Manually Planned order creation

Hi Gurus,
When i am creating planned order manually in MD11, some times ( not allways) it is asking for components although it has a Bill of material. But if we create pland order through MRP it woudn't asking for any components. Can u please tell me when it will ask for components if it has a BOM maintained?
Regards
Rajib Pathak

Hi,
I am using same order type for both manual creation and automatic creation......also i am using a valid BOM. Furthermore some time it is not asking for components. My question is in which condition it wil ask for components whereas there is a valid BOM.
Edited by: Rajib Pathak on Oct 27, 2009 12:14 PM

Similar Messages

  • Automatic Planned order creation-Strategy 50

    Hi all,
    I am using strategy 50 and first two levels of the finished material are make to order. Whenever i create sales order a planned order is automatically created for the finished material but for the material one level below no planned order is create, although this material is also make-to-order (ind/Col indicator is empty). Please guide me how can i achieve automatic planned order creation for the materials which are one level below the finished material (Note: Assembly is also of make-to-order strategy)
    Best Regards,
    Shah

    HI ,
    You are using planning stg as 50 " Planning without final assembly ", and this stg you need assgin only TOP level code i.e salable code , and down level codes no need to maintain .
    Once you enter sales order in TOP level code system will generate planned order  and from next level onwards you need to run MRP manually / Scheduled  ( single level / multilevel).
    System will not generate MRP for two level automatically i.e TOP level and next level when you enter SO.
    I hope this will clear to you
    Thanks
    Sekhar

  • Prevent Planned orders creation in Sourcing Org

    Hi,
    We have a customer requirement as below:
    Supply Chain : Org1 <-- Org2 <--Org3
    Item Name: X
    Item X has demand in Org1 procured from Org 2 by Sourcing "Transfer From"
    Item X in Org2 has planned order demand which triggeres a Planned Order in Org2 and to be procured from Org 3 by sourcing type "Transfer From" and it will create a Planned Order in Org3 which has sourcing "Buy from" External supplier.
    Org1 : Sales Order -->Planned Order1 for Item X
    Org2: Planned Order Demand2 -->Planned Order2
    Org3: Planned ORder deamand3-->Planned Order3
    Planners are different for Org2 and Org3 wan to do releases indivudually on their own schedules.
    Planner in Org2 want to ensure Planned order3 in org3 not to be released earlier than ISO creation in Org2 for item X.
    How to prevent planned order creation in Org3 having transfer planned order from Org2 to org3 for ISO creation.
    Need your valuable inputs.
    Regards,
    Kumar Kancherla

    Hi Kumar
    If I understand your question, the requirement is not truely about Planned Order Creation but releasing a planned order in Org3 before ISO is recieved in Org2 from Org1?
    This is more of a business process issue than planning since plan will provide a replenishment suggestion when there is a requirement based on sourcing rule. I'm assuming that these 3 orgs are planned in single ASCP Plan.
    One way to enforce this business process is by using "Auto-Release within Time Fence". Since lead times for Item X will be longer in Org1 vs. Org2 and Org3, planned order in Org1 will be released first triggering Internal Req/ ISO between Org1 & Org2 first and then between Org2 & Org3. While this may be OK if you plan to implement all suggestions from ASCP without manual intervention, it may not be acceptable to some planners who may want to control the release process manually.
    You may try it out with a limited set of items initially before rolling it out for all item/ orgs.
    I re-iterate that this issue is more of a discipline that planners need to use their discretion and due diligence to collaborate with other planners to ensure that lower level supplies are released only after a firm demand is released from higher level.
    Please feel free to let me know of any further concerns in this respect.
    Thanks
    Navneet

  • Error while creating manual planned order in apo

    Dear expert
    While I am creating manual planned order i am getting error as message /sapapo/rrp251
    Every thing is correct BOM and PV's no error after consistency check and it getting succesfully transffered to APO and it is also visible in APO
    But while creating manual planned orders planned order are not getting generated  I am using BLock planning with PPDS
    Please help How to resolve it
    Regards
    Virender

