i want to  mass change some components in BOM. For example in the BOM i have 10 components. Now i want to change 5 components in the BOM
I have around 500 FG How to do that? Is it possible in LSMW?. or CS20?

It is better to go for getting a BDC developed for all the mass changes in the BOM.
Using CS20 you can only change a single component and replace with a new material. I think BDC is the best alternative.
Hope this helps you.

Similar Messages

  • Impacts of important component change in BoM on CO-PC

    Hello dears,
    will anybody please help me?
    I have to change the principal component for a lot of materials.
    I premise that we wouldn’t change the name of the material produced.
    What kind of impact this will have in Product Cost Controlling?
    Thanks in advance,
    Best regards.
    Juan

    Dear Juan,
    In your case if the change is only for one HALB item(change) for only one BOM
    means,easily you can do a cost rollup & released cost estimate using T code
    CK40N.But this has to be done by the CO consultant and they can observe the
    changes properly.But on the other side if you have carried out mass changes
    using CS20,then it takes much time to clear the Finance issues.
    The impact will be seen in variances,so kindly take the help from your FI-CO
    consultant & proceed.
    Regards
    Mangal

  • Impacts of important component change in BoM on VARIANCES?

    Hello dears,
    will anybody please help me?
    I have to change the principal component for a lot of materials.
    I premise that we wouldn’t change the name of the material produced.
    What kind of impact this will have in Product Cost Controlling and overall on variances?
    Thanks in advance,
    Best regards.
    Juan

    Dear Juan,
    In your case if the change is only for one HALB item(change) for only one BOM
    means,easily you can do a cost rollup & released cost estimate using T code
    CK40N.But this has to be done by the CO consultant and they can observe the
    changes properly.But on the other side if you have carried out mass changes
    using CS20,then it takes much time to clear the Finance issues.
    The impact will be seen in variances,so kindly take the help from your FI-CO
    consultant & proceed.
    Regards
    Mangal

  • Impacts of important component change in BoM on BW

    Hello dears,
    will anybody please help me?
    I have to change the principal component for a lot of materials.
    I premise that we wouldn’t change the name of the material produced.
    I premise that we wouldn’t change the name of the material father.
    What kind of impacts this will have on BW considering that we reunite the report by this component?
    Thanks in advance,
    Best regards.
    Juan

    Dear Juan,
    In your case if the change is only for one HALB item(change) for only one BOM
    means,easily you can do a cost rollup & released cost estimate using T code
    CK40N.But this has to be done by the CO consultant and they can observe the
    changes properly.But on the other side if you have carried out mass changes
    using CS20,then it takes much time to clear the Finance issues.
    The impact will be seen in variances,so kindly take the help from your FI-CO
    consultant & proceed.
    Regards
    Mangal

  • Mass change in component Scrap % in BOM

    Hi Guru,
    Can someone explain me the process of mass change in component scrap % in BOM ? I have to make zero coponent scrap % in BOM for all materials.

    Dear Vikash,
    Check with t-code CEWB
    for this you need to define work area in OP77
    Regards
    Madhu

  • Mass change in BOM - field "Relevant to sales"

    Hi All,
    How to do Mass change in BOM for the field "Relevant to sales" ?
    Thanks.
    Marianna

    Hi,
    Need to use CS02 recording in such a way that you can change every item in a particular BOM.
    e.g. First get into HEader Material BOM (CS02), once you've General Item Overview screen, do NOT directly go to item details of any item.... first click on tab-'Position', enter either Item Number or Component or both and then go to item details to change the relevancy indicator. Once changed for a particular item, save the BOM & come out of it. Then try for next item & so on....
    Again this is my initial thought, you need to try out few recording options like this and then chose the most suitable one. Take help from ABAP expert if any available.
    Off-course, initiallly it would take time to set-up LSMW but later on just need to create a data-file & do the mass changes.
    Hope it will help.
    Regards,
    Anup

  • Component change in respective BOM

    Hi All,
    I have situation, one raw material used in 10 diff BOMs, but now i want to replace this component by other,
    Is there is any mass transaction to amke this replacement effective.
    Thanks
    Regards

    Hi,
    Yuo can try here CS20 mass changes in BOM  .Where you can change material ..
    Just try it.
    Regards
    SANIL

  • Mass change in bom

    dear experts
    how to add materials in mass change in BOM with CS20 or LSMW or BDC.
    regds
    prince

    HI
    Check  T code CS20 or thru workbench for CEWB you need to activate working area in OP77 select SAP_item .
    check this thread
    Mass changes for BOM Base Qty
    Regards
    Anupam Sharma

  • Mass changes in BOM

    Dear Experts....
                            I want to delets some items from all BOMs.Items are specially tools having a matrial type ERSA. How to delete same items from all BOMs.
    Rakesh

    Hi,
    You can carryout the Mass changes of BOM using the Tcode : MASS.
    Where you need to select the object type related to BOM and perform the mass change.
    It can be done through CS20 and CEWB also.
    Hopwe this will help you.
    regards
    radhak mk

