Mass Processing of Planned orders

Hi all,
We can do mass availability check for the planned orders and we can firm the planned orders for which the materials are available through COHV but can we have a output log after the mass processing so that we can see the list of planned orders got firmed and for any other messages.
Regards
Kumar

Dear,
In COHV or COMAC.
in mass processing gtab page
select function = material availability check, execute it.
In selection tab page
Plant
Order type
System status - MSPT.
Or
Start the report PPCOXPR1 with the T.code SE38
Then try with Tcode CO24..
Regards,
R.Brahmankar

Similar Messages

  • Mass creation of planned order

    Hello,
    is there a way to mass creat a planned order for a finished product? having same FG mat, plant and prod version.
    Thanks

    Dear
    1.Goto MD61 with User parameters like Plant , Requirement type , Version and Planning Date .Then Select the Material Radio Buttion with FG item code .
    2.Enter the FG qty as required in each month as demand
    3.GotO MD02-Single Item ,Multi Level with indicator : NETCH , 2,1,3,3,2   and Execute the MRP to create the Planned order  for FG
    4.Check the result in MD04
    There is no SAP Standard Traction to Mass creation of  Planned Order .That is possible in Demand Creation and MRP run .
    Regards
    JH

  • ESYU: Planner Workbench Release process가 다른 user로부터 planned orders를 release

    Purpose
    Materials Requirement Planning - Version: 11.5.9 to 12.1
    Information in this document applies to any platform.
    11.5.9 ~ R12 version:
    두 명의 users가 MRP Planner Workbench에서 Release를 위해 records updating을 진행하는 경우, 두 명 중 한명만이 update 후 실제로 release를
    submit 했으나 두 명 user의 모든 records가 release 되어 버린다.
    User1은 자신의 Planned Orders 만을 release 할 수 있고, User2 또한 자신의 저장된 Planned Orders 만을 release 해야 한다.
    STEPS:
    1. User 1이 MRP Planned Workbench로 log
    2. User 1은 특정 planner code를 위한 current planned order recommendations 을 찾는다.
    3. User 2가 MRP Planned Workbench로 log
    4. User 2가 특정 planner code를 위한 current planned order recommendations 을 찾는다.
    5. User1은 All for Release를 선택
    6. User2도 All for Release를 선택
    7. User1은 checking process를 끝낸 후 저장
    8. User2는 아직 checking process를 끝내지 못해 save를 아지 않은 상태로 남아 있다.
    9. User1이 [Release] button을 선택
    10. User1이 [Release] button을 선택시 User1과 User2에 의해 저장되거나 check 된 모든 planned order recommendations이 Work in Process와
    Puchasing modules로 released 되어 버림
    Cause
    이 issue의 원인은 현재 MRP planning의 경우 expected functionality 이다.
    MRP Workbench Release process는 모든 planner에 의해 check 되거나 저장된 모든 planned orders를 항상 release 한다.
    Bug 891669 : Enhancement Request
    PLANNER'S WORKBENCH SHOULD RELEASE ORDERS BASED ON PLANNER NAME NOT BY BATCH
    It is explained that this is current functionality in the following rejected Enhancement Request:
    Bug 891669 : PLANNER'S WORKBENCH SHOULD RELEASE ORDERS BASED ON PLANNER NAME NOT BY BATCH
    Solution
    Solution을 적용하기 위해 아래 steps을 실행:
    1. 모든 planner에 의해 check 되거나 저장된 모든 planned orders가 [Release] button에 의해 항상 release 되는것은 현재 MRP Workbench
    Release process에서는 correct functionality 이다.
    2. ASCP Planning의 경우엔 Planner/User에 의해 Release process가 아래 option에 의해 처리 가능하다.
    -- profile MSC:Released Only By User
    -- Standard MRP에서는 이 option은 사용할 수 없고 고려되지 않는다.
    Reference
    Note 311053.1

  • Mass Firming of planned order

    Dear gurus,
    I am looking for any tool by which i can make firming of collective planned order.
    Thanks,
    Das

    Hi Das,
    In SAPAPO itself, there are standard t-codes to carry out these options.
    1) /SAPAPO/RRP_SNP2PPDS - Conversion of Supply Network Planning -> Production Planning
    2) /SAPAPO/SNP2PPDS - Conversion of Supply Network Planning -> Production Planning in Background
    3) /SAPAPO/CDPSB0 - Production Planning Run  - To convert planned orders to production/process orders
    4) /SAPAPO/CDPSB1 - Production Planning Run in the Background - To convert planned orders to production/process orders in background.
    Regards
    R. Senthil Mareeswaran.

