Mass creation of planned order

Hello,
is there a way to mass creat a planned order for a finished product? having same FG mat, plant and prod version.
Thanks

Dear
1.Goto MD61 with User parameters like Plant , Requirement type , Version and Planning Date .Then Select the Material Radio Buttion with FG item code .
2.Enter the FG qty as required in each month as demand
3.GotO MD02-Single Item ,Multi Level with indicator : NETCH , 2,1,3,3,2   and Execute the MRP to create the Planned order  for FG
4.Check the result in MD04
There is no SAP Standard Traction to Mass creation of  Planned Order .That is possible in Demand Creation and MRP run .
Regards
JH

Similar Messages

  • Reg:Bapi for mass creation of production order/confirmation

    Dear Experts,
    I wanted to know with the following BAPI is it possible to create Multiple production orders for different semifinshed Materials along with material availability check and other functions similar to CO01 transaction.
    I knew there are standard transactions for mass confirmation for production orders. But i need a confirmation on this BAPI . As i am planning to go-ahed with ,mass creation of production order creation / Order confirmation in single custom transaction.Need back flush activity even supported.
    BAPI_PRODORD_CREATE to create the orders.
    BAPI_PRODORD_RELEASE to release the orders.
    BAPI_PRODORDCONF_GET_TT_PROP to get the default data for the confirmation.
    BAPI_PRODORDCONF_CREATE_TT to ost the confirmation of production order.
    Along with this BAPI do i need to commit any other BAPI to carry out back flush for components.
    Need your suggestions to take it further.
    Regards,
    Daya.

    Dear SAP Daya
    If the issue has been solved, please close this thread.
    You have already mentioned that the issue has been resolved, thefore, you should not ask for help on another thread before closing this one, as it looks like you are trying to force people to answer your threads.
    Users are always trying to answer as many threads as possible on good will we don't need this kind of "incentive".
    Please read carefully the The SCN Rules of Engagement, especially point 8:
    Be responsive. If an SCN member has answered your question, please mark the answer as "helpful” or “correct”. Mark the discussion as “answered,” so that other members can find the answers more easily
    Also, I checked your old threads and I could observe that there is only one closed. Please review your old threads and close those already solved.
    BR
    Caetano

  • Automatic Creation of Planned Order in PPDS Horizon

    Dear Experts,
    Kindly answer my following query.
    I have created PIRs before/inside my PPDS Horizon (its also falling outside horizon as SNP horizon is shorter than PPDS Horizon). If I check the PIRs created by me in /SNPAPO/RRP3, it also shows me planned orders corresponding to them. However, if I create PIR outside PPDS horizon then system is not automatically creating the planned order.
    Kindly let me know which master data/configuration setting is responsible for automatic creation of planned orders within PPDS horizon.
    Best Regards
    Rinju
    Edited by: Rinju Mukherjee on Sep 26, 2010 10:05 AM

    Dear Rinju,
    Check in Product Master PPDS view the Planning procedure maintained? if it is balnk check in the heuristic, the palnning procedure maintained.
    Since automatic planning procedure(3) is maintained, that is the reason it is creating order proposals, it self.
    Sree

  • Block the creation of planned order

    Dear experts
    How can I control the creation of planned order? I want to block the creation of planned order if the BOM or routing is not exist.
    BRs

    Hi,
    I think this can be done using 'Material status' try the following and let me know if it works.
    Create a new material status in transaction OMS4 (like R1 - "Created but BOM and Routing not maintained" )and in the details screen select Option "B" for MRP messages.
    You designate a material as a "R1 -Created but BOM and Routing not maintained" In the master record.
        MRP                          "B" = warning
    Please try this and let me know the result.   
    Regards,
    Prakash

  • APO: RRP3 automate Production order creation from planned order ?

    Hi everyone ,
    I have got a business requirement in APO where in Open sale orders uploaded in R/3, needs to be converted to Planned order and subsequently to Production order in APO-PPDS tcode RRP3 at all stages. They want to automate this process rather than doing it
    manually.
    Can anyone tell how is this possible . Any BAPI or function module available to do this . Please help.
    Regards,
    Syed

    Hi,
    1.You need to run the heuristics Planning of standard lots SAP_PP_002  in /SAPAPO/CDPSB0 by specifying the time profile
       and  strategy profile, planning version and propagation range, product and location.
    2. Convert PPDS Planned Orders created to process orders thru /SAPAPO/RRP7 by specifying the product location start date of the order for production order creation.
    Out put of step 1- For sales order requirement, PPDS Planned orders gets created.
    Out put of step 2- PPDS Planned orders are converted to production orders.
    Thanks,
    nandha

  • Manual creation of planned order in REM

    Hi, 
    Can we manually create a planned order in repetitive manufacturing? I know that in case we run MRP , then planned order for finished is created with order type 'PE' due to which it cannot be converted to production order.
    I dont want to run MRP , still can i create a planned order manually with the same order type 'PE' ? I tried in MD11, but not getting option to chose PE as it is not available  in F4 of planned order profile.
    Please help..
    Regards.