  • Mass changes of BOM with ECM

    Hi
    I wanted to change into BOM by Cs20 Mass changes into BOM with ECR Number which is created throgh CC31 .
    but system is not allowing me to do the same , pl tell me where is GAP.
    Rgds
    Pankaj Agarwal
    Edited by: Csaba Szommer on Dec 28, 2011 10:43 PM

    Hi Mario
    For ECR i have done the same and even that is Released and also Status with ECO. but still System is showing the same.
    Mario one more thing i have written on SDN pl have a look on Followup material , i have read about your post MRP-MPN.
    we are also having the scenario of alternate Material Within the Bom and also wnat to be correct the Procurement Proposal.
    how it will be helpfull by the MPN-MRP Set function.  i am also searching the same thing into Follow up Material . pl have a look on that.
    yours reply will be highly appericiable...
    Rgds
    Pankaj Agarwal

  • BOM Component changes when changes done in VC

    Hi All,
    When ever we are changing the characteristic values in Variant configuration, it result the component changes in the BOM.
    Please any body let us know how to find the what are the component changes in the BOM when we change any characteristic value in VC. Is there any FM or it will store in any table?
    Regards,
    Vasu.

    Sure Vasu,
    Find explanation on  this as below :
    BOM components are selected by making use of a special type of dependency called SELCETION CONDITIONS.
    If you want to find which BOM components will be selected on selecting which characteristic value, then follow the below given procedure :
    1. goto T.Code CS03.
    2.enter BOM header name , plant etc. and press enter.
    3. now you are in inside BOM.
    4. Select any BOM component for which you want to check when will it be selected during configuration.
    5. then, in top menu , choose  Extra --> Object Dependencies --> Assignments
    6. It will display all Object Dependencies assigned to that BOM component.
    7. Select the Dependency with type Selection Condition.
    8. Click on Dependency editor.
    9. It will show you the Dependency code
    10. when the condition as per this code is satisfied, the component is selected during configuration.
    Please revert back if you have any doubt.
    Reward Points.
    Regards,
    Gaurav Raghav.

  • Mass change of BOM item and BOM item catergory

    Hello Everyone,
    I have a need to complete a mass change of a BOM item with another, usually I use transaction CS20,this works o.k. but this time I'm also changing the material with a new item catergory, for example a stock item with a phantom item.
    Does anyone have an idea how to complete this task.
    Kind Regards
    Frankie

    Hello,
    Thankyou very much for your reply.
    I did try adding the new material using CS20 but all the BOM qty's are different and as you know you have to complete this field, so it would mean changing one at a time, I attacked this issue from a different angle and created an LSMW so I can Mass delete the parts but then use this program to change the BOM item to the new part.
    Thanks again for your reply
    Kind Regards
    Frankie

  • Add component to 200+ BOMs

    Hi,
             I want to add a single component to over 200 BOMs. Is there any mass change transaction ? I tried the CEWB but cant seem to figure out how to use it to add a single component to many BOMs.
    Thanks
    GS

    >
    GS wrote:
    > ok dudes, I am not getting a firm answer still.
    >
    > Can CEWB be used or not ? Whether LSMW or BDC is better is a later discussion.
    >
    > Also to use CS20 I need to specify a common component which would need to be replaced by this new component. I DO NOT have a common component in the 200+ BOMs. So where do I put the list of 200+BOMs to be updated ?
    >
    > Thanks
    > GS
    GS,
    1. CEWB cannot be used to mass add a Components to Multiple Material BOMS.
    CS20 if none of the BOM components are common for all 200, may be you can try to group them based on common materials and then try to run CS20 multiple times to complete your task.
    Final option is as described earlier LSMW and BDC.
    Regards,
    Prasobh