  • Reg. Mass update of Planned order components

    HI all,
    I have a requirement wherein I will come to know the raw material consumption from storage location only at the time of production.
    Now what I am doing is before doing confirmation I am updating the storage location for particular component in the planned order change mode - md12.I am doing this because the  production confirmation is happening at External system and transferred via IDOC to SAP.So I cant add the sloc at that time.
    I am doing the changes to planned order one by one. On an average I am doing this for say 50 Planned orders which is time consuming
    Is there any option available in SAP to do mass change to the planned order components.
    Regards,
    MBN.

    Hi MBN,
    You can use the LSMW, BDC program or FM MD_PLDORD_CHANGE_COMP_ITEMS to update the storage location in planned order components.
    Regards,
    R.Brahmankar

  • Error while mass conversion of Planned order to production order

    Hi All,
    Thanks in Advance for help. We are facing one issue since Oct-2011.
    We have set up batch jobs for early morning to convert planned orders in to production orders. This is set up for transaction COHV.
    We have both MTO and MTS scenario.
    But problem occurs in Make to Order (MTO) scenario.
    Error comes in ST22 as   " SAPSQL_ARRAY_INSERT_DUPREC"
    *..Reservierungsköpfe inserten
      IF NOT rkpf_i[] IS INITIAL.
        INSERT rkpf FROM TABLE rkpf_i.
      ENDIF.
    Note : This error is not coming on consistent basis, it comes randomly. Secondly we are not aware of the reason/root cause of this error, hence not able to replicate error at all on Quality server.(Quality is backup of production till nov-2011)
    Writing to SAP, they debugged and provided note 504255. A part of that note says "Remember that this note describes a MODIFICATION which differs from
    the standard behavior of the system. Therefore, the customer assumes
    the responsibility for the implementation of this source code
    change. Due to this reason, SAP AG does not provide any support or
    maintenance for the changed source code."
    Hence client is reluctant to implement that note.
    Can any one help us out on
    1) What can be the cause of error as mentioned above?
    2) Resolution apart from SAP note?
    Best regards,
    Ravi Davda

    Hi Ravi,
    I am also facing same kind of issues from past couple of months.
    Sometimes this issue come up as sales order credit ststus is not approved and some times it happens due the following error INSERT rkpf FROM TABLE rkpf_i..
    I am also looking for some permanent solution.And today I have also faced same error and will be converting it manually.
    And can you tell for which client you are working?And if you find any solution for this please update me
    Regards
    Punjabi

  • Mass processing for inbound orders idoc's from file

    Hi Experts,
    I have an requirement wherein we need to process all the ORDERS idocs sent from a thrid party system to a particular folder in the SAP system. Now we use a custom programme which in turn calls fn module IDOC_INBOUND_FROM_FILE to process each file. Here if the fn. module IDOC_INBOUND_FROM_FILE hits an erroneous file (control record error) it issues abend message which causes to entire programme to exit leaving rest of the files in the folder unprocessed.
    Let me know if there is any other function module or way to tackle this issue so as to process all the files.
    Thanks & Regards,
    Jimmy.

    Add the exception ERROR_MESSAGE = 99 (or some other unique number) to the standard exceptions in the function module call in your custom program.  This will allow you to trap the error and continue processing.

  • Mass processing of sales orders

    Dear All,
    The scenario is, we need to remove the delivery block from the sales order and the sales orders are huge in number. So is there a easier way to do the same or the only option is to use the transaction VA02 and change each one.
    What is this VA14L for?
    Looking for some help other than MASS as the authorization to this transaction cannot be given to end users..
    Thanks & Regards,
    Arun

    Hi Arun,
    I think SAP wants to drive a point here. Industry best practices, probably do not allow for "closing eyes and releasing dely blocks for multiple orders at a time??!!!"
    I think you got it right - VA14L - and the only solace is: You can select a bunch of docs from this screen and press Edit Sales doc...icon. this will save you from opening each and every individual doc on your own - it opens VA02 of each sales order one after the other and you can maintain the values.
    Probably it is best addressed by reviewing the business requirement that lands up in a situation of huge orders getting into dely block...that's not the ideal situation to be, rite?
    The benefits of SAP lies in altering the business process to suit the appln rather than tampering the appln to suit the business process! hope, you agree with this one!
    Hope, this helps!
    Thanks,
    siva

