Manual scheduling phases in Process order

Hello dears,
a question came out to my business during Process order (PP-PI module) testing.
When a order is created, the system uses master recipe data to schedule each phase, and to assign them a start and finish time. These values are displaied in the process order for each phase.
The question is: is it possible to change them manually, in case I need to reschedule only a specific phase and not the whole order? Because currently I see that dates fields are not editable in COR2.
Thanks a lot.
Kind regards,
Giovanni

Dear ,
You ca not  able to manually chanes  the date and time unless they are Dispatched  after capacity evalution  or leveling at the Resource level.
Generally , if your resource is having finite scheduling active and you have CRP planning is in place , then you need to goto CM07/CM05 to check the Overload/Availablit of the resouce in a certain date n time so that you can re-scheule them manually from CM21/CM22/CM23 .
To meet this requirement , you have to adop Capacity Requirement Planning set up .
Check our earlier posting  on the similar issue : Capacity Planning not considering plnd order
Capacity requirements generation at phase level only
Regards
JH
Edited by: Jiaul Haque on Dec 8, 2010 9:30 AM

Similar Messages

  • How does the GR processing time affect the scheduling of the process order & the latest start date in the operation.

    Hi
    Can anyone explain  how does the GR processing time affect the scheduling of the process order & the latest start date in the operation overview.

    Hi
    GR processing time means number of workdays required after receiving the material in storage.
    Check this link:GR Processing time
    Regards,
    Anupam Sharma

  • Scheduling Time in process order

    Dear All
    While creating process order system is not picking scheduling time as per maintained in recipe because of this capacity is not being load on WC & showing zero reqmnt. Whreas date are properly calculating as per inhouse time maintained. In OPUZ i had ticked both scheduling & capacity reqmnt.
    In resource i had maintained all parameter in capacity & capacity is showing as 24 Hr. Scheduling & Capacity fromula had aslo maintain. Wht could be other reason for nt calculating time as per recipe.
    Thanks & regards

    Rashid,
    So is the dates getting populated correctly after scheduing function? If so then probably you current system design it to perform scheduling manually. You can use the "Production Scheduling profile" to perform this automatically. You need to assign a production scheduling profile defined for automatic Scheduling at the creation stage to you materil master "Work Scheduling" view
    Regards,
    Prasobh

  • Scehduling should be Fix for Only One Phase in Process order

    Dear ....
                          I created Recipe having  5 phases with base qty of 5000 Kg.
    Each havign differten machine HR . Now when i crated the Process order for 5000 kg then all timing get copied in schedulinng of Opeartion.
    Now my requirement is that One of Phase is independant of Process order quanity.
    So for this Phase i need same timing of 5000 kg, irrespective of process order qty.
    If i created process order of 3000 kg , the timing of thi phase get reduce in scheduling.
    I need to prevent the schedulling of this one phase irrespective or process order qty, wheather it wil increase or descerase scheduling of this phase should be same as per Reciepe.
    Edited by: abhisappp on Dec 28, 2009 7:44 AM

    ya..U r right actauly it was misatke..formula now corrected.
    But whre should i used this formula..as I am having other Activities which i am using for other phases .
    For this phases scheduling i am using scheduling formula as "Machine * Operation quantity / Base quantity / Operation splits".
    As thre is only one field for formula..how should i assign this my Fixed Fomula in reosurce so that only one phase should be effective with  new formula.
    Hopw u got my query..

  • Editing of scheduled dates in Process Order Operations

    Hello,
    I have a requirement, in which the client would like to change the Scheduled dates in the operation details of a process order.
    In the header screen of a process order, if we change the basic start / finish dates (depending on forward or backward scheduling), and reschedule the process order, the process order is rescheduled, with the new dates.
    The client's requirement is, they should be able to change the Scheduled dates in the tab "Operation - Dates", of the "Operation overview" screen, in a process order. Normally the field is not editable, and the system calculates the dates, based on the start / finish dates, entered in the process order header.
    I would like to know, what is the way out, to meet this requirement.
    Thanks.

