Manufacturing Lead time, milestone operation wise

Good Evening to All !
I have a scenario. I am explaining this scenario through 1 example.
We have a material 'X'. Inhouse production time for this material is 6 days, which is maintained in MRP2 view.
Now in Routing of this material 'X' there are total 10 operations starts from 1 to 10. Operation No. '4' & Operation No. '10' are milestone operation. The workcenter for both milestone operations are different. Now in house production time which I maintained in material master is total lead time for material 'X'.
The requirement is:  Workcenter of Operation "4 "wants to know on daily basis that what quantity should be delivered from their workcenter.
Now my question is that can I maintain this lead time(6 days) in 2 parts as:
Till operation "4" my lead time is 5 days &
From operation "5" to Operation 10 lead time is 1 day.
Please suggest all possible solutions.
Can APO help in this scenario.
Thanks in Advance.

If you run MRP with "lead time scheduling" (instead of "basic dates"), it will schedule the order by the routing, and let you know the planned workload for each WC in advance.

Similar Messages

  • Lead Time Provision BP Wise

    Dear All,
    I have checked that there is a provision to store Lead Time in Item Master.Is there a similar provision also available in Business Partner.I could find only shipping type in BP Master.
    Kindly Suggest.

    HI
    No lead time field in BP Master.
    If you want keep information only then you can use UDF or Standard field which is not usable.
    Thanks
    Mohammad Imran

  • Compute manufacturing lead time

    Pls tell the detailed computing lead time in oracel.
    Thandks

    If you run MRP with "lead time scheduling" (instead of "basic dates"), it will schedule the order by the routing, and let you know the planned workload for each WC in advance.

  • WO scheduling based on lead times defined in item attribute

    I wanted WIP to consider the fixed & variable lead times specified for the item - where I am not rolling up mfg lead times using BOM.
    Has anyone been able to automatically schedule WO start date based on the lead times inputted in Item attribute.
    null

    Dear Bimal,
    The manufacturing lead times (setup and operation) are resource specific, and to declare them at item lead time attribute level is not practical (you need to define too many item levels in BOM to reflect every manufacturing step). The other work around is when routing is defined, you define two resource steps for each resource and make the first step lot basis and give setup time as usage rate and the second step item basis and operation time as usage rate. This gets reflected in manufacturing scheduling irrespective of quantity limitation (to define lead time at item level you need to define lot size also). I hope this takes care of your needs.

  • Target and Actual Lead time in MCP1 report

    Dear Experts,
    In MCP1 report, what is Target Lead Time and Actual Lead Time. How it is calculated?
    Thanks in advance for your valuable replies.
    Regards,
    Jejesh

    Hi,
                                                                                    Target lead time                                                                               
    On the operation level, it is the time period between the scheduled      
        input date at the work center (target input) and the latest scheduled    
        finish of the operation.                                                                               
    The target input date is calculated through the scheduled execution      
        finish of the previous operation.                                                                               
    On the order level it is the time period between the scheduled start and 
        the scheduled finish.                                                    
    and
                                                                                    Actual lead time                                                                               
    At operation level, the time between the input date at the work center   
         and the completion confirmation date (the total from queue time,         
         execution time and move time).                                                                               
    When calculating, the input date is determined via the completion        
         confirmation date of the preceding operation.  The process-dependent     
         wait time of the preceeding operation is subtracted.                                                                               
    At order level, the time between the reported start date and the finish  
         date (the total from execution times and transit times of the operations 
         as well as the order floats before and after production).                
    Regards,
    Rajesh

  • Difference between Compute lead time and Rool up lead time

    Hi All,
    Could you please clarify what is difference between Compute Lead time and Roll up lead time.
    I see in Routing > Tools.
    Thanks in Advance
    Regards
    Ravi

    Refer The Oracle document
    Manufacturing Lead Time Computations
    Manufacturing Lead Time Computations (Oracle Bills of Material Help)
    Rolling Up Cumulative Lead Times
    Rolling Up Cumulative Lead Times (Oracle Bills of Material Help)

  • How to get Operation wise Time for a list of Production Orders

    Dear Sir,
    We have a list of Production Orders numbers and need to know the operation wise time duration for these production orers (off course the desired time is same as mentioned in the routing for the relevant component)
    Kindly guide us as how can we get these timing details .
    Rgds
    Sonia agarwal

    Sonia,
    I hope your are refering to setup time, process time, teardown time in the production order.
    use report COOIS for it.
    In the 'List choose operation.
    Give input for the production orders in the slection scren. Execute.
    In the report select the columns as per your requirement.
    Hope this helps you.
    SmanS