  • Differemce between  PROCESS ORDER,PLANNED ORDER AND PURCHASE ORDER??

    what is th edifference between PROCESS ORDER,PLANNED ORDER AND PURCHASE ORDER ??? can any one explain with some examples?
    n.bhardwaj
    [email protected]

    Process Order:
    Process order / Production order are activities within a business, where the production planning team team creates to absorb costs / evaluate costs / and check against planned figures. There would integration between MM/FI/PP to create such orders and process.
    Planned Order:
    A request created in the planning run for a plant to trigger the procurement of a plant material for a certain quantity for a specific date.
    Purchase Order:
    A request or instruction from a purchasing organization to a vendor (external supplier) or a plant to deliver a quantity of material or to perform services at a certain point in time.
    Regards
    AK

  • Automatic Firmed Planned Order / Mass Change Planned Order

    Hi PP Gurus,
    My requirement is I want to make all planned order created from planning run will be automatically firmed. I tried several option :
    1. MRP type : P1, automatic create firmed planned order within planning time fence but for new requirement, planned order will be created after planning time fence date. Example planning time fence date lies on 20/10/2011
    PIR
    09/2011     3 pc
    10/2011     4 pc
    end of planning time fence date
    11/2011     5 pc
    run MRP
    Planned order firmed for month 9 and 10. for 11 is not firmed. But the problem is if PIR on month 10 is change from 4 to 6. the other 2 planned order will be created at end of planning time fence date.
    Is it possible for planned order created at appropriate date as requirement date ???
    2. Mass Change of Planned Order
    I browse the help SAP there is function module : MD_SET_ACTION_PLAF for mass changes of planned orders.
    http://help.sap.com/saphelp_46c/helpdata/en/9e/e84226c1c311d3b54a0004ac160649/content.htm
    I execute it with SE37 but i don't know what should i do with this function module after the next screen.
    In my mind, there will be selection screen for choosing which planned order will be perform firmed action.
    Any other idea to solve my requirement is welcome.
    Regards,
    Arman Lie

    Dear Arman,
    Use T.Code MD19 for firming the planned orders,also check MDBA for firming the planned order.
    For your first question let me check and revert back.
    Regards
    Mangalraj.S

  • Planned order scheduling mass update

    Hello all,
    Is there a way I can change the scheduling dates for the planned orders collectively. (not MD16) ?
    Thankyou

    Hi,
    check the following
    Mass Changes of Planned Orders (Action Control)
    Use
    You can use this function to execute one or more actions for a large number of planned orders simultaneously. This is possible both within the SAP System and over an interface from an external assembly control system.
    Features
    SAP supplies the function module MD_SET_ACTION_PLAF for action control.
    This function module includes the following actions:
    Explode BOM
    Explode BOM, check availability
    Check availability, only explode BOM in the case of a requirement
    Check availability, do not explode BOM
    Reset availability
    Change planned order data
    Schedule planned order
    Delete planned order
    Confirm planned order (in repetitive manufacturing)
    Firm planned order data
    Firm planned order components
    Print component overview
    In connection with an action, you can always change planned order data, for example; order quantity, dates or production version.
    The function module also enables you to program further customer-specific actions.
    You can execute the actions for several planned orders simultaneously.
    You can create action chains, that means, have the system execute several actions in a single operation.
    Activities
    Define your own actions and program a report that includes these actions. As an example of this, the transaction MDAC Execute action for planned order (MRP ® Planned order ® Execute action) is available.
    In this example action, you can use actions only for individual planned orders. Nor can you form action chains, only simple action transitions are possible.
    Determine an action key and action controls in Customizing for MRP in the IMG activities Define action key and Define action control. An action key describes the actions that can be executed for a planned order. Action controls determine which actions are allowed and in which sequence they are to be executed.
    Assign the key for the respective action control to the materials in the material master (MRP 4 view).
    Regards,
    nandha

  • Conversion of planned orders to production orders

    Hi,
    we are doing mass conversion of planned orders to production orders and performing capacity availability check, how system will give log information based on these two things,
    when i perform availability check at time of order creation and will not allow to create if anything is missing (i selected user decides option in configuration), does it show any error log report and where can i see.
    When i perform availability check at time of release, if anything missing it will not allow to release and give a choice for a user to release in normal production order creation process, how it will work in mass conversion. is there any standard report to look at missing planned orders so that users will come to know and then decides whether to convert to production order or not.
    thanks in advance.