    Hi,
    As every body else is explaining it is not possible for standard SAP ,  as of normal business or any business scenario why would a client want to change the operation dates from Production order ( still not understood.....)
    There are two options to do that:
    1) Copy the whole transaction ( programmes ) into some Z - transaction and in the programme you can change the object ( CO_VG_OPR_*) from being grayed out.
    This will alllow you to change the dates.
    2) you can go for enhancement with the following FM
        BAPI_ALM_ORDER_MAINTAIN
    I suggest you to clear these things with client.These things require more of ABAP work.
    And as said changing the standard behaviour of the system can cause performance issues.
    Please close the thread if satisfied.
    prakash

  • Create default operation & phase in process order

    Dear PP Guru,
    We used PP-PI and have a production type for simple production that there is no recipee for them.
    We used auto generate order for this kind of production.
    But in order, only operation is created and no phase is generated.
    Hence this process order can not be confirm?
    Is there any solution for this??
    Best regards,
    Freddy Ha

    Dear,
    In transaction "OPJG" you need to maintain default values for creating operation in case the system is unable to find a suitable master recipe. You need to maintain this for Plant/Order type combination.
    Then define the confirmation parameter for this order type and plant for operation level confirmation.
    Please refer this link,
    Re: Creation of Process Order without assigning master recipe

  • How to assign Inspection characteristic to the Phases in Process order

    Hi PP/QM  experts,
    There is business requirement to assign Master Inspection
    Characteristics to the Phases in the process order. But there is no
    functionality to assign MIC's in process order. So this is stopping me to map the scenario for Rework execution.
    Requirement is results recording is required for additional added phases (Phases added to the process order to perform Rework) in the process order.
    Expecting to provide a possitive solution to resolve this issue.
    thanks®ards,
    Hima

    hi hima
    there may be one solution that if you maintained separate master recipe for rework and maintained inspection characteristics there.and while creating rework order assign that master recipe. that would help you to result record.
    and one more solution is that you have to maintained inspection characteristics for your rework phase in the master recipe.
    if any query please come back
    Regards
    Pravin
    Edited by: pravin dhokey on Jan 15, 2009 10:01 AM

  • System status LKD REL for operation & phases in Process order

    Hi Gurus,
    We have a process order in which system status for operations & phases is LKD REL due to which user is not able to confirm the process order. The status of process order is REL PRC APNG APRS BASC BCRQ GMPS MACM RESA SETC. One of the user from planning has set the status to LKD due to some artwork changes. Now another user set the status to unlock. Locked status from order status was reset but at operation & phases level the status is still LKD REL & hence order confirmation is not allowed.
    I try to again set the status to lock but i am getting message system status LKD is active (ACT 40547870 0010) which is similar to one which we get during order confirmation.Pls. suggest.
    Regards
    Amit 

    Hello Amit
    If the status LKD is not set for the order header, this is possibly an inconsistency.
    Please open an OSS incident to SAP for further analysis.
    BR
    Caetano

  • COOISPI: No display of operations/phases from process orders

    hi All,
    I'm using EHP$4and having this problem The List "Operations/Phases" does not show any output in the process order information system (Transaction COOISPI).,however i used to work on EHP3 and did'nt face this problem
    please advice
    Regards,
    Ahmed Sobhi

    Hi Ahmed,
    I think the SAP correction note 1460244 will solve your problem.
    Best regards,
    Marcelo

  • Problem  with Process Order Scheduling..

    Dear Experts,
    i'm stucking with the scheduling of a process oreder.
    I've maintained all scheduling parameters into OPUZ except "selection ID" for detailed scheduling as it is grey & not allowing to fill any entry into it.
    I've also maintained production scheduler and other relevant settings into master recipe & resource regarding scheduling .
    Still i'm getting the error"Scheduling parameters for process orders have not been entered" message no CT609.
    Kindly help me out , where i'm wrong
    Thanx in advance...

    Dear Dennis,
    Ensure the scheduling parameters in OPUZ for the order type,plant combination and for all (* )scheduler you have maintainied
    the scheduling type,the check box for scheduling and generate capacity requirements under detailed scheduling is set.
    Check and revert back.
    Regards
    Mangalraj.S

  • Automatic confirmation in process order

    Hello everybody.
    I need made automatic confirmation to some phases in process order, I hade read that this is possible using process messages.
    Process management supports the direct confirmation from the PI sheet and process control system to the process order by sending process messages to predefined message destinations.
    Someone know what are the steps I need to follow to customize process message?
    What are the transactions that I need to use?
    In some documentation say that for access process management, I need proceed as follows:
    From the main R/3 menu, select the menu options Logistics u2192 Production - process u2192 Process management.
    The system branches to the initial process management menu. From here, you can access all the application functions of process management.
    But when I access that path there is not any transaction for use process management.
    Something is missing for install or what is the transaction that I need use?
    Thanks in advance.