    Hi
    The error message /SAPAPO/RRP251 - Error occurred while creating order means While creating an order, the system encountered problems, such as, for example, no available components or components that are available late, orders that could not be scheduled, and so on.
    I think system attempted to solve the availability problems by using alternative procurement options. This was not successful. The order could not be created. Check the exceptional situations in the planning protocol, under Goto -> Planning log, and deal with the causes of the exceptional situations if this is possible or necessary.
    Thanks
    Amol

  • Planned order creation IDOC

    Hi Experts,
    i've a requirement where i need to develop a custom IDOC for Planned order creation. is there any standard IDOC for Planned order creation and if it is there then provide me the complete details like IDOC name, message type name, posting and selection program names etc.
    if i need to create a custom idoc then wht is the procedure for it.
    Regards
    Faisal

    Hi Abdul,
    You can use the below details for achieving the below requirement:-
    Message Type :- LOIPLO
    Basic Type      :- LOIPLO01
    You need not create any custom IDOC type as we are having a standard IDOC type available within SAP, but you need to write a custom function module to read the data from the IDOC segments and then call the below BAPI to post the Planned Order.
    Check the input parameters of BAPI and gothrough the documentation of the Basic Type in WE60 transactions, whether all the necessary input parameters of the BAPI are covered in the standard IDOC type, if not then we need to customize the standard basic type to meet the requirements.
    Bapi which needs to be used is BAPI_PLANNEDORDER_CREATE.
    I think all these inputs will solve your purpose.
    Thanks,
    Mahesh.

  • Planned order creation via MRP depends, If we change Delivery date in STO

    Hi,
    Planned order  creation via MRP depends, If we change Delivery date in Stock transfer Order.
    I created STO with delivery date as 31.1.2012 and when i checked MD04, i can see Planned order created on 27.2.2012 with the same above STO quantity .
    Now when i changed the delivery date as 30.1.2012 and runned MD03, and then checkd MD04, planned order disappeared.
    Why Planned order got created when STO delivery date was 31.1.2012 and when I changed the delivery date in PO, planned order disappeared.
    MRP profile details :
    Plnd delivery time   1
    GR processing time   1
    Planning time fence  38
    Tot. repl. lead time 38
    Can you please let me know why system is beaving in this manner?
    Regards
    Utsav

    Hi,
    Normally , MRP runs based upon the requirements.If your STO is created for a date , system checks through the availabiloty check wheather there exists any stock for that date to get deliverred in the supply plant .If there exists for that date the stock , planned order will not be created.If no stock available then a planned order will be created in MRP.
    cHECK the availability check parameters assigned to material master in supply plant.
    Regards,

  • Optmizer Planned Orders Creation

    Dear SAP Experts ,
    I am facing some problems with Planned Orders creation. I am executing discret optimization but it is creating planned order without taking into account minimum lot size.
    For i.e
    For one product with forecast 500 pc and minimum lot size 150 .
    Optmizer should create 4 orders with 150 pc taking into account minimum lot size but it is creating 3 orders with 150 and 1 order with 50 pc to fullfil demand .
    Some one can help me ?
    Nice Regards
    Mauricio Filho

    Hi,
    What is PPM/PDS max lot size? it seems due PPM max lot size you are getting these results.
    SNP Optimizer can't respect max lot size defined in product master.
    it can respect only min lot size and rounding value from product-location master for that
    in optimizer profile must be discrete and on discrete consraints tab define Mini PPM/PDS lot size and Integral PPMs/PDS horizon.
    If data view has weekly as well as month buckets, define 12 Months (don't define 52W) in discrete constraints tab if you want to respect these constraints for one year.
    Regards,
    Vipul

  • Planned order creation with PDS valid on only order start date and not finish date

    Hi All,
    We have requirement to allow creation of planned order manually if production version is valid on order start date and not finish date.  This is because lead time of order is longer. I refered OSS notes 385602. I could find out solution for this is implementation of OSS note 694140 to change validity mode at activity level to consider start date of first produce activity  in validity interval. Problem is even If I create order in APO by implementiong this note planned order is not transfered to ECC and it gets stuck with error production version not valid.
    Is there any way in ECC to control this? Any config or customization?
    Regards,
    Santosh