  • While trying to change a BOM with transaction CS02, a runtime error appears

    While trying to change a BOM with transaction CS02, a runtime error appears.
    In intial screen he entered material ,plant BOM usage and date valid from  after executed then id displayed item list in that he wantu2019s delete one item, he has been deleted selected item after that when he was saving he is getting runtime error
    Developer trace
    ABAP Program SAPLKED1_WRITE_CE4_BPS1                 .
    Source LKED1_WRITE_CE4_BPS1U01                  Line 30.
    Error Code SAPSQL_ARRAY_INSERT_DUPREC.
    Module  $Id: //bas/640_REL/src/krn/runt/absapsql.c#17 $ SAP.
    Function HandleRsqlErrors Line 775.
    RABAX: level LEV_RX_STDERR completed.
    RABAX: level LEV_RX_RFC_ERROR entered.
    RABAX: level LEV_RX_RFC_ERROR completed.
    RABAX: level LEV_RX_RFC_CLOSE entered.
    RABAX: level LEV_RX_RFC_CLOSE completed.
    RABAX: level LEV_RX_IMC_ERROR entered.
    RABAX: level LEV_RX_IMC_ERROR completed.
    RABAX: level LEV_RX_DATASET_CLOSE entered.
    RABAX: level LEV_RX_DATASET_CLOSE completed.
    RABAX: level LEV_RX_RESET_SHMLOCKS entered.
    RABAX: level LEV_RX_RESET_SHMLOCKS completed.
    RABAX: level LEV_RX_ERROR_SAVE entered.
    RABAX: level LEV_RX_ERROR_SAVE completed.
    RABAX: level LEV_RX_ERROR_TPDA entered.
    RABAX: level LEV_RX_ERROR_TPDA completed.
    RABAX: level LEV_RX_PXA_RELEASE_RUDI entered.
    RABAX: level LEV_RX_PXA_RELEASE_RUDI completed.
    RABAX: level LEV_RX_LIVE_CACHE_CLEANUP entered.
    RABAX: level LEV_RX_LIVE_CACHE_CLEANUP completed.
    RABAX: level LEV_RX_END entered.
    RABAX: level LEV_RX_END completed.
    RABAX: end RX_RFC
    In sm21
    Perform rollback
    Run-time error "SAPSQL_ARRAY_INSERT_DUPREC" occurred
         Short dump "090618 110101 donalda 11557 " generated
    Runtime Error          SAPSQL_ARRAY_INSERT_DUPREC
    Exception              CX_SY_OPEN_SQL_DB
           Occurred on     18.06.2009 at   11:01:01
    The ABAP/4 Open SQL array insert results in duplicate database records.
    What happened?
    Error in ABAP application program.
    The current ABAP program "SAPLKED1_WRITE_CE4_BPS1" had to be terminated because
    one of the
    statements could not be executed.
    This is probably due to an error in the ABAP program.
    What can you do?
    Print out the error message (using the "Print" function)
    and make a note of the actions and input that caused the
    error.
    To resolve the problem, contact your SAP system administrator.
    You can use transaction ST22 (ABAP Dump Analysis) to view and administer
    termination messages, especially those beyond their normal deletion
    date.
    Error analysis
    An exception occurred. This exception is dealt with in more detail below
    . The exception, which is assigned to the class 'CX_SY_OPEN_SQL_DB', was
    neither
    caught nor passed along using a RAISING clause, in the procedure
    "RKE_WRITE_CE4__BPS1" "(FUNCTION)"
    Since the caller of the procedure could not have expected this exception
    to occur, the running program was terminated.
    The reason for the exception is:
    If you use an ABAP/4 Open SQL array insert to insert a record in
    the database and that record already exists with the same key,
    this results in a termination.
    (With an ABAP/4 Open SQL single record insert in the same error
    situation, processing does not terminate, but SY-SUBRC is set to 4.)
    How to correct the error
    The exception must either be prevented, caught within the procedure
    "RKE_WRITE_CE4__BPS1"
    "(FUNCTION)", or declared in the procedure's RAISING clause.
    To prevent the exception, note the following:
    Use an ABAP/4 Open SQL array insert only if you are sure that none of
    the records passed already exists in the database.
    You may able to find an interim solution to the problem
    in the SAP note system. If you have access to the note system yourself,
    use the following search criteria:
    "SAPSQL_ARRAY_INSERT_DUPREC" CX_SY_OPEN_SQL_DBC
    "SAPLKED1_WRITE_CE4_BPS1" or "LKED1_WRITE_CE4_BPS1U01"
    "RKE_WRITE_CE4__BPS1"
    If you cannot solve the problem yourself, please send the
    following documents to SAP:
    1. A hard copy print describing the problem.
       To obtain this, select the "Print" function on the current screen.
    2. A suitable hardcopy prinout of the system log.
       To obtain this, call the system log with Transaction SM21
       and select the "Print" function to print out the relevant
       part.
    3. If the programs are your own programs or modified SAP programs,
       supply the source code.
       To do this, you can either use the "PRINT" command in the editor or
       print the programs using the report RSINCL00.
    4. Details regarding the conditions under which the error occurred
       or which actions and input led to the error.

    Hi ,
    you are getting beacuse u are trying to do mass update to database.
    Please check that below note are applicable to your system.
    Note 453313 - DBIF_RSQL_ERROR_INTERNAL for mass insert
    Note 869534 - AFS MRP doesn't work properly with all BOM item categories
    Thanks Rishi Abrol

  • Delete a component in the BOM

    Hi,
    I have created a BOM for SD (one material with some component)
    Do I have a choice to delete one component for one day in the BOM (if this component is insufficient  or too late GR)  without change my BOM for the future days?
    where can I do it in th eBOM or in the sale order.
    Thanks

    Dear,
    I hope the situation is you have sales order and for that sales order you have a production order
    Decide in which in production order you donot want to withdrew the component and delete that component in production order. When you confirm that component will not be issued.
    If you donot want to delte in Production order, then during confirmation itself...goto goods movement screen and delete atht conmponent and save the confirmation.
    pl conme back if required

Maybe you are looking for