    Hi,
    You can do that in T Code CORW.
    For the required production scheduler select the batch creation for process order.
    Also in the Assignment tab of the process order, there is a field for batch, next to it there is a Create button. Click that, you will get the batch number in that field.
    Hope that helps.
    Regards,
    Rohit.
    Added: I apologise, its not the Assignment tab in process order. It is Goods Receipt tab.
    Edited by: Rohit Chauhan on Aug 3, 2009 9:42 AM

  • PRTs in Process order

    Hi
    I want to use PRTs in process order.I am not able to do it?.Why SAP is not supporting to use PRTs in process orders?
    Can anybody through some light on this?
    Rgds
    Gob

    PRT Assignments to Operations/Phases in Process Order
    Use
    You use this function in master recipes to determine which production resources/tools (PRT) are required to carry out an operation or phase.
    You can subsequently assign the PRTs as test equipment to the inspection characteristics of the operation or phase.
    PRTs are not taken into account in recipe scheduling or product costing. As PRTs cannot be used in process orders at the moment, they do not affect capacity requirements planning, availability check, or confirmation.
    Prerequisites
    The PRTs must have a master record in the system. Depending on the PRT category, the following additional conditions have to be met:
    Materials, equipment, and documents must be released for use as production resources/tools in their status
    PRTs with a PRT master record (miscellaneous) must be released for resource planning in their status
    PRTs with material master records, PRT master records, or equipment master records must be intended for use in master recipes in their task list usage
    Features
    You can assign several PRTs to an operation or phase and one PRT to several operations and/or phases.
    During assignment, you can enter data that determine how PRTs should be treated during order processing. As PRTs cannot be used in process orders in Release 4.0, this data does not have any functional significance in PP-PI. This includes:
    The PRT control key
    Data on the quantity, usage value, and usage dates of the PRT

  • Blocking Changes in Released Process Orders

    Hi Experts,
    I need to block manual changes in Released Process Orders ( both in quantity and date) in APO. So, I need some userexit/BADI/FM which can help me to stop this change.
    Can anybody suggest something for this ?

    Hi Ulrich,
    Can you please explain a bit further --when this BAdI comes into picture ? When you save the Product view ?
    Is there something similar for Detailed Scheduling Planning Board also ?

  • Process order, no goods receipt without goods issue.

    Dear Experts,
    My client does auto and manual goods receipt for process order. He wants GR not to happen auto or manually till GI is not being done. I tried by user status but, user status was not changing automatically as system status. Secondly is their any user-exit for the same.
    Regards,
    Rajesh Prasad.

    Rajesh,
    Please check the following,
    Enhancement - MBCF0002
    Function Module - EXIT_SAPMM07M_001
    Include - ZXMBCU02
    This has been several times discussed in this forum, so suggest you to do a forum search for details about this.
    Regards,
    Prasobh

  • Process Order Quanity based on Component Quanitity

    Hy,
    In most cases the component qty. are depends on prodcution/process order quanity, but we have a scenario in which Order quanity is only decided on the basis of Active component's avalable qty of a single bacth which is based on its potency.
    For example
    1.0) If available stock of a single batch of a active ingredient is 5.5 Kg (Assay is 97.5%) then we can take process order quantity of 5000 Nos.
    2.0) If available quanity of a second batch of a actuve ingredient is 3.1 kg and (Assay is 98%) then we can tak process order quanity of 2800 Nos.
    Due this we can not set our lot size.For every single bacth of active ingredient we have to do manual calculation of a process order quantity.
    So pls guide how we can map this scenario for both planing and process purpose.
    Regards,
    Dhaval

    Hi Dhaval,
      I can suggest you to search any planning strategy available where you can create the planned order based on component.
    If it is not there then create one custom transaction where you can get the component availability along with batch ids. and use the same quantity for creation of Header material production order.
      We have developed custom transaction for PO creation where we adjusting or assigning the batch on availability.
    Regards,
    Shailendra

Maybe you are looking for

  • RSS Feeds on Yahoo Front Page/My Yahoo are no longer loading. Please help!

    After "fixing" my installation of Firefox I am unable to load any RSS feeds onto My Yahoo Front Page! They are all gone. Please help me to recover these important feeds. They are my only source of News every day.

  • Search service is not working in sharepoint 2013

    Dear Support, please find below mentioned log file details. Timestamp               Process                                 TID   Area                           Category                       EventID Level     Message Correlation 07/07/2014 18:10:33.

  • How to get tamil font????

    i would like to read tamil ebook in my handheld but i found that my device is not supporting tamil fonts. I would like to know how to install fonts and where i can find them.

  • I'm looking for iPad backup to windows software reviews

    I'm looking for software that will run on windows that will backup/restore reliably : iPad2 / iPhone 5 1. apps. 2. photoes / movies. 3. Settings. 4. Documents. 5. Contacts 6. iBooks Thank you, Docfxit

  • Use Web API url for loading an external image in a report

    Hi there, I am trying to host an image in a report, which is coming out of a Web API. I am able access the image through a URL in a browser: https://companytest.com/api/TestFormImage?id=10358&EntityId=6719&imgMetadataName=TestDiagram Can anyone pleas