  • Which table can give Operation wise Machine/Labour Std Value Time

    Dear Sir,
    We need to know the Table name which can be used to get  Operation wise Machine/Labour Std Value Time for a given Production Order .
    Using CO03 . we can get Std Values displayed for the Machine/Labour Time by double click on the operation .  Using Help , it shows that displayed is based upon the structure AFVGD .
    Kindly help us to know that using which table , structure AFVGD is fetching this required data filed value .
    Rgds
    Sonia Agarwal

    Dear Soni,
    Plz refer my reply from this thread
    [table that contains planned labour hours of operation;
    Regards
    Madhu

  • Lead Time for manufacturing and its corresponding Quantity in Material Mast

    Hi all ,
    Do we have any feilds in SAP Material Master
    which are useful for
    1) Lead Time for manufacturing
    2) Manfactured Lead Time Quantity
    if the mateials are produced inhouse.
    thanks
    ksr

    Dear,
    There are no such a fields in material master, But in MRP 3 view you will get theotal replenishment lead time field.
    Which use for the produced in-house if the replenishment lead time is included in the availability check:
    This is nothing but the  in-house production time and, if available, the goods receipt processing time.
    Also refer this link to calculate the in-house production time correctly,
    Total Manufacturing time for assembly
    Regards,
    R.Brahmankar

  • Lead Time for Purchasing Material & Manufacturing Material

    The query is related to the process of Material Requisition planning.
    I need to know from where exactly the system picks up the lead time for generating Purchase requistions?
    - For purchased material (lead time from placing order to actual recipt of material, time needed for QC checking till its release)
    - For own manufactured material (lead time at each work center in the recipe along with actual time required for a particular process)

    Hi
    for your information for  any material the data for the lead time comes from the material master
    http://help.sap.com/saphelp_46c/helpdata/en/fd/45b7ee9d6411d189b60000e829fbbd/frameset.htm
    if you click on the link you can get the entire process.
    as you can see SAP picks up the deatil from the MRP2 view of the material master.
    hope this  is helpful.
    regards
    Vignesh.

  • Total replenish lead time

    Hi gurus,
    anyone can explain why this field (total replenish lead time) is designed to enter manually instead of system automatically calculate from BOM for a manufactured part? and how does it work according to the following scenario:
    product X is produced in plant=1000 from material A and B (both A and B are procured externally for plant 1000, to simplify the case)
    in plant 1000, PO processing time=1day
    A: planned del.time=3 days, GR. processing time=1 day.
    B: planned del.time=5 days, GR. processing time=1 day.
    to make X need 2 operation: 1st operation need 1 day to assemble A and B together, after assembling, 2nd operation need 1 day to paint, 1 day to dry
    what's the total replenish lead time we should enter for X?
    thanks,
    cookie

    Dear Cookie
    3.if it's only for availability check, does that mean the MRP would not be affected by this field, then what would be the lead time feed into MRP? what's the relationship between MRP and availability check? why they use 2 different sets of data?
    1) MRP will not take this field into Account for Calculating Dates
    2) MRP for in-house materials - in-house production time & GR Procesing time ( Lead time )
    3 ) For external Procured materials - PR processing time , Planned delevery time & GR Processing time
    4) MRP Net Req. Calculation Concept is different from Availbility check Concept
    Regards
    Madhu

  • View of lead time of product in APO

    In R/3 under transaction C203 we view the time required for different operations to manufacture a product.
    Where in APO does the inidividual operations time appear in APO. Specially the leadtime.
    Regards,
    Chetan

    Hi Siva,
    Thanks for your reply. but that data is maintained in R/3 Material master in MRP2 view.
    my question is related to production lead time maintained in transation C202 in R/3
    Regards,
    Chetan

  • Scheduling by Milestone Operations

    All, I have a scenario where my customer would like to calculate the lead time to produce material based soley on the length of time which is entered on Milestone operations for a routing. Currently durations are maintained at each operation and we do not want to remove this as it is important for costing. However they want to have the queue times at the end of a group of operations instead of on each individual. A simple example is below;
    Step Duration Milestone lead time
    10 1 hr
    20 3 hr
    30 2 hr 8 hr
    40 2 hr
    50 2 hr 8 hr
    In this example the customer would want this order to take a total of 16 hours. They have a good idea of how long it takes the product to get from Milestone to Milestone. They want to capture all of the queue time in the milestone steps. Also they may have another order which has 7 steps but the overall leadtime the wish to capture is still 16 hours. This is a way for them to set general parameters without having to do time studies for every routing

    Hi Gordon,
    What I have understood from your requirement is that you wish to use Non - Milestone operation only for costing and not for scheduling but the scheduling for these operation must be done in milestone operation.
    I suggest you follow the below steps.
    1. Remove the NON Milestone Operations from scheduling in control key.
    2. In Mile stone Work center add another standard value key as wait time or previous operation time. (I assume u will have space to add another standard value key.)
    3. Please assign the control key meant for scheduling in this work center.
    4. Please note the activity type assigned in this standard value key must be dummy and unit cost must be negligible to avoid costing duplication. you can contact finance or costing team in this possibility.
    5. In routing, you can use the new assigned standard value key to assign the total time taken by operation before this milestone operation. Hence the scheduling could be done in mile staone operation and costing will not be duplicated.
    OR
    Using Queue time means you will have to maintina std. queue time and mini. Queue time.
    You can try using wait time in routing as the wait time can not be reduced.
    Let me know in case of any issue.

