Manual Change Revision Level in Production Order
Dear guru ,
The revision level in the production order (for material to be produced and for the component) isn't manual changeable.
Does exist a chance for a manual change of revision level ?
Thanks in advance.
Dear Suresh ,
i know the link with ECM. In production order i can change the component revision level if i work with bom explosion date in read PP master data. But this solution isn't flexible. Imagine that i want to read PP master data with different explosion date for different component ...
Why in the purchase order the system allow a manual change of revision level and this chance doesn't exist in production order ?
Thanks in advance.
Similar Messages
-
FM to change Confirmation number of Production order
Hello Experts,
I have a requirement where I need to change the confirmation number ( which is already created for a production order) AFVC-RUECK. I could see that the confirmation number is not modifiable once it is created and no opition to change it by BDC. But my requirement is to change it for a production order.
1. Is there any FM or BAPI to change it?
2. Or directly changing in the database table AFVC is the only option?
3. Or is there any other method in which we can do it.
Awaiting your reply,
BalajiHi Balaji,
Please check whether the below link is helpful,
Re: How to modify a wrong confirmation of a production order
Also for the relevant tables, check the link,
confirmation number of production order
Best Regards. -
I have change some fields in (Production order component )
I have change some fields in (Production order component overview)
Hi,
do you want to hide or disable the fields or add new fields ??? by the way can you please let us know the transaction that you are referring to ??
Regards,
Santosh -
How to change operation dates in Production Order /Capacity Leveling
Dear Experts ,
We are using ECC 5.0 .In production order , scheduling happing as Backward based on the Sales Order Delivery Date .I am doing the following :
1.Demand as Sales Order with Delievery date : 20.03.2010
2.Running MRP with Lead Time Scheduling -2 in md02 and converting the Planned Order to Production Order .
4.Production Order have following dates :
Basic Finsish Date : 21.03.2010
Basic Start : the day Pl.Or--Pr.Ord
Schedule Start : 15.03.2010
Schedule Finsish : 17.03.2010
Schedule Release : 13.03.2010
5.In schedueling margin key : Float Before Production : 3 , FAP : 3 , Release Period : 2
6.In material master : Work Scheduling View : Setup : 3 days , Processing : 4 ,Interoperation : 2 for one Base Qty 1
7.In operation : Op1 : Start Date : 15.03.2010 Finish Date: 15.03.2010
Op2 : Start Date : 16.03.2010 Finish Date : 17.03.2010
Op2 : Start Date : 17.03.2010 FD : 17.03.2010
Question :
1.How to change the Operation dates in Production Order Operation over view screen ? Today, operation over view screen , Start date and Finsih Date of individual operation are not changable with in Production Basic Start /BF date or beyond .It is only changing based on the Standard Value : Labor
2.How to change/re-schedule operation dates d in CM21 (Graphical view -Work Center Capacity load as per Production Order and Operation combination ) based on capacity availale in advance dates? I am using Time Profile : SAPSFCZ002 -SFC Graph midterm-3 motnhs and Planning ,
How to solve this above issue in scheduling operation and capacity distribution .
Regards
JHClosing the thread
-
Change Work Center during production order confirmation
Dear All,
I must to modeling this situation:
I created an production order. In routing I used an work center A.
After I confirmed a half of quantity, the work center A was damaged and I must to change it, with the work center B.
The system allow this change, but when I checked the costing, the situation isn't real. The system counted the costs just for the work center A, and no for work center B.
My question is: it's possible to change the work center, during production order confirmation and the costs updated with new cost?
Thank you for your answer!
Regards,
Marianonce a Order is released, the Process order detaisl for that order is frozen.
however if you want to do it, change the order status to CRTD after reversing the Movements done.
Do READ MAster data , this will copy the new Work center , redo the previously done Moevements.
if the change is long term.
or
Just manually add the new work center and do the processing. if the change is temporary. -
Why some items can not change issue method in Production Order?
Hi,
I have a Production Order which had been released.
As some reason, I need to change issue method on some items in this Production Order, but I found that some items can be changed with a dropdown list, and some items can not be changed without dropdown list.
Why they are different?
What should I do to meet my users' request?
Thanks.Hai wilson,
sorry i visits forum after long time .. item category means , when create item group there are two option Service / Material if u select service , inventory come under that group only in "Back flush" other wise u can select "Manual / Back flush"
Regards
Janeesh -
Changing the Assignment of production order in sales order in MTO scenario.