    Nilesh,
    I think there is a simple procedural skip happening in your business process. You are right when a planned order is created after MRP it would default assign it to the first available production version. 2options available for us,
    1. First use transaction MF50 and do the line loading and assign the quantites to the production versions/Production lines, so that the actual capacity planning is getting completed. This way you can have planned orders with both the production versions and matching to your actual line capacity.
    2. Use Quota arrangement concept, to automatically split the Planned orders during MRP for a percentage based on individual production versions.
    Now when backflush is performed S225 table is updated and Planned order qty also gets reduced.
    Hope this helps....
    Regards,
    Prasobh

  • Manual production order creation in MTO

    Dear collegues,
    I am stuck in a scenario:
    I have a finished item A. strategy 20 is used.I created sales order for A in plant 1000. MRP run in plant 1000 happens. Through special procurement key 40, system generates planned order in plant 2000. Planned order is converted to production order. I can see in assignment tab of production order,  Production plant is 2000 and planning plant is also 2000. Till here it is ok. I will do GR against production order in plant 2000 and through SD route I will send it to Plant 1000.
    But when I create manually production order in CO08, always system sets in assignment tab of Production order , production plant as plant 2000 and planning plant as 1000. How to avoid this? Why manual production order is not like MRP generated planned u2013production order?
    Kindly help.
    Regards.

    Give below a try in sandbox (Not from experience, so not sure if it works):
    At the time of production order creation, maintain the production plant in Sales Order & ensure the demand flow to MRP is switched off at schedule line (If you're not sure, take help of your SD person).
    The order created in CO08 should now have production & planing plant as same. Once that is done, switch back the plant in Sales Order & release the demand to MRP. (I hope the cut over plan has addressed the sales & MRP flows, so no inputs from my end)
    If the above does not work, then revert with details.

  • Planned order creation problem

    Hello everybody,
    When I am creating a planned order manually in MD11, I receive the message "Planned order xxxxx will be created".
    Then I receive a popup window telling me "Express document 'Update was terminated' ".
    But, when I am having a look in MD04 to see the planned order, I can't see it.
    It was still okay yesterday morning, but since yesterday afternoon, no more planned orders can be created manually. Do you have an idea about what can be the reason of this?
    It's just like if the order creation was delayed... But for how long, and waiting for what???
    Thanks in advance for your help.
    Regards,
    Rudy

    Hi,
    There is something issue with ur data while saving..hence it is not saving and throwing the message. so that while upadting data in table  is not acccepting.
    GOTO SM14->click on ALL UPDATEREQUESTS push button->U will find the reocrds,select ur userid and double click on it,now u can see the module name,select it and double click on it,now u will get one small dialog box,there u can find the abap editor symbol ,click on it..it will take u to the program where it has taken place
    Please refer this thread,
    Update was terminated
    Regards,
    R.Brahmankar

  • PLANNED ORDER CREATION FROM SALES ORDER SAVING (REQUIREMENT CLASS 200)

    Dear All,
    By using requirement class 200, assembly type 4 (dinamic planned order) Iwould like that at sales order registration the planned order for the sales order material is created.
    I have two problems.
    The system doesn't schedule the planned order, even if the scheduling parametres are entered for planned order type (relation between routing id and planned order type).
    So I have a planned order in which i have to manually schedule it.
    The second problem is that the planned order is firmed at creation. I would like that it was not firmed to adjust by MPS procedure the components from BOM modification. Infact at the creation of the sales order The complete BOM is not defined, and I don't want to unfirm the planned order so run th mps procedure.
    Can anyone answer to these questions?
    Thank's in advance
    Luca Pastura

    Hi Luca Pastura,
    For Scheduling
    1. You need to Give the appropriate check mark ( 1 or 2 ) In the capccity check of the requirement class configuration (ovzg)
    For Firming
    1. Since youare using dyanamic processing ""During dynamic assembly processing, you can not change the quantities and deadlines"
    2. kindly refer the F1 help for the assembly type inthe OVZG.
    Check and confirm
    Reg
    Dsk
    1.