  • Sheduling by Milestone Operations

    All, I have a scenario where my customer would like to calculate the lead time to produce materrial based soley on the length of time which is entered on Milestone operations. Currently durations are maintained at each operation and we do not want to remove this as it is important for costing. A simple example is below;
    Step

    Hi Gordon,
    What I have understood from your requirement is that you wish to use Non - Milestone operation only for costing and not for scheduling but the scheduling for these operation must be done in milestone operation.
    I suggest you follow the below steps.
    1. Remove the NON Milestone Operations from scheduling in control key.
    2. In Mile stone Work center add another standard value key as wait time or previous operation time. (I assume u will have space to add another standard value key.)
    3. Please assign the control key meant for scheduling in this work center.
    4. Please note the activity type assigned in this standard value key must be dummy and unit cost must be negligible to avoid costing duplication. you can contact finance or costing team in this possibility.
    5. In routing, you can use the new assigned standard value key to assign the total time taken by operation before this milestone operation. Hence the scheduling could be done in mile staone operation and costing will not be duplicated.
    OR
    Using Queue time means you will have to maintina std. queue time and mini. Queue time.
    You can try using wait time in routing as the wait time can not be reduced.
    Let me know in case of any issue.

  • Lead time scheduling Vs Takt time scheduling

    Hi Experts, we are planning to implement sap in one of our plants..below is our business structure for your understanding..
    OEM - Mini bus Manufacturer which is the customer
    Bus seat manufacturer - Our plant (we already have sap here) - we already have sap repetitive here
    bus seat components manufacture - our plant (we are planning implement sap here)
    based on bus seat forecast the component plant will drive their production and will be send it to assembly plant which is seat manufacture.
    I have two questions
    1. what should we do in our component plant discrete orders or repetitive? I know you cannot tell me without seeing the plant but that my question. what questions should be ask our business to make this decision? how do anyone make the decision of going either repetitive or discrete? pleade do not point out the link to rep vs dis.. I have already those but I need something more in detail..
    2. I was reading a lot of help.sap.com and I have a question on below statement
    Basically, you can use two different types of scheduling:
    Sequencing with takt-based/rate-based scheduling
    The system schedules the planned orders using the number of takts and the takt times/rates of the line hierarchy. You define the line hierarchy in Line Design. In this type of scheduling, the system does not create any capacity requirements and only schedules the main lines. The system does not schedule the feeder lines.
    Lead time scheduling
    In lead time scheduling, the system creates capacity requirements and also schedules the feeder lines. The system uses the operations from the rate routing or the standard routing for lead time scheduling.
    what does lead time schuling will also do feeder line scheduling and take based does not schedule feeder lines means? can some explain with an example?
    Thx
    Swathi

    any help is appreciated

Maybe you are looking for

  • Cisco ASA 5505 SSL VPN

    Hi Everyone, In my study home lab, I wanted to configure a cisco ASA 5505 ( Base license) to allow SSL VPN. I follow carefully the configuration procedure as instructed on a short videos I downloaded on youtube. I configured my outside e0/0 with a va

  • Problem with Stack XML file

    Hello, We have an ECC 6 system with EHP 4 SPS 5 and we watn to install a new Technical Usage (IS-OIL, IS-PRA and IS-UT) In order to do that I have to supply an xml file created by the MOPZ. I created a new MOPZ transaction, in the phaze "Update Optio

  • Scorm enabled content created in a trial version of Captivate 7

    I am in the process of getting a subscription to captivate 7 through my school and have created some content to test in my Moodle LMS. When I go to view the content, I cannot view it. A window appears with the project skin but no content. Is this due

  • Easy question about 'javac'...

    Yeah, at school, we're so used to using a program like CodeWarrior or NetBeans to do all our programming with. However, here at home, I'm trying to code simply in Notepad, and I'm having a little trouble. Basically, I'm getting the NoClassDefFound er

  • *WHERE* is the reset button on WRT54GC?

    Hi everyone, I have the WRT54GC wireless router, and though I spent a lot of time on the phone with a technician, trying to find the router's reset button, I can't. It sounds ridiculous, but I was hoping to find a diagram online to aid my search (I m