Hello all!
I have following problem:
After the MRP a production order was created for a sales order. Because of the production in another plant
the production order which was created automatically had to be technically completed and a new one
created.
If you want to check now the availability, the sales order finds nothing, because it's linked to the one,
which was technically completed. Now is the question how can I change the production order for this
sales order. (In the production order the correct sales order is connected!)
As I found out it's connected to the field AUFNR in the table VBEP. But how can I change this
field within a transaction and not in the database?!?No replies
-
Report to list manual changes to conditions in sales orders and invoices
Hi experts,
Is there a Standard Report to list the manual changes of pricing conditions in sales orders and invoices?
Should be a selection on the field KONV-KMPRS.
Please advice.
Rgds,
PriHi priya,
In the Sales Order,Select Environment and then Changes to See all Changes made.
Follow the Same procdure for Invoice also.
There is no Standard report as such to see the changes.
Thanks,
Neelima. -
How to change Profit center in production order
Hi guys,
I have to change Profit center value in production order. Order has been created and released also. How to change, if i directly change system throwing error...Please suggest me in this case.
RGDS
DosThen Go to OBA5 enter the KO Application area
Add the 367 message and your user iD enter warning in online and Batch,
After that You can able to Change the profit center in Order with warning message in Order -
Revision level in purchase order
Hello all,
when creating a purchase order for a material, the revision level from the material master will be automatically added to the Item-Material Data-Revision Level field.
But what happens if in the meantime the revision level is updated on the material master, I guess the PO will not be updated on that field?
The problem is, I need the updated revision level field on the output of the PO, currently I am using the field EKPO-REVLV in the sapscript which refers to the revision level data from the PO.
Any suggestions?
Thanks
AnneHi Prakash,
I have tried to use this field in the form: AEOI-REVLV
This should be the original table.
I am using the standard print program for POs: SAPFM06P
Unfortunatelly, somehow the value does not come up for AEOI-REVLV, but it does come up for EKPO-REVLV.
Thanks,
Anne -
Change planning plant in production order
Hi Gurus,
my business scenario is the following:
I have 2 plants that are assigned to 2 different company codes. Plant A (ordering plant) and Plant B (supplying plant).
The users place a sales order on plant A and through MRP with special procurement key 80 the planned order is turned into a production order in plant B.
But in the order confirmation the system tries to post the GR in plant A. Is there a way to change the planning plant of the production order at any time i.e in order creation or order confirmation? Because I need the GR against the production order to be done in plant B. Since the subsequent posting according to the business scenario would be after production, the goods should be sold from Plant A to Plant B via a sales order.
Your help would be greatly appreciated.
PanosHi Panos,
SPK 80 doesn't suit your requirement, since by design it is doing GR in the ordering plant.
Alternatively you need to work with a SPK like 40, that is stock transfer from B to A. Just set up the intercompany process for this stock transfer.
This way, when MRP in A detects a need for replenishment, a stock transfer requisition from B to A is created. Then MRP in B will create a planned order for production (that you will convert into a production order later). GR is in B. The stock transfer requisition is converted into a stock transfer order, and the actual transfer takes place.
Check also this for more details:
http://help.sap.com/saphelp_erp60_sp/helpdata/en/f4/7d2d4d44af11d182b40000e829fbfe/content.htm
Regards,
Mario -
ECM: Change Master Record in Production Order
Hi
I have created a Change Master Record and made change to the BOM with respect to that change master record.
Now I want the Change master record (Eg. 001) to be visible in the production order (Master Data tab) when the production order is created.
Also, I would like to know if I can change the change master record (to say, 002) in the Production order so that the BOM with respect to that particular Change master record is selected.
Thanks a lot for your help..
TomHi Jack
I think at the time of creating Change master record u haven't maintained the Object types.
In that View u have to maintain Tick at the check box of Actv., Object & MgtRec of Object types-- Bill Of Material & Task List.
This will resolve your problem of Change Master Record Display at the time of Production order Creation at View of Master Data.
Parminder Sikarwar -
Use of Planning Table (MF50) in Capacity Levelling with Production Order
Hello Experts
I wish to know that is it possible to perform Capacity Levelling in planning table (tcode MF50) with respect to a Production Order ? It is known that MF50 is used in Repetitive manufacuring to do the capacity levelling with respect to Planned orders. But in our discrete manufacturing scenario we want to use planning table to the capacity levelling with respect toa Production order.