    Dear ,
    In SM38-Enter PPBICO40 -Execute -Here you need to Mark the Output log option with Erros only or Error Folder for each MRP controller  .Frist you do it in test mode and then remove test mode , mark the Output log option as per requured field and check the result .
    refer this useful thread : Program PPBICO40 for conversion of planned orders to production order
    Regards
    JH

  • Conversion of planned orders to prod orders in background

    hi All
    Is there any program for mass conversion of planned orders in production orders which we can schedule in background.
    Amit

    Hi Amit,
    Try below method
    TCode: COHV (tab selection --- plant and etc...,, tab mass processing --- function - conveted planned order, order type - PP01, collective orders - do not collective orders)
    after Menu -- Program --- Excute in background -- set properties -- to set send SAP spooler --- click button immediate then check box periodic job and periodic values after save
    to monitor and get spool request bcackground this job
    TCode SM37
    or
    you can create background job using TCode SM36
    pls create varient for COHV
    PRG: PPIO_ENTRY with Varient
    Regards,
    Sankaran

  • User exit/ badi needed for planned order create/change,collective ATP check

    Dear All,
    I'm looking for a user exit/ badi which can be used for planned orders at the stage of
    mass collective availability check (COMAC tcode) update; or at some other relevant stages of mass update of planned orders.
    I need after collective availability check to perform the following:
    1) to copy date from "total comitment" field on header tab of planned order and paste it (replace old date) to order finish date on header screen
    then
    2) to start a scheduling.
    Very appreciate your help.
    Best Regards,
    Andrey
    Edited by: Andrey Kruglov on Apr 15, 2010 3:06 PM
    Edited by: Andrey Kruglov on Apr 15, 2010 3:07 PM

    Dear,
    Use the BAPI : BAPI_PLANNEDORDER_CHANGE
    Or use the function module MD_SET_ACTION_PLAF for Schedule planned order.
    and the transaction MDAC Execute action for planned order
    This function module includes the following actions:
    Explode BOM
    Explode BOM, check availability
    Check availability, only explode BOM in the case of a requirement
    Check availability, do not explode BOM
    Reset availability
    Change planned order data
    Schedule planned order
    Delete planned order
    Assign the key for the respective action control to the materials in the material master (MRP 4 view).
    Please refer this thread,
    Re: MDVP for collective orders
    Regards,
    R.Brahmankar

  • Planned Order to Purchase Order report in SAP

    Dear All
    The Business process is Planned Order - Converted to Purchase Requsition - Converted to purchase order .
    Is there any report in SAP , which shhows the direct link between Planned order to Purchase Order ?
    Regards
    Shyam

    I have never seen a standard report, build a query based on tables PLAF, EBAN and EKET should be involved

Maybe you are looking for

  • Error: Insufficient permission on the folder in which the format is to be s

    Hi Experts, I have two users A and B. Now A is sharing a OLAP worksheet with B and getting following error. oracle.dss.d4o.common.D4OException: D4O-1209 Insufficient permission on the folder in which the format is to be saved. oracle.dss.bicontext.BI

  • How to make use of *progress bar*?

    I have a progress bar requirement in my swings project, i.e on clicking a button, some task should be executed and in parallel to this progress should run on progress bar in the same frame and soon after this task gets completed the progress on progr

  • GWI - All Business Transactions by Process Type (MESG) - Multiple Types

    Dear sir or madam, We have implemented SAP not 686880 to synchronize only one process type to Outlook (appointment). Currently, we have the requirement of the sales department that also tasks should be synchronized to Outlook. Since we are not using

  • How to create instance in linux

    Hi guys how to create instance in linux? I know that in order to create a instance in window, we can use oradim cmd. But what about linux?

  • EPS files open with unusual line slices

    We have roughly 4500 eps files that were created in freehand years ago. The files contain both raster images that were embedded as well filled vector paths which were created in freehand. The embedded raster image opens flawlessly as wells as some of