Mass change on Backflushing box in Routing change when several Alt. BOM

Hello Gurus,
Is there a standard program to tick the box Backflushing in Routing change ?
It tried to manage it with LSMW but unfortunately there is one major difficulty: more than one Alternative BOM.
When I click on CompAlloc, SAP displays a list of all Alternative BOM existing for the selection.
We can manage this list only with mouse click which LSMW doesn't manage properly.
Second problem is to tick in one shot all the box item.
Scenario I used:
Transaction CA02.
Enter Material / Plant / Group.
Diplay List of Operations.
Click on CompAlloc.
Click on one Alternative BOM -> Here is the problem 1
Display List of Material Component Overview.
Tick Backflushing for all items displayed -> Here is the problem 2
Many thanks.
Stéphane

Hello Veerabathiran Suresh,
My situation is slightly different.  I have a ONE specific material that needs to be backflushed on the MANY materials it is being consumed by.  Using CEWB I call all the BOM's that are using this material.  Unfortunately CEWB only allows me to view only one material assignment and BOM it belongs to at a time for this specific material. 
I am assuming the individual that started this thread needed MANY materials for ONE specific BOM backflushed.  One material assignment needs to be viewed in this scenario.
Can it be done in mass, in my situation explained above (MANY BOM's using this ONE material and changing those backflush indicators)?

Similar Messages

  • Mass change in routing - operation details - machine times

    Dear all,
    I want to do mass change in machine times of aprox 20 materials in routing.
    So can anyone guide me for the procedure.
    Thanks.
    Edited by: sapsarang on Aug 19, 2009 1:39 PM

    HI ,
    As suggested by Mervin,better option is record in LSMW for CA02 transaction.
    For creating LSMW ,please refer the link which explain the step by step procedure.
    http://nabiljirani.com/SAP/SAP%20ABAP/SAP%20brain/LSMW_STEPS.doc
    https://wiki.sdn.sap.com/wiki/display/CRM/LearningLSMWStepbyStep!!!
    Hope it helps
    Edited by: Girish  Adaviswamy on Aug 20, 2009 6:59 AM
    Edited by: Girish  Adaviswamy on Aug 20, 2009 7:00 AM

  • Mass Changes to Rate Routing

    Dear All,
    We were trying to carry out mass changes to Rate Routing,
    by using CA85N we were able to make changes to Normal routing but not rate routing, in CA85N we were able to select only three types of task lists ie N, S & Q. Also checked in CWEB here also only the three types of task lists were provided for selection. Is there any other way for carrying out mass changes to rate rouitng, or settings in the above transactions.
    Regards
    Mithun

    Dear Mithun,
    In my understanding only CEWB can help you to some extent,otherwise you may have to develop some
    BDC's or LSMW's.
    Regards
    Mangalraj.S

  • Mass change for QM at operation level in routing

    Dear Experts,
    I have to carry out mass change for Quality Management at operation level in routing. The steps that I am carrying out for an individual record are as follows.
    1.     CA02
    2.     Inspection point 100 is maintained at header level
    3.     Go to operation level
    4.     At operation level work center and control key have been maintained
    5.     Double click on operation
    6.     When I scroll down here I go to Quality Management: Inspection Points view.
    7.     There by default in Insp.pointCompletion system shows the option as u201CQuantity, valuation (production) and radio button selected default indicates u201CQty-relatedu201D
    8.     I want to change these options as only u201CValuationu201D and u201CNo relationu201D respectively
    My queries are,
    1.     Is there any T-code available to carry out these changes in mass?
    2.     Is it possible to do this without any Z development?
    I am doubtful about using LSMW here. I would be highly grateful to you if someone can help me step by step.
    Thanking you,
    Anand Rao

    Hi Sujit,
    Thanks for your reply!
    I tried CWBQM. Unfortunately could not succeed. I think may not be feasible through CWBQM.
    But I came across T-Code CEWB . There I opted "SAP_OPERATION" as working area and it worked. Its quite useful T-Code.
    Thanks again for your input.
    Regards,
    Anand Rao

  • Mass change of routing

    Hi all,
    My question is mass changing of routing. Is there any transaction, mass changing of routing?
    Regards
    MSinan

    Hi,
    Try T code CA85, CA85N, CEWB.
    SmanS

  • Help me,Mass Changes to Reference Rate Routing

    Hi,
    I need to mass changes to reference rate routing.
    but i don't know how to do it.
    by using CA85N i was able to make changes to Normal routing but not reference rate routing.
    so.so.so. i need your helps.
    best regards.
    thanks.