    Dear,
    You cannot create a planned order with PE order type manually, because a planned order of REM related material gets order type "PE" only when it is assigned with a Production Version.
    So achieve manual creation of REM Planned order with PE type with the following options,
    I - Using MD11 transaction create a planned order with LA type and assign a suitable REM related Production version to the planned order during creation itself, now this order would automatically become "PE" order type on saving the order.
    2. In the planning table using MF50, you can directly create a planned order for a production line using F7 key.
    Regards,
    Prasobh

  • Unit of measure - rounding off during creation of planned order

    Dear All,
    We have defined one material OIL in MM41 and its UoM is EA also we have put alternative UoM is L(liter).
    now we create BOM of semifinished material we use this oil as a component and enter its value in decimal points.
    e.g 0.375 EA
    During planned order creation or REM backflush system convert this quantity to 1 EA ,WE dont want this automatic conversion .
    We have uploaded all master data in production and now it is very difficult to change all BOM
    So what is the solution of this that system can not convert qty (rounding off).EA
    Kindly reply
    Sunil

    Hi Sunil,
    IN CUNI Transaction Field Decimal Places is for displaying the decimals,there is a decimal place Rounding off field below,there try to maintain 3 decimals and check whether it is working.
    One more thing is Unit EA will be used always as non decimal unit,But i dont know in your buisness how for unit EA there is a decimal qty
    Edited by: Girish  Adaviswamy on Mar 2, 2010 10:59 AM

  • Not scheduling on manual creation of planned order

    Creating planned order through MD11 and noticed there scheduling not done and capacity planning not done and on doing scheduling manually dates altered and capacity planned which are appearing in CM01 for the respective week
    Planned order created through MRP are fine with scheduling an capacity planning .
    Please let us know what could be a reason for not updating on manual creation.

    Hi
    This is standard behavior of SAP as when you create the planned order through MD11 manually , you need to do the detailed scheduling manually by executing schedule in Edit>Schedule.
    Check this thread:
    Need Automatic Lead-time scheduling in Planned Order using MD11
    Regards,
    Anupam Sharma

  • Setting nedded for creation of Planned Order for Dependent Requirement.

    Hi PP Gurus,
    I have a one material for which I m running MRP which have three Components.
    I m using strategy 10 for FG and SFG also.
    When I m running MRP for FG the system is creation planned order for FG, but not for SFG even though no stock available for them.
    I m using lot size EX for all SFG.
    Please Help.
    Thanks in Advance.

    Dear ,
    You should maintain proper MRP related parameters for both FG and SFG.Check all the MMR parameters :
    1.MRP Type -PD for FG/SFG
    2.Procurement Type -E  for FG/SFG
    3.Planning Startegy -10  in FG
    4.BOM/Routing Explosion -Keep it Blank
    5.Indiviaul/Collective Indicator -not applicable as it is MTS  so keep it blank
    6.Validity of BOM /Routing should be corrcet before MRP run in MD02-NETCH , 2,1,3,3,2
    7.What is the Lot Sizing Set up-EX in OMI4-Scheduling Tab -Requirement date =Delievery Date and BOM Validity Date  .
    Ref .Re: MRP not plalned for dependent components
    8.Check in MRP4 -MRP Dept Requirement Parametre should be balnk for plalling the SFG  in MMR of FG -MM02
    I hope this issue may be with BOM explosion as per the validity and lot size -schedueling set up .
    Hope this will be useful
    Regards
    JH

  • Mass Processing of Planned orders

    Hi all,
    We can do mass availability check for the planned orders and we can firm the planned orders for which the materials are available through COHV but can we have a output log after the mass processing so that we can see the list of planned orders got firmed and for any other messages.
    Regards
    Kumar

    Dear,
    In COHV or COMAC.
    in mass processing gtab page
    select function = material availability check, execute it.
    In selection tab page
    Plant
    Order type
    System status - MSPT.
    Or
    Start the report PPCOXPR1 with the T.code SE38
    Then try with Tcode CO24..
    Regards,
    R.Brahmankar

  • Reg. Mass update of Planned order components

    HI all,
    I have a requirement wherein I will come to know the raw material consumption from storage location only at the time of production.
    Now what I am doing is before doing confirmation I am updating the storage location for particular component in the planned order change mode - md12.I am doing this because the  production confirmation is happening at External system and transferred via IDOC to SAP.So I cant add the sloc at that time.
    I am doing the changes to planned order one by one. On an average I am doing this for say 50 Planned orders which is time consuming
    Is there any option available in SAP to do mass change to the planned order components.
    Regards,
    MBN.

