    If there is a variance from the prices stored in the info record, the new prices can be adopted in the info record.
    If there are no valid conditions, the prices in the relevant info records are not changed.
    Requirements
    The Test run indicator determines whether the new prices are to be adopted in the info records:
    'X' -> the report does not update the info records with the new prices;
    ' ' -> the report updates the info records with the new prices.
    Output
    The report generates a list containing only those info records in respect of which the newly calculated prices differ from those of the info record. Included in the output are the old and the new prices.
    and according to it it should update the Net Price in the Screen. Well, issue is 'Not updating the Price'...it is updating price at table level...but not at screen level...manytimes...
    Can you/anyone please suggest on this ?
    Regards
    NAP

  • PO Net price problem

    Sir in ME21n my system is not taking net price ,if i mention any net price it dissipears & system gives message that net price is greater than " 0 ". Also condation type of net price is dissipeared from ME21n.
    What is this.
    I am on line............

    Hi,
    Don't enter Price in "Net Price" field directly.
    Enter Price manually against condition type (PBXX) under "Conditions" Tab, it will automatically carry this value to "Net Price" field.
    Because Net Price = Gross Price - Discount. So you can not directly enter value in "Net Price" field. Enter Gross Price against condition type (PB00 or PBXX)

Maybe you are looking for

  • Can't get substring to work properly

    I have one field called 'Name', you are supposed to put full name and list it like this, 'Last, First, MI' in this one field separated by a comma, for each name, ex., 'Doe, John A.'. I need to be able to extract the first initial from the last name,

  • Purchasing in US, registering in Europe

    Given the current $ rate, and the fact i travel to the US a lot, can i buy DreamWeaver in the US, and legally register it without issue in Europe.

  • Hardware, software or me?

    I'm making a movie condensing 40 minutes of video into 10 with lots of transitions, audio extracts etc. Early in the project all went well but now, I'm having difficulty editing because the video (but not audio) "sticks" and then jumps frames. I have

  • Programming PLDs with LabView 5.01

    Hello I have to programm an ALTERA PLD. I have the Input File *.JBC (binary) or *.JAM (ASCII). There is an interpreter called JAM-Player (http://www.jamisp.com) available. How can I include these programming sequence in LabView? Has anyone already do

  • Sync Manager for Visio

    Hi... just installed the Sync Manager and when i try to syncronize the player in a certain point, without reason given, the software give me an error message and shut down. Now, i would to format the player but i know that this process will delete al