Any clue or help pertaining to this will be highly appreciated.
Thanks in advance
Regards
JayantaDear ,
MF50 is does the cacapcity leveling based on mateail -run schedule order (planned order ) where as in discrete manufacturing , when you run the MRP , MRP system assume Infinite Capacity and schedule the order as per your selection in MD02(2,1,3,3,2) and then you convert those planned order to Production order .Here you checkied the Capacity in Production Order level .
In stanadrd SAP , it is not possible to use MF50 for discrete production order.
In discrete order or process order , do the caapcity leveling , there are seperate planning table available based on Over all Capacity Profile and Schedule type .This can be done in following way :
1.CM31-Production Order Wise -Tabular
2.CM23-PO wise -Graphical
3.MC88: Ruf Cut Planning
Work Centre Wise : CM21 -Graphical , CM22-Tabular Planning Table .
Make sure the below set up before you carry on the Capacity leveling :
.Define time profile in OPD2.
Define the strategy profile in OPDB
Define the Overall profiles in OPD0.
In OPJK maintained check capacity with SAPSFCG013 profile for your production order type
In OPU3 , scheduleing parametre s: Generate Capacity , Scheduling Type , Automatic Log ,Start date in Past as per your req.
In OPJU , chekc the contol tab of the scheduleing as per OPU3
In OPKP- Production scheduling paranmeters assing the overall capacity profile -SAPSFCG013 with finte scheduling tick.
Master Data :
1.Materials Master define the Production scheduler and production scheduling profile
2.Work Center - Define the capcity planner group,activate checkbox Relevant for Finite sceduling,on the capacity header define the shift timings,break timings and unit of measure,no of individual capaity, enter formula for scheduling in capacity view.
3.Routing - enter the values for the standard values. Use control key with scheduling.
Hope this will help you .
Regards
JH -
Hello Friends,
How can I change the revision level of a DIR without creating a new version?
Per config, when I create a DIR it is assigned a rev level "-". Then I want to change it to an higher level "A" or "B" or whatever.
I am using BAPI_DOCUMENT_CREATE2 and BAPI_DOCUMENT_CHANGE2 for my process. Eventhough I pass a different rev level, SAP creates the DIR always with the first revision level per the config, which in our case is "-".
Any input/advise on this issue will be greatly appreciated!
Thanks,
SamRevision level has to be changed using a separated function call - REVISION_LEVEL_UPDATE
-
Function Module /BAPI for changing the components in Production order
Hi,
We are in ECC5.0. We have requirement wherein we want to change /delete the existing component of the production order and add new component through RFC call from an external system. We tried to use CO_XT_COMPONENT_ADD FM for adding new components and when we tested this FM in SM37 with data there were no error messages . When we checked the Production order ,no changes were made to the production order component. Tried to use Commit statement and there is no change in the system behavior.Can some one help me to understand the system behavior . If possible kindly suggest me some alternate FM/BAPI .
With regards,
Joseph Anand BDear,
Please check this link,
ADD COMPONENTS TO PRODUCTION ORDER
Regards,
R.Brahmankar
Maybe you are looking for
-
I have an GL account that represents a recent bond issue and there is an uploaded csv file with all the account groups and ranges defined to which it should be on. After realising that my report amounts were incorrect because of this account not bein
-
I use the latest FF browser and yesterday when I would try to go to a site I wanted to see, I would be redirected to an advertising site... Usually it happens from a google search but not always.... I ran the Microsoft Security software, but it did n
-
Problem with hearing sounds from macbook air, through earphones.
This happened just recently, my mac won't "send" sounds or music to my iphone earplugs. What to do?
-
FB60 Invoice posting system is showing blocked for payment
Dear all, When ever we post FB60 Vendor Invoice document system is showing blocked for payment error. In OBA5 we changed the message warning to Error thats why it is showing error message. In XK01 vendor master we have put it as Payment Block "B". Wh
-
Script to change colors of Illustrator shapes based on excel data?
Hi. My Problem: I have a list of names in excel and I would like each name to correspond to a given color. And I have the same number of shapes in Illustrator which I would like the color fill to match those names/colors from my excel file. Is this p