    Hi MBN,
    You can use the LSMW, BDC program or FM MD_PLDORD_CHANGE_COMP_ITEMS to update the storage location in planned order components.
    Regards,
    R.Brahmankar

  • Issue in creation of Planned Order

    Hi all,
    There is a customer requirement on 08.02.2010 and there is shortage quantity as we don't have enough stock in the warehouse to cover the cust req. So when I run the MRP, planned orders are not getting created on 8th. Can you please tell me what could be the reason?
    Regards,
    Brijesh

    Hi,
    Are you saying that the planned order is not getting created at all or is it being created for an earlier date?
    If it is not being created at all, check in your sales order, whether the schedule line category is CP i.e. MRP relevant & in MD04 you notice the demand. Also check if the material is MRP planned & has a planning file entry (check using MD21, if no entry, make an entry via MD20).
    If it is being created, but at an earlier date, then check the lot sizing procedure. It could be that the lot sizing procedure is weekly or monthly & system has combined the needs & put a supply proposal at an earlier date.
    Check the above & revert with additional info if it does not resolve the issue.
    Regards,
    Vivek

  • Error while mass conversion of Planned order to production order

    Hi All,
    Thanks in Advance for help. We are facing one issue since Oct-2011.
    We have set up batch jobs for early morning to convert planned orders in to production orders. This is set up for transaction COHV.
    We have both MTO and MTS scenario.
    But problem occurs in Make to Order (MTO) scenario.
    Error comes in ST22 as   " SAPSQL_ARRAY_INSERT_DUPREC"
    *..Reservierungsköpfe inserten
      IF NOT rkpf_i[] IS INITIAL.
        INSERT rkpf FROM TABLE rkpf_i.
      ENDIF.
    Note : This error is not coming on consistent basis, it comes randomly. Secondly we are not aware of the reason/root cause of this error, hence not able to replicate error at all on Quality server.(Quality is backup of production till nov-2011)
    Writing to SAP, they debugged and provided note 504255. A part of that note says "Remember that this note describes a MODIFICATION which differs from
    the standard behavior of the system. Therefore, the customer assumes
    the responsibility for the implementation of this source code
    change. Due to this reason, SAP AG does not provide any support or
    maintenance for the changed source code."
    Hence client is reluctant to implement that note.
    Can any one help us out on
    1) What can be the cause of error as mentioned above?
    2) Resolution apart from SAP note?
    Best regards,
    Ravi Davda

    Hi Ravi,
    I am also facing same kind of issues from past couple of months.
    Sometimes this issue come up as sales order credit ststus is not approved and some times it happens due the following error INSERT rkpf FROM TABLE rkpf_i..
    I am also looking for some permanent solution.And today I have also faced same error and will be converting it manually.
    And can you tell for which client you are working?And if you find any solution for this please update me
    Regards
    Punjabi

  • Automatic creation of planned order in APO

    Dear Gurus,
    I originally posted this in PP and SD, however, it does now seem to be APO related.
    Hence my posting here. Can you help? This is the question:
    "How can we prevent that APO immediately creates a planned order when the purchase requisition is put in the system.
    (apparently they set up the system as such that a flow then starts and automatically transforms the planned order into a production order).
    We want to prevent APO to automatically create a planned order from the purchase req, we only want a planned order at a later stage, i.e. the finalised purchase order.
    If a setting like this exists, can we activate this per plant?"
    Thanks!

    Hello there,
    The control that you mentioned can be maintained at a product level, which is more granular than what you have asked for. Refer to the PP/DS tab of the product master and you will find a filed for PP planning procedure, which determines various actions that PP/DS executes for a specifi type of event. There are standard planning procedures (procedures 1-9) and ofcourse you can configure your own procedures as well.
    The configurations here define if your dependents requirements have to created immediately or just a planning file entry has to be created or a product heuristic has to be started immediately or no action has to be taken!
    Refer to below link for more info:
    http://help.sap.com/saphelp_scm70/helpdata/en/c1/147a375f0dbc7fe10000009b38f8cf/frameset.htm
    Cheers,
    Kalyan.

  • Source determination not happening during PR creation from Planned order

    Hi Experts
    We have set up source determination and we have created a sourcelist of material and a vendor is fixed, there is a inforecord alos maintined,
    I am trying to convert a planned order from MD04 to a purchase requisition, the source is not being assigned for the PR, I am alos getting an  information saying that 'the material is defined for inhouse production'
    secondly if I click the 'Assign Source of Supply', then I am getting an error 'not possible to assign  a source of supply'.
    The material is a finished material 'FERT' with procurement key 'X' so in MRP an planned order gets generated for converting a PR or a production order.
    Note - I was doing this effectively in a differnt client without any proble.  I am unable to find what I am missing, please sugest.

    Nagaraj Chaganti wrote:
    Thank you everyone for the suggestions,  The issue is resolved by testing with a new material with tproper master data.  Basically the problem occured when some user created additional inforecord for the same P,Org hence there was no automatic source detemination happening.
    >
    > Bye with regards.
    a second info record may explain that AUTOMATIC source determination ddid not work but it does not explain the error messagees you described earlier.