  • Planned Order Creation - Firming Indicator

    Hi Team,
    When i am creating the planned order in MD11, the field "Planned Order (Firming)" is automatically set. I do not want to set this field is getting set automatically. Any configuration required to set this?
    Thanks

    Hello Sugan
    Remove the fixed indicator for a planned order created manually makes no sense!!!
    This planned order will be deleted or changed by MRP on the next planning run.
    I can tell you that this is not possible on the standard system, however, you can use BADI MD_PLDORD_CHANGE to do that.
    See this document with more details about the BAdIs available on MRP:
    BAdIs for MRP
    BR
    Caetano

  • Planned order creation in the past

    Dear Experts,
    For some business requirements, I have a necessiity for placing orders in the past.
    Is there any method to make a planned orders manually in the past in APO ?
    Thanks in advance four your input.
    Regards,
    Lee, Seung Won

    Hi,
    Yes it can be created.
    Check strategy profile maintained for interactive planning in  Production planning and detailed scheduling--global setting--maintain global parameters and defaults.
    Now go to Production planning and detailed scheduling--global setting--maintain strategy profile.
    For strategy profile maintained for interactive planning maintain scheduling offset in minutes with minus sign.
    Means if you want to allow order to be scheduled maximum two days in past from todays date+time
    Scheduling offset= -2880..
    Then go to product veiw /SAPAPO/RRP3 and create order manually.
    If you donot want to change configuration setting you can change strategy setting for product veiw interactively and save it for particular user.
    Hope this helps.
    Regards,
    Santosh

  • Planned Order creation for Sales Order and Purchase Order

    Hi
    We have a following requirement.
    In normal scenario when we have demand for material  which was created by MD61 and in addition to that if there is Sales Order the 1st planned order gets revised.To better expalin this consider possible scenario
    You create plan via MD61 for 200 qty .The system creates Planned Order for 200.
    Now there is Sales Order for 150 peices.Then what happens is original  Planed Order of 200 is changed to 50 and another planned order is created for 150 peices.The requirement is not summed.
    Now in new scenario instead of Sales Order there is Intercompany Purchase Order of 150 peices.
    Now the system is not changing original Planned Order of 200,but it created another planned order of 150.So now there are 2 Planned Orders of 150 and 200.
    What I want to know is there any way wherein the system will reduce the original planned order (similar to Sales Order scenario)
    Regards

    Hi,
    Use Strategy 52 in urs case.
    PIR witll be created .
    None convertable planned order will be created.
    Once you get sales order for that material.
    New planned order will be created which will consume PIR( planned order ).
    Eg.
    PIR 10.
    Planned order 10 qty.
    Sales oder 6
    Planned order for SO 6 qty
    Planned order through pir will become 4 qty.
    Regards,
    Vishal

  • Planned order creation with sale order assingment at the run time of MRP

    some material item not planed with sale order stock in MRP run time. all setting in material master are corrected as i knowing.having some mistake in setting other configuration.

    Planning strategy is Make to order individual collective as individual but still come as make to stock plan orders
    Incase of Header material- Plan order is creating in MTS
    Check the sale order procurement tab, Is The requiremnt type is relevant to your Stratergy?, if not chnage it to correct requiremnt type and rerun MRP again
    Incase of component material- Plan order is creating in MTS
    Check for the component material MRP 4 View, individual/Coll.req- as 1. If not set as 1 and rerun the MRP again

Maybe you are looking for

  • File Name Format

    I have a coldfusion app that allows users to upload images. The problem is that many of these users are not web savvy and upload hte wrong types of images with terrible names. I have error handling in place but would love to be able to disallow uploa

  • How to print a pdf file from reader?

    We have Reader X1 and cannot print a pdf file. Although it says 'print', it only allows us to save the file

  • Receiver Mail Adapter - Mail body as attachment

    Hello friends, I have scenario = File -> XI  -> Mail The scenario is working but the problem is body of the email is coming as attachment in the mail client.(outlook express) Is there any way to avoid the body coming as attachment. Regards Ramesh P

  • Subsequent credit to PO with multiple account assignments

    Good Morning - In ECC 6.0 when posting a subsequent credit to a purchase order that has multiple account assignments, the posting adds a commitment back onto the purchase order.  This works opposite of the subsequent credit that is posted to a purcha

  • NT Realm and Properties Files