    Hi
    While entering the selection criteria make sure that you are entering the correct selection parameters. Since the routing exist in CA32, it will be come in CA95N also. Please try with correct selection parameters.
    Thanks
    S.Murali

  • Component Allocation Mass Change

    Is it possible to mass change, say the backflush indicator, in CEWB for component allocations? If not, any other suggestions?
    Regards,
    Luiz

    Ashok,
    Since this deals with routing for configurable material with average of 1500 to 1700 component allocations, I thought CEWB would be the tool to use.  But I find no mass change capabilities in the Component Allocation view.  Do not know of any other mass change transactions for routings dealing with component allocation.
    Regards,
    Luiz

  • Mass change of payment in customer line item for all open line item.

    Hello,
    We have updated the new payment as per the new agreement with customer in customer master. We want this new payment term should also be updated in all the open invoices which are not cleared. Is there are way we can do the mass change in Payment term as the open line item in the customer where line item are more than 50. Please let me know the transaction code for the mass change of payment term in Customer account balances.
    Thanks and Regards,
    Rajesh Kumar Mantri

    Hi
    you can find the way to change the payment terms
    first check weather the payment term field is having change option in your document change rules in the line item for you customers.
    Financial Accounting (New)Financial Accounting Global Settings (New)DocumentRules for Changing DocumentsDocument Change Rules, Line Item
    if the payment term BSEG-ZTERM(payment term) is there for your customer and having deselcted check box for changing document you cannot change payment term for your company code.
    This can done client level or company code level.
    if the payterm  can be changed you do changes to payment terms mass level.
    Thanks
    ANJI

  • Production Order Mass Change

    Hello All,
    Do you know a transaction which allow mass change of productions orders?
    I found COHV, but I'm not sure how to use it, and if is useful for what I need.
    What I need is to change let's say for 100 orders field Scheduling margin (Tcode Co02).
    Rewards points guaranteed.
    Thank you
    Bogdan

    I don't want to change the material master...
    I would like to this on a daily basis on opened production orders.
    I would like to fake the order reservation for the default storage location 10 and at a certain date; I want to change in the production orders the storage location 30 (1 day prior to backflush)...
    I know it sounds weird; but let me explain the entire process...
    we have a stoarage location caged (Locked) ex: 10 where we really know the inventory levels; we would like to order according to the inventory level on this storage location.
    --> At a point in time we will issue to another storage location (Production area)ex: 30 the material physically.  In SAP we would issue to a cost center the material.
    --> Storage location 30 allows negative stock (in fact there will nevever be any stock)
    --> at the end of the month we will know the standard consumptions (total of the negative quantitiues in storage location 30)
    -->  We will also know the real consumptions according to the content of cost center (related to stor. 10)
    In order to do that we need to change the storage location 10 --> 30 before backflush.
    If we do not change it the backflush will not be done at the right place.
    If we always use stor. 30, our dependent requirements / inventory level / Pur req will be mixted and we don't want that.
    The production area is hard to control and the inventory there is rarely good because the processes are specials.
    --> ex: huge paper rolls:  Before starting a lot, we need an entire roll (to avoid stops) in fact in the inventory we have 4 rolls with remaining quantity of 0.25 (4x0.25 = 1) for example.  So for the buyer we're ok, but for the operations its not enough..
    I hope my problem is clearer...
    Any suggestions would be very appreciated...
    Regards!

  • Mass changing of folder names in CRM under tcode COMMPR01

    Hi Experts,
    Good day!
    I would like to ask help regarding mass changing of folder names in CRM in tcode 'COMMPR01' under documents tab. I tried to change the folder name of one material but it only updates the folder name for that specific material and not for the whole CRM box. Is there a way for me to do a mass change of name for the folders in CRM? Can this be done in customizing(SPRO)?
    Thank you,
    Christian del Rosario

    Hi Christian,
    Welcome you post on the forum.
    However, here is not for question of your CRM module. It is the forum for SAP Business One E-Commerce and Web CRM. If you are not using B1, close your thread.
    Thanks,
    Gordon

  • Mass Change ERS in PO + BAPI

    Hi All,
    I need to make mass change in lot of PO at itme detail level. I need to uncheck ERS and GR based IV check box in invoice tab.
    I dont want to make use of Mass change tcode for this as it cause lot of work and chances of manual error are lot.
    I have never used BAPI in LSMW  but I have come accross BAPI for PO Change......I am pretty good at recording method in LSMW but I think that wont help me in this case due to the table control in PO. I have also found a tutorial on BAPI + LSMW for PO creation so I got some rough idea for it.
    Can someone tell me the sturucture I should use for the BAPI in LSMW for my requirement and the points which I need to take care of. also tell me do I have to actiavte the inbound idoc processing for it.
    Please guide....
    Also suggest if i need to create 2 flat files for this ....like 1 for header and antoher 1 for item level.
    Edited by: Sap: IN on Apr 30, 2011 2:36 PM

    I am able to map my flat file with the structure sucessfully
    But I am facing problem
    1. IDOC segment E1BPNEPOITEM  does not have the field GR based IV and ERS.
    requirement : as I want to remove these 2 check boxes from couple of PO for different line item I have mapped the fields with the segement mentioned above but I am passing blank value from my flat file...so in the display imported data I am getting PO number and line item number and for those 2 field blank value.
    due to this in the step display converted data those 2 fields along with all the fields of the segement itme data are blank and so the IDOC gets created with out any field in the item segment.
    question: how to over come this problem ...I need thoes 2 field in the segment but with balnk value. as the check box need to be unchecked in the po.
    Edited by: Sap: IN on May 1, 2011 11:56 AM

  • Mass change for field Confirmation control Key in PO / SA

    Dear All,
    There is a need to do mass change in value for field Confirmation control Key in PO / SA. Some of them have PO history. If we have PO history system wont allow to change conf. ctrl key. Also since it is a production system we can not cancel previous po histories. This is in SAP 4.7 where we dont have mass change tcode for Scheduling agreements.
    Can we maintain the values thru table entries. like using se16n maintain entries check box. This option is greyed out. can we activate that & do this requirement.
    please suggest.

    hi Greetings!
    The confirmation control key can not be changed in the scheduling agreement if GR for item had already been posted. If the GRs can be canceled , it is possible to change the confirmation control in the SA item.
    Version 4.7 do not support Mass change of scheduling agreements, hence you have to either create a SCAT or BDC to perform the task.
    Gobinathan G

  • Mass change email by FK02/LSMW

    Hi Experts,
    I'd like to mass change the email address and Standard communication method in vendor master data by LSMW. But when I tried to record, the two fields are not found. I can change them directly by FK02.
    I suppose it's because the two fields are not in table LFA1. Then how can I change them by batch input?
    Thanks and regards,
    Eunice

    Hello,
    When you are doing the recording for FK02 or XK02
    Try to check
    Address Check box
    USE CENTRAL ADDRESS MANAGEMENT (if you do not check this check box, your email address and standard communication method will not be available)
    Hope this solves your problem.
    Regards,
    Ravi

  • Mass Change in Credit Limit

    Dear All
    I have four company codes and i each company i have lot of customers and i have to increase the credit limit of customer at each company codes so plz tell me how to do this at mass level.
    Looking Forward
    Shujaat Abbas.

    > I have four company codes and i each company i have lot of customers and i have to increase the credit limit of customer at each company codes so plz tell me how to do this at mass level.
    Hi Shujaat,
    Try the following:
    T.code: MASS
    In the new screen, give business object as KNA1 (for customers), and click on execute.
    Under the tab "Tables", select the table KNKA (Customer master credit management: central data) and click on the tab "Fields".
    You will be routed to a screen where you have to give all the customer numbers and their respective credit control areas, for whom who wish to change the credit limit. Then click execute.
    In the new screen, there will be an icon "Select fields". Click on it, and select the field "Individual limit" and press enter. Beside "New values" give the new credit limit. Finally click on "Carry out a mass change"
    Save the changes.
    Hope this helps. Do get back if further clarification is needed.
    Regards,
    Swapna

  • Mass change of Production orders operations in ECC 6.0 using COOIS

    Dear experts,
    Kindly Suggest a way to mass change of direct operations and components overview screen of production orders in ECC6.0
    using COOIS transaction code which was available in SAP 4.7 using environment >change order> operations or components once we execute the COOIS with certain input parameters in the out put screen,this function seems to be not available in ECC 6.0 , if available kindly guide me or any alternative way to perform the same.
    Thanks in advance for your inputs and help..
    Best regards,
    Nitish jain

    You have that button "Change Order" you can just click on it and once you're in the change mode of the order click "Component Overview" button , it's the same number of clicks...
    Anyway, SAP has changed the entire ALV for all the transaction codes using PPIO_ENTRY (COOIS, CO26, CO27, CO28 et al)
    look at question 12
    https://service.sap.com/sap/support/notes/540779
    if you really want your old GUI status. there is a way to get it back. In SE38 enter the program name PPIO_ENTRY and select variants and click display. Once you're in variants screen enter variant name and click create and select all "screens" check box and then it will take you the selection screen in there check the box "Old ALV Display" in the Technical settings sub screen. (If you want you can choose other functions also like "Selection List" as PPIOM000 Always display components directly etc. if you want ) Click on "Next Screen" button and it will show "Attributes" button then click on the attributes button and save it.
    Now go to SE93, make a copy of transaction COOIS to ZOOIS and in the variant field enter the variant you just created. The new transaction will always start with the variant you just created and it will look like your old COOIS with Environment > Change Order > Components will be visible.
    Edited by: Jeevan Sagar on Oct 20, 2011